M9sol Logbooks Solenoid Daily log
  Solenoid logbook, Page 4 of 15  ELOG logo
IDdown Date Author Operational Mode Subject Text Attachments
  226   Fri Oct 5 13:25:41 2007 Doug PreddyQuench Recoveryfunny graph There was a fluctuation of the positive lead
temp with no flow going to 
the power leads.
 Capture.jpg 
  225   Fri Oct 5 10:25:43 2007 Doug PreddyQuench RecoveryUnknown quench 2Kevin and I were at the Sulzer panel when
the system quenched 2. No 
obvious reasons. Restarted the system.
  
  224   Tue Oct 2 13:02:37 2007 Doug PreddyNormal RunningPLC problemsWhile downloading new code for 2A PLC the
M9 and M15 vacuum systems were 
shut off. This is due to the two systems
  
  223   Thu Sep 27 07:41:15 2007 Doug PreddyStart UpSolenoid coldSolenoid cold and in series mode. 50% liquid
level. Starting flow to 
powerleads.
  
  222   Wed Sep 26 08:52:46 2007 Doug PreddyStart Upswitched to parallel cold return    
  221   Tue Sep 25 07:34:04 2007 Doug PreddyStart UpPIC229 to 11 baradjusted turbine speeds and HIC104 to maintain
their values.
  
  220   Mon Sep 24 15:08:41 2007 Doug PreddyStart UpStarted cool down this morningThe vacuum in the cold box was good on Friday
0.0 X 10-4. Let it pump over 
the weekend. Added two bottles of UHP helium
  
  219   Wed Sep 19 20:53:18 2007 Doug PreddyMaintenanceMore diff pump newsCold box pumped out to ~ 190 mTorr overnight.Leak
checked the pump again. 
Still leaks at dip stick.Tried resetting
  
  218   Tue Sep 18 18:48:11 2007 Curtis BallardMaintenancecold box leak checkThe leak check of the cold box diff pump fittings.
 Found a leak at the 
base of the diff pump on the tee that is
  
  217   Fri Sep 14 12:44:52 2007 Doug PreddyStart Upstarted compressorrunning purifier over weekend   
  216   Wed Sep 12 12:01:02 2007 Doug PreddyMaintenanceregenerated adsorberregenerated adsorber
replaced MV902 "ON" switch (used nitrogen
precooling on switch)
  
  215   Tue Aug 14 12:55:12 2007 Doug PreddyNormal RunningStrip tool savesThere are two strip tools saved:
coils
powerlead
  
  214   Tue Aug 14 10:15:22 2007 Doug PreddyMaintenanceSolenoid ramped downSolenoid ramped down and locked out for M9A
slits work.
  
  213   Mon Aug 6 08:41:31 2007 Doug PreddyQuench RecoveryCold box trip at 6:00compressor off due to cold box trip at 6:00
this morning. Restarted system 
and started flow to solenoid in parallel
  
  212   Tue Jul 31 07:53:57 2007 Kevin TrithardtNormal Runningcycled power leadsgot a page for the power lead temp
came down and cycled the power leads.. did
not seem to make a difference..
  
  211   Sun Jul 29 04:58:27 2007 Doug PreddyQuench RecoveryEnergizing solenoidLHe level~50%. Still have a slight ripple
in the power leads, but they are 
cold enough to power the solenoid. LHe_in
  
  210   Sat Jul 28 22:30:13 2007 Doug PreddyQuench Recoveryquench againrecovered system and energized solenoid at
about 6:00 this evening.
At 9:30 power lead temps quenched solenoid
  
  209   Sat Jul 28 15:45:17 2007 Doug PreddyQuench Recoveryquench recoveryThe solenoid tripped off this morning due
to pwer lead over temp. The 
compressor was also off. I restarted this
  
  208   Thu Jul 5 11:01:47 2007 Kevin TrithardtOtherCurrent lead warm upDue to curent lead temperature occilation
Doug recommended warming up the 
current leads.
  
  207   Thu Jul 5 03:04:50 2007 Doug PreddyNormal RunningPower lead problemsThe power leads temps are starting to cycle
again. Earlier today M9 
experimentor cycled HIC142 to stablize the
  