  2   Wednesday, September 14, 2011, 15:33 John WongTest#1HP-SISITWTM1testtestIn progresstesting elog for test stand

Wednesday, September 14, 2011, 15:33

blah blah blah...

  72   Monday, April 16, 2012, 11:16 Anders MjosNb#6LP-SISITWTM1  In progressVenting, purging cooling lines

Venting chamber and purging cooling lines in preparation for target removal

  73   Monday, April 16, 2012, 11:56 Anders MjosNb#6LP-SISITWTM1  In progressVenting, purging cooling lines

Anders Mjos wrote:

Venting chamber and purging cooling lines in preparation for target removal

 Monday, April 16, 2012, 11:55: Target removed. Cooling lines must be blanked off before pumping down.

  77   Friday, April 20, 2012, 08:56 Anders MjosNb#6LP-SISITWTM1  Problems/SolutionsInsulator stand-off failure

 When the target was removed from the test stand it was discovered that the custom designed insulator stand-off (ITD0400 made from Mycroy 1100) had swollen and become discoloured in the area exposed to "heat shine" from the target oven. See attached pdf for photos of the insulators.

The heat shield lid was opened up and the target temporarily removed to replace the two insulators that had failed. These were replaced with the commercially available glazed steatite stand-offs. The target had some marks from the insulators which was cleaned with acetone and methanol.

After replacing the insulators, the target assembly was assembled, leak checked and a new electrical check was performed.

 

Additional photos are available on DocuShare

Attachment 1: ITW-TM1-Nb#6-LP-SIS_-_TestStand.pdf
ITW-TM1-Nb#6-LP-SIS_-_TestStand.pdf
  101   Thursday, May 31, 2012, 15:43 Anders MjosTa#38LP-SISITWTM1  In progressTarget ready to be heated

Thursday, May 31, 2012, 15:42: Roughing

Thursday, May 31, 2012, 16:01 : Starting turbos

Thursday, May 31, 2012, 16:08 : Turbos at speed. Vacuum 1.7 E-5

Friday, June 01, 2012, 08:08: Cooling water opened. Vacuum stable at 5.7E-7. Target ready to be heated and biased.

  102   Friday, June 01, 2012, 12:23 Aurelia LaxdalTa#38LP-SISITWTM1  In progressHV & Heaters conditioning.

Did the HV conditioning.

Heaters conditioning in progress.

The Hall probe is not working: couldn't pass 35.5 units (readback) or 50.16 units (setpoint) at field -3710G.

Tried to turn ON/OFF magnet PS and to reboot Canbus, but nothing worked. Still waiting for E-Fault 6031 to be resolved.

Started cool-down.

  103   Monday, June 04, 2012, 10:51 Anders MjosTa#38LP-SISITWTM1  DoneVenting chamber

Aurelia Laxdal wrote:

Did the HV conditioning.

Heaters conditioning in progress.

The Hall probe is not working: couldn't pass 35.5 units (readback) or 50.16 units (setpoint) at field -3710G.

Tried to turn ON/OFF magnet PS and to reboot Canbus, but nothing worked. Still waiting for E-Fault 6031 to be resolved.

Started cool-down.

 Monday, June 04, 2012, 10:51: Turbos switched off

Monday, June 04, 2012, 11:06: Purging water. Venting.

Monday, June 04, 2012, 11:36: Target removed

  192   Friday, August 31, 2012, 13:59 Anders MjosNb#7LP-SISITWTM1  In progressNb#7 installed

Friday, August 31, 2012, 15:19: roughing

Friday, August 31, 2012, 15:39 : starting turbos

Friday, August 31, 2012, 15:44 : TP1B at speed

Friday, August 31, 2012, 15:48 : TP1A timed out

Friday, August 31, 2012, 15:48 : TP1A restarted. at speed.

Friday, August 31, 2012, 15:49 : both turbos at speed. Vacuum @2.7E-5

  193   Tuesday, September 04, 2012, 08:11 Anders MjosNb#7LP-SISITWTM1  DoneNb#7 installed

Anders Mjos wrote:

Friday, August 31, 2012, 15:19: roughing

Friday, August 31, 2012, 15:39 : starting turbos

Friday, August 31, 2012, 15:44 : TP1B at speed

Friday, August 31, 2012, 15:48 : TP1A timed out

Friday, August 31, 2012, 15:48 : TP1A restarted. at speed.

