  283   Mon May 31 09:18:39 2010 Damien Gallop  33S to DRAGON

Delivery of 33S6+ to DRAGON continues. A couple of RF tweaks done over the weekend. Source gas canister pressure at -20"Hg. MCIS pressure at 7.3e-8 Torr. At this rate, we could deliver 33S until approximately forever.

Attachment 1: Picture_2.png
Picture_2.png
  284   Tue Jun 1 09:12:39 2010 Damien Gallop  33S to DRAGON

33S6+ delivery to DRAGON continues. Looks like there was an RF tweak overnight. Source gas canister still at ~-20"Hg. MCIS vacuum at 7.4e-8 Torr.

Attachment 1: Picture_2.png
Picture_2.png
  285   Wed Jun 2 09:19:04 2010 Damien Gallop  33S to DRAGON

33S6+ delivery to DRAGON continues. It is Maintenance Day for everybody else today. Source gas canister pressure = -20"Hg. MCIS pressure = 7.7e-8 Torr.

  286   Thu Jun 3 09:29:11 2010 Damien Gallop  33S to DRAGON

33S6+ delivery to DRAGON continues until Saturday morning. All the signs are that beam is excellent. Source gas canister is still at ~-20"Hg, and MCIS vacuum is at 7.0e-8 Torr.

Attachment 1: Picture_1.png
Picture_1.png
  287   Fri Jun 4 09:30:48 2010 Damien Gallop  33S to DRAGON

Delivery of 33S6+ continues to DRAGON for the final day. Some online tuning of the line overnight. Source gas canister pressure remains at ~-20"Hg, and MCIS pressure is at 7.1e-8 Torr.

Attachment 1: Picture_2.png
Picture_2.png
  279   Tue May 25 22:02:41 2010 Keerthi Jayamanna  33S spectrum

33S spectrum is saved as 33S_spectrum.dat 

  453   Wed Oct 19 09:53:27 2011 Damien Gallop  33S from MCIS to HE Development Setup

MCIS configured for 33S+6 yesterday afternoon. Beam grew nicely overnight. Beam development expected after source hand-off.

Attachment 1: Picture_9.png
Picture_9.png
  447   Tue Oct 4 10:37:38 2011 Damien Gallop  33S from MCIS Source Development Setup

Beam development with 116Sn+18 finished last evening around 21:00. Source was off overnight. 33S material loaded into MCIS oven. Source pumped overnight.

Later... source is lit. 33S+6 on FC6 and growing.

Attachment 1: Picture_24.png
Picture_24.png
Attachment 2: Picture_25.png
Picture_25.png
  448   Wed Oct 5 10:11:28 2011 Damien Gallop  33S from MCIS Source Development

The source stayed up overnight. A little RF tweak, but 33S+6 beam still on FC6.

Later... IOS:MCOL3 slits calibration with beam in progress.

Attachment 1: Picture_1.png
Picture_1.png
  155   Fri Oct 9 16:33:45 2009 Keerthi  33S development

SO2 gas line is connected again. Leak hand valve is closed.

Intermediate section is pumping through source chamber.

CSB development is completed.

 

  275   Mon May 24 22:42:51 2010 Keerthi Jayamanna  33S development

Tried to see the background before 33S installation. Found few problems: MCIS:YCB1 does not hold more than 58V.

Very difficult to transport the beam without YCB1. Need to find a solution. Open and fix it is not an option even though we have a ready spare. It will take two weeks to get the vacuum back.

------------------------------

Outgoing TIGRESS experiment was the occasion for another ISAC milestone, 8MeV/u through the SCC for the first time just around midnight last Friday, May 21st. This also represented the first 8MeV/u beam to an experiment. And we can proudly say that OLIS beam was used. TIGRESS run ended at 08:30 as scheduled. Attached is a trar graph of beam on FC6, snapped periodically throughout the run. As before, you can see a small daily variation likely related to temperature of NA-LCW. There were reports of HPL tests this past Thursday and Friday. Evidently no effect over here.

 

Attachment 1: Picture_1.png
Picture_1.png
  278   Tue May 25 11:58:02 2010 Keerthi Jayamanna  33S dev

after 24 hours background spectrum saved as "BackgroungNo33S003.dat"

RF Amplitude :7.767 , RFoutput power= 5W, Output power (dB)=36.4

  281   Thu May 27 09:11:10 2010 Damien Gallop  33S Development and Handover

33S on FC6 overnight. Preparing to send beam to DRAGON now, and confirm isotope.

Source gas pressure gauge on canister = -20"Hg. MCIS pressure = 7.8e-8 Torr.

Attachment 1: Picture_2.png
Picture_2.png
  280   Wed May 26 18:16:10 2010 Damien Gallop  33S Development

Some 3enA of beam on FC6 presently. Let it sit.

Attachment 1: grab.Cm6004.png
grab.Cm6004.png
  276   Tue May 25 00:19:18 2010 Keerthi Jayamanna  33S

 

Finally got something going. YCB1 short to the ground. YCB common plate connected to YCB1 power supply. We were lucky. Polarity was right. Ran the source with no 33S.
Saved file as “backgroundNo33S.dat” No optics set yet. SO2 connected not open yet. 33S 17% is in the oven, but not heated yet.
  277   Tue May 25 11:28:00 2010 Keerthi Jayamanna  33D dev

after 24 hours background spectrum saved as "BackgroungNo33S002.dat"

RF Amplitude :1.553 , RFoutput power= 0, Output power (dB)=0  

  416   Fri Jul 22 15:56:08 2011 Damien Gallop  27Al+1 from MWS for DRAGON status

There have been teething pains developing a good 27Al beam. The Supernanogan sputter source ate through aluminum rods like candy. The MWS worked for a while, but would not hold a sustained plasma. IOS was opened a couple of times to clean the MWS. It ran for a while today, then blinked out. Leak checking is in progress. But the source looks pretty tight from that point of view.

Update at 16:30: Bob has declared EOB for the 27Al run. Next up next week: 22Ne2+, from MCIS if bias will hold comfortably at 22kV.

Attachment 1: Picture_7.png
Picture_7.png
  406   Wed Jul 6 09:56:45 2011 Damien Gallop  27Al+1 from MWS for DRAGON EOB

DRAGON has been taking beam since approximately noon on Monday, and finished a little while ago. Feedback I have received is that beam intensity was lower than experimenters' ideal, but quality of the beam was very good. I will run an emittance scan shortly. Then next up: Mg setup.

Attachment 1: Picture_4.png
Picture_4.png
Attachment 2: Picture_3.png
Picture_3.png
Attachment 3: Picture_5.png
Picture_5.png
Attachment 4: Picture_6.png
Picture_6.png
Attachment 5: Picture_7.png
Picture_7.png
Attachment 6: Picture_8.png
Picture_8.png
Attachment 7: grab.Qq4317.png
grab.Qq4317.png
Attachment 8: grab.jS4323.png
grab.jS4323.png
Attachment 9: grab.Vf4385.png
grab.Vf4385.png
Attachment 10: grab.gT4404.png
grab.gT4404.png
Attachment 11: grab.Bd4470.png
grab.Bd4470.png
Attachment 12: grab.XF4445.png
grab.XF4445.png
Attachment 13: grab.UT4495.png
grab.UT4495.png
  403   Wed Jun 29 15:49:16 2011 Damien Gallop  27Al+1 from MWS Setup

Switchover from 58Ni+1/MCIS to 27Al+1/MWS began just after noon. MWS cleaned and fitted with aluminum liners. Pumping in progress. Good leakup curve. All electrostatics checked and operational. Source should be conditioned to at least 55kV at some point. Let it sit at 30kV overnight with 100W on MW.

Attachment 1: grab.Q27242.png
grab.Q27242.png
  404   Thu Jun 30 10:02:08 2011 Damien Gallop  27Al+1 from MWS Setup

Source pumped overnight to previous baseline (red trace on attached Stripchart). IOPS conditioned it up to 42kV without a hitch.

Close Ne source gas line and pump out flow controller... noticeable improvement.

Bias conditioned up to 50kV.

Bias conditioning at 58.5kV with MW at 600W. Raising the RF outgassed the plasma chamber for the first while then went quiet again.

Bias set to 55.08kV for 27Al+1 run. Source lit around 14:30.

15:30: IOS:FC3 = 1.9e-5 (no bias); IOS:FC6 = 9.3e-9. It's coffee time.

16:40: IOS:FC6 = 4.9e-9 (attached)) after settling and a few little tweaks. We're just about ready.

16:45: Hand it over to ICR.

Attachment 1: Picture_2.png
Picture_2.png
Attachment 2: Picture_3.png
Picture_3.png
Attachment 3: Picture_4.png
Picture_4.png
Attachment 4: Picture_5.png
Picture_5.png
ELOG V2.9.2-2455