233
|
Wed Mar 17 09:25:27 2010 |
Damien Gallop | | | 20Ne1+ at 40.8keV for accelerator commissioning | 20Ne1+ set up from the MWS and handed over
to Sophia & Marco for accelerator recommissioning.
Strip to 5+ at M:5. First day of beam. Happy |
  |
232
|
Fri Mar 12 11:35:34 2010 |
Keerthi | | | Cusp water cooling | Cusp source water cooling (#4) interlick
does not work. |
|
231
|
Fri Mar 12 11:33:09 2010 |
Keerthi | | | IOS:IG! | IOS:IG1 is faulty. Need to replac it during
next earliest window. |
|
230
|
Thu Mar 11 23:02:18 2010 |
Keerthi | | | OLIS status after shutdown | Microwave source is up and running.
Supernanogan: grounding rod is stuck,
RF generator does not clear the interlocks |
|
229
|
Fri Feb 19 17:54:40 2010 |
Damien Gallop | | | OLIS Shutdown in progress | Partial disassembly of DB1 optics today.
Shielding of insulators is definitely working
and indicated for unshielded insulators. |
 |
228
|
Wed Feb 17 18:28:33 2010 |
Damien Gallop | | | OLIS Shutdown in progress | More materials prepared for optics refit. |
|
227
|
Tue Feb 16 16:04:18 2010 |
Damien Gallop | | | OLIS Shutdown in progress | Preparations for rewiring the DB1/3 optics
have begun. Sgan gas manifold work is in
progress. Note: IOS:MP1 is scheduled for |
|
226
|
Fri Feb 12 14:42:06 2010 |
Damien Gallop | | | OLIS Shutdown in progress | Supernanogan cart removed from Faraday
cage to dock today. Some beam safety tests
on FC6 in progress presently. FC3 was already |
8x |
225
|
Wed Feb 10 17:18:24 2010 |
Damien Gallop | | | OLIS Shutdown in progress | OLIS Shutdown has been in progress for
a week. IOS is vented, was swiped clean and
opened. DB3 was craned out, a precision job. |
|
224
|
Wed Feb 3 16:30:02 2010 |
Damien Gallop | | | OLIS Shutdown began today | We prepared stuff last night. This morning
we vented IOS to argon, then swiped. Clean.
Lu and Ajit craned out DB3 for us. Nice job, |
|
223
|
Tue Feb 2 10:06:41 2010 |
Damien Gallop | | | Supernanogan development wind-up | We ran 32S5+ overnight. Keerthi has been
working with the new surface source oven
for the last couple of weeks. His results |
9x |
222
|
Fri Jan 15 15:30:02 2010 |
keerthi | | | Supernanogan oven start up | Voltage
Current
MCIC:IG1 |
|
221
|
Thu Jan 14 09:57:05 2010 |
Damien Gallop | | | 20Ne1+ beam from MWS for 8pi diagnosis | Beam is on for 8pi diagnosis by special
request.
We set up beam in IOS yesterday. |
9x |
220
|
Wed Jan 13 18:16:22 2010 |
Damien Gallop | | | OLIS development with MWS at 28keV | We will be delivering a 28keV beam to the
tuning boys tomorrow for further diagnosis
of the 8pi line. In anticipation, I restarted |
6x |
219
|
Mon Jan 11 17:46:31 2010 |
Damien Gallop | | | OLIS development for 4He2+ beam loose ends | OLIS was shut down over Christmas. We did
a "soft start" of the MWS last
Tuesday, after refurbishing and installation |
  |
218
|
Mon Jan 11 17:40:07 2010 |
Damien Gallop | | | Happy New Year! | Welcome to 2010. Shutdown is underway across
the site, while beam development is going
on at OLIS. |
|
217
|
Thu Dec 24 10:13:00 2009 |
Damien Gallop | | | OLIS development 20Ne1+ from MWS | The MWS stayed up flawlessly overnight.
Beam grew from about 2µA to over 5µA
this morning. Was it the pre-conditioning |
|
216
|
Wed Dec 23 11:09:37 2009 |
Damien Gallop | | | OLIS development | So... lots has happened.
* Supernanogan *
Heater components installed in plasma |
7x |
215
|
Mon Dec 21 10:22:33 2009 |
Damien Gallop | | | OLIS development for CUSP source - installation cont'd | Keerthi and Marco achieved visible 4He2+
through the RFQ on Friday (or so). Mass spec
attached. Development continues today. |
 |
214
|
Fri Dec 18 13:14:01 2009 |
Damien Gallop | | | OLIS development for CUSP source continued | Yesterday: Busy! Source filment changed
last night. Source pumped overnight. First
start this morning. |
9x |