Friday, August 31, 2012, 15:49 : both turbos at speed. Vacuum @2.7E-5

 Tuesday, September 04, 2012, 08:10: Opened cooling water. Vacuum stable @ 2.2E-7

  197   Friday, September 07, 2012, 14:34 Anders MjosNb#7LP-SISITWTM1  Problems/SolutionsInsulator ITD0342 overheated - swelling

 See attached photo

Attachment 1: Nb#7_swelling_insulator.pdf
Nb#7_swelling_insulator.pdf
  200   Wednesday, September 12, 2012, 08:02 Anders MjosNb#7LP-SISITWTM1  In progressVenting

Wednesday, September 12, 2012, 08:01: Turbos off

Wednesday, September 12, 2012, 13:35: Venting, water off and purged.

Wednesday, September 12, 2012, 13:55: Vented

  201   Wednesday, September 12, 2012, 17:04 Anders MjosNb#7LP-SISITWTM1  In progressPumping down - w/replaced insulators

Replaced swollen insulator and added Ta heat shield on insulator.

 

Wednesday, September 12, 2012, 17:03: Roughing

Wednesday, September 12, 2012, 17:23 : Starting turbos

Wednesday, September 12, 2012, 17:32 : Turbos at speed

Wednesday, September 12, 2012, 17:33 : Vacuum at 3.2E-5

  202   Thursday, September 13, 2012, 08:24 Anders MjosNb#7LP-SISITWTM1  In progressWater on

Thursday, September 13, 2012, 08:16: Opened up cooling water. Vacuum (IG1) increased from 5.9E-7 to 6.2E-7 before returning to 5.9E-7. Similar response on IG6 (valve closed). Response is however similar to previous (short time ~5 min) vacuum fluctuations.

  204   Friday, September 14, 2012, 15:27 Anders MjosNb#7LP-SISITWTM1  DoneVenting

Target cooled down. Power supplies off.

Friday, September 14, 2012, 15:27: Turbos off.

Friday, September 14, 2012, 15:32: Water purged.

 Friday, September 14, 2012, 16:00: Venting

Friday, September 14, 2012, 16:26: Vented

  223   Thursday, October 25, 2012, 13:02 Anders MjosTiC#3LP-SISITWTM1  In progressPumping down

Thursday, October 25, 2012, 13:00: Roughing

Thursday, October 25, 2012, 13:19 : Turbos on

Thursday, October 25, 2012, 13:28 : Turbos at speed

Thursday, October 25, 2012, 13:29 : Vacuum at 1.6E-5 T

  224   Friday, October 26, 2012, 08:29 Anders MjosTiC#3LP-SISITWTM1  DoneTarget ready for conditioning

Anders Mjos wrote:

Thursday, October 25, 2012, 13:00: Roughing

Thursday, October 25, 2012, 13:19 : Turbos on

Thursday, October 25, 2012, 13:28 : Turbos at speed

Thursday, October 25, 2012, 13:29 : Vacuum at 1.6E-5 T

 Friday, October 26, 2012, 08:29: Opened water. Vacuum stable at 1.8E-7 T

  225   Thursday, November 01, 2012, 11:16 Aurelia LaxdalTiC#3LP-SISITWTM1   TiC#3-LP-SIS Startup

Did the HV conditioning for the TiC#3 up to 30kV.

Heaters ramp up in progress.

  226   Thursday, November 01, 2012, 14:57 Aurelia LaxdalTiC#3LP-SISITWTM1   TSH:TGHT readback stopped at 264.5A (for a higher setpoint)

The TSH:TGHT stopped at 263.7A, but the setpoint is still ramping (now at 421A). The voltage is set correctly: have 6.238V setpoint and 4.386V readback. The reading on the Power Supply shows 418A. Through the window the target assembly looks at high temperature. The readback on Epics seems stuck. E-Fault for Controls 6389

  227   Friday, November 02, 2012, 14:20 Aurelia Laxdal LP-SISITWTM1   Mass scan done

Mass scan file: plotdump-local-clean.txt Nov2 12 13-15-59.txt

The scan was taken at TGHT=573A (read from the PS panel) .

The TBHT = 230A

  228   Friday, November 02, 2012, 15:40 Aurelia Laxdal LP-SISITWTM1  DoneSiC#3 cooldown started

Started the cooldown for SiC#3.