877
|
Monday, June 07, 2021, 14:40 |
Aaron Schmidt | | | | | | | Done | FC6 re-installed | Monday, June 07, 2021, 14:39: Roughing
beam line section.
Monday, June 07, 2021, 14:46: TMS:TP6 |
|
|
399
|
Thursday, August 14, 2014, 08:45 |
Anders Mjos | | | | | | | Problems/Solutions | FC0 reading full current | since yesterday around 19h. See attached
screen shot of archived data
Thursday, August 14, 2014, 08:40: |
|
|
893
|
Saturday, August 07, 2021, 18:07 |
Fernando Maldonado | | | | | | | Problems/Solutions | FC0 lasrge oscillation and RMPs offset. Both started today. [Got solved by itself] | Saturday, August 07, 2021, 18:02: As mentions
in previous entries, the FC0 current oscillates
with no change on ion source parameters. |
|
|
388
|
Thursday, June 19, 2014, 10:48 |
Anders Mjos | | | | | | | Problems/Solutions | FC0 did not retract from beam line | Upon inspection it was found that the bolt
attaching the FC to the actuator had fallen
off. The bolt was reattached and FC0 can |
|
|
994
|
Tuesday, February 06, 2024, 14:09 |
Aaron Schmidt | | | | | | | Problems/Solutions | FC0 Solenoid issue | Tuesday, February 06, 2024, 14:06: Attempted
to 'Close' FC0. While it succeeded in moving
into position, HPA rushed out of the exhaust. |
|
|
990
|
Thursday, January 18, 2024, 10:47 |
Aaron Schmidt | | | | | | | Problems/Solutions | FC0 Solenoid Replaced. | Issues with valve operations due to a leak
in the solenoid valve above FC0. The HPA
leak did not allow for sufficient pressure |
|
|
699
|
Thursday, December 06, 2018, 11:02 |
Aaron Schmidt | | | | | | | Problems/Solutions | FC0 Bellows Replacement. | Thursday, December 06, 2018, 11:02: Turbo
pumps (TP6 & TP2) off on beamline side.
IG6 off. |
|
|
513
|
Friday, June 10, 2016, 12:42 |
Anders Mjos | | | | | | | Problems/Solutions | FC0 BIAS probelm | Graham Waters is looking into this
problem. The IOC has been rebooted a couple
of times. |
|
|
165
|
Sunday, August 12, 2012, 22:07 |
Pierre Bricault | | | | | | | In progress | FBIAD test | The reset restored the control.
But magnet supply does not put any
amperage out. |
|
|
476
|
Monday, October 19, 2015, 15:39 |
Anders Mjos | | | | | | | Problems/Solutions | Exhaust came off the new RP2 |
|
|
|
458
|
Tuesday, August 04, 2015, 13:37 |
Anders Mjos | | | | | | | Problems/Solutions | Equipment for outgassing measurements removed | |
|
|
628
|
Monday, February 05, 2018, 09:17 |
Aaron Schmidt | | | | | | | Problems/Solutions | Epics loss | Monday, February 05, 2018, 09:10: the epics
program was in 'White-out'. Turbo pumps tripped.
Unplug, re-plug PLC. |
|
|
681
|
Wednesday, August 29, 2018, 11:36 |
Aaron Schmidt | | | | | | | | Epics / putty crash. | Wednesday, August 29, 2018, 11:35: EPIC's
crashed.... epically.
Unable to restart Putty or TS controls. |
|
|
846
|
Monday, February 08, 2021, 09:20 |
Aaron Schmidt | | LP-SIS | | | 44139-10 | 44378-2 | Failed | Energy spread calibration with SIS. No PE | Re-salted. PE removed. EE Cleaned
Monday, February 08, 2021, 09:17:
Roughing. |
|
|
840
|
Thursday, January 21, 2021, 10:10 |
Fernando Maldonado | | LP-SIS | | | 44139-10 | 44378-2 | Done | Energy spread calibration - SIS with TBHT negatively biased | Thursday, January 21, 2021, 10:05:
Anodeless Negative Bias On Surface Ion
Source, or ANBOSIS (still working on the |
|
|
844
|
Thursday, February 04, 2021, 18:48 |
Fernando Maldonado | | LP-SIS | | | 44139-10 | 44378-2 | Problems/Solutions | Energy spread calibration with SIS | The system was vented to make clearance
on the waterlines as a very small continuous
discharge was observed. |
6x |
|
845
|
Thursday, February 04, 2021, 19:22 |
Fernando Maldonado | | LP-SIS | | | 44139-10 | 44378-2 | Done | Energy spread calibration with SIS | See e-log entry: 884:
Thursday, February 04, 2021, 18:45:
Roughing |
|
|
848
|
Wednesday, February 10, 2021, 09:49 |
Aaron Schmidt | | LP-SIS | | | 44691-8 | 44378-2 / 44378-3 | Failed | Energy spread calibration with SIS | Note* target has a ring on the TGHT - Right
leg. EE & PE placed. Target to HS OL
- OK. |
|
|
843
|
Monday, February 01, 2021, 08:38 |
Fernando Maldonado | | LP-SIS | | | 44139-10 | 44378-2 | Failed | Energy spread calibration | Monday, February 01, 2021, 08:38 : The
anode seems to be shorted but we can still
test the amount of dispersion at the |
|
|
104
|
Monday, June 04, 2012, 11:40 |
Anders Mjos | | | | | | | In progress | Empty chamber | HS water lines blanked.
Monday, June 04, 2012, 11:40: Roughing.