284
|
Tuesday, March 19, 2013, 17:25 |
Sebastian Raeder | | | | | | | Problems/Solutions | new turbo installed | Edi replaced the faulty turbo pump in the mass separator section.
Roughing and turbo started
vacuum @ 9E-7T after 2.5h |
283
|
Tuesday, March 19, 2013, 12:34 |
Anders Mjos | SiC#28 | | ITE | TM4 | | | Done | Installation of SiC#28 LP-RFQ | Tuesday, March 19, 2013, 12:32 : Turbos off (vaccum at 2E-7 Torr)
Tuesday, March 19, 2013, 13:35: Venting
Target SiC#28 LP-RFQ inserted
New bolts used. Old bolts removed.
All bolts torqued to 120 in lbs
By Sebastian (SR) & Henning
modification of 9 Pin connector needed to match wiring in TM4 (see separate e-log entry)
Tuesday, March 19, 2013, 18:32 : started roughing - SR
Tuesday, March 19, 2013, 18:52: started turbos - SR
Tuesday, March 19, 2013, 18:57: TSGIP1 on - SR
Tuesday, March 19, 2013, 19:00: turbos at speed - SR
Tuesday, March 19, 2013, 19:02: vacuum at 1.68E-5T
By Anders
Wednesday, March 20, 2013, 08:18: Opened cooling water. Vacuum stable at 6.8E-7 Torr
By Sebastian (SR) & Henning
Wednesday, March 20, 2013, 11:39: 9PIN connector in HV cage connected
4,5,6,9 on GND 1,2 to RF, 7,8,RFoffest,Source for now also on GND
RF: 800kHz, 20Vampl, 0.128mA
HV cage locked up for heating
Wednesday, March 20, 2013, 16:42: heating is taken care of by ISAC operations, now at 300A / 3V TGHT and 250A / 1.47V TBHT reading on the panel is really close
Friedhelm restarted some of the CANBUS ports, since not all optics were working properly
Thursday, March 21, 2013, 10:53 start cooling down
Vacuum not perfect was around 2E-6T, over nigth not full current
Suppression tested yesterday: full beam (SRC +3V, others GND) was 40nA, while no signal on FB0B with SRC +3V, IGOffset&Exit +25V
!!!!! but short on #7 --> 2nd Repeller, was OK when tested, after some minutes on 25V short was there, reading now (Thursday, March 21, 2013, 10:58 ) <1OHM, will be checked while heating down
Magnet had wrong polarity - so no mass scans yesterday evening, Friedhelm looked into this this morning
Mass scan only for good transmission mode (SRC +3V) this morning - see attached scan (seen Na, Al, K, Ca, Cr, Rb, Sr, Cs and Ba)
Thursday, March 21, 2013, 12:26: stopped turbos
#7 still short
By Anders
Thursday, March 21, 2013, 13:25: Venting |
282
|
Tuesday, March 19, 2013, 09:04 |
Anders Mjos | | | | | | | Problems/Solutions | Venting TMS section for replacement of TP2 by vacuum group |
Anders Mjos wrote: |
Tuesday, February 26, 2013, 08:24: Started turbo
Tuesday, February 26, 2013, 08:24: Turbo timed out
e-fault 6585 submitted
|
Edi called to inform that he can replace the turbo today.
Tuesday, March 19, 2013, 09:03: Stopped TP6
Tuesday, March 19, 2013, 09:35: Venting
Tuesday, March 19, 2013, 09:48 : TMS section and backing line vented
The turbo pump has been replaced see
https://elog.triumf.ca/TIS/Test-Stand/284
Some heat marks were observed on the turbo pump that was replaced. Vacuum group took pictures.
|
281
|
Monday, March 04, 2013, 09:11 |
Anders Mjos | | | | | | | Problems/Solutions | Restarted turobos after planned power outage | Started archivers
Started turbos
Switched on ion gauges
TMSTP2 out as per precious e-log entry (and e-fault 6585) |
280
|
Tuesday, February 26, 2013, 08:32 |
Anders Mjos | | | | | | | Problems/Solutions | TMSTP2 timeout / fault | Tuesday, February 26, 2013, 08:24: Started turbo
Tuesday, February 26, 2013, 08:24: Turbo timed out
e-fault 6585 submitted |
279
|
Tuesday, February 19, 2013, 08:28 |
Anders Mjos | | | | | | | Problems/Solutions | Opened all backing valves after scheduled site wide air outage | |
278
|
Monday, January 28, 2013, 14:41 |
Anders Mjos | Empty | | | | | | | Pumping down | Monday, January 28, 2013, 14:41: Roughing
Monday, January 28, 2013, 15:35: Starting turbos
Monday, January 28, 2013, 15:43: Turbos at speed
Monday, January 28, 2013, 15:45: Vacuum at 3.9 E-6 T |
277
|
Monday, January 28, 2013, 12:56 |
Anders Mjos | Empty | | | | | | | Venting | For conductor bolt work
Monday, January 28, 2013, 12:56: Turbos off
Monday, January 28, 2013, 14:18: Venting |
276
|
Friday, January 18, 2013, 16:17 |
Anders Mjos | RFQ empty | | | | | | In progress | heating |
Sebastian Raeder wrote: |
Thursday, January 17, 2013, 08:16: started heating of the target, vacuum at 2.6E-7T
Thursday, January 17, 2013, 14:55: current at 572A/6.95V (panel reading), vacuum at 6.7E-7T
Thursday, January 17, 2013, 18:40: measurements done, vacuum at 5.3E-7T, current 572V/6.94V, start cooling down
|
The temperature of the cooling water was logged during this test. See attachments for details. Note that current and voltage read back is not available due to trouble with the power supply. One thermocouple (Heat Shield circuit) came loose before the end of the test (not shown in plot). |
275
|
Friday, January 18, 2013, 15:57 |
Anders Mjos | | | | | | | Problems/Solutions | Conductor bolts to be replaced | After the