Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 39 of 53  Not logged in ELOG logo
ID Date Author Target/No.# Source Station Module Target Oven W.O#down Heat Shield W.O# Status Subject Text Attachments
  590   Tuesday, June 06, 2017, 09:22 Aaron Schmidt       Pump down empty chamberTuesday, June 06, 2017, 09:21: roughing.

Friday, June 09, 2017, 08:50:
Ion gauge off. Turbo pumps off.
  
  591   Wednesday, June 07, 2017, 12:49 Aaron Schmidt       Gas bottles Gas bottles for FEBIAD testing were
exchanged yesterday around 1:30. One Neon
& one Argon bottle were removed.
  
  593   Friday, June 16, 2017, 11:23 Aaron Schmidt       Pump down empty chamber.Friday, June 16, 2017, 11:22: roughing.
Friday, June 16, 2017, 14:28: Turbo
pumps on
  
  600   Wednesday, July 19, 2017, 09:13 Aaron SchmidtTa Targets     DoneIon PeaksAttached is a recent list of Ta targets
with their extracted ions peaks.
 Magnet_peaks.xlsx 
  601   Thursday, August 03, 2017, 17:00 Anders Mjos      Problems/SolutionsVacuum system tripped on power interruption Thursday, August 03, 2017, 17:00:
Restarted TPs
  
  603   Thursday, August 17, 2017, 12:45 Anders Mjos      Problems/SolutionsTBHT power supply removed  The Xantrex 10V 600 A power supply
for the TBHT has been moved to ITE to replace
the failed TGHT power supply
  
  604   Monday, August 21, 2017, 16:20 Anders Mjos      Problems/SolutionsTBHT power supply removed


   
        
            
  
  606   Monday, September 25, 2017, 14:10 Aaron Schmidt       Pump down empty chamberMonday, September 25, 2017, 14:10: Roughing.

Wednesday, September 27,
2017, 08:23: Turbo pumps on
  
  608   Tuesday, October 10, 2017, 13:10 Aaron Schmidt       Gas bottlesTuesday, October 10, 2017, 09:30: 
Install/swap gas bottles. Elog.
Removed smallest Neon leak. Neon
  
  609   Tuesday, October 10, 2017, 14:56 Aaron Schmidt      In progressFEBIAD Anode bias configurationUnable to hold Anode voltage after power
supply change out.
Tuesday, October 10, 2017, 14:55:
  
  611   Monday, October 16, 2017, 11:46 Aaron Schmidt      In progressPump down empty chamber Test EEMonday, October 16, 2017, 11:45: Roughing.
Monday, October 16, 2017, 12:05:
Turbo pumps started.
  
  612   Tuesday, October 24, 2017, 11:38 Anders Mjos       FEBIAD coil magnetic field measurmentwith Fernando
Tuesday, October 24, 2017: Testing
setup with triple coil
 FEBIAD_Coil_Field_Measurement_2017-10-25.xlsx171025-First-Run.xlsx 
  613   Monday, October 30, 2017, 08:54 Anders Mjos      Problems/SolutionsTMS:TP6 shut down due to high noiseThe turbo pump will need replacement.   
  614   Wednesday, November 15, 2017, 10:56 Aaron Schmidt      Problems/SolutionsTMS:TP6 replacementTurbo pump TP6 requires replacement.
Wednesday, November 15, 2017, 09:55:
Turbo (TP2) off. Ion gauge off.
  
  616   Monday, December 04, 2017, 08:29 Aaron Schmidt      Problems/SolutionsPower outagePower outage over the weekend. Reboot PLC
and systems.
Monday, December 04, 2017, 08:22:
 20171205_103324.jpg 
  619   Thursday, December 21, 2017, 15:12 Anders Mjos       Powered down devicesPowered down vacuum gauge and turbo pump
controllers
  
  620   Tuesday, January 02, 2018, 09:18 Anders Mjos      Problems/SolutionsStarting systemTuesday, January 02, 2018
Cycled power for TCSIOC and PLCIOC
TP2 and TP6 started
  
  621   Monday, January 22, 2018, 09:04 Aaron Schmidt      DonePower outage & Controller replacement.Computer, TS, epics, restarted. Power checks
Monday, January 22, 2018, 09:00:
ISAC PLC TLCIOC Restarted. 
  
  622   Friday, January 26, 2018, 11:10 Aaron Schmidt      DoneHelium tank replacementFriday, January 26, 2018, 11:08: New Helium
tank installed inside the Test Stand.
-The 'Full' tag remains. The He tank
  
  628   Monday, February 05, 2018, 09:17 Aaron Schmidt      Problems/SolutionsEpics lossMonday, February 05, 2018, 09:10: the epics
program was in 'White-out'. Turbo pumps tripped.
Unplug, re-plug PLC.
  
ELOG V2.9.2-2455