Message ID: 990     Entry time: Thursday, January 18, 2024, 10:47
Author: Aaron Schmidt 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: FC0 Solenoid Replaced. 

Issues with valve operations due to a leak in the solenoid valve above FC0. The HPA leak did not allow for sufficient pressure to remain in the lines to operate. The solenoid as changed this morning.

Thursday, January 18, 2024, 10:32: Roughing. Valves can be cycled. FC0 cycled. OK.

Thursday, January 18, 2024, 10:40: TMS TP6 & TMS:TP2 on.

Thursday, January 18, 2024, 10:45: IG6 on.

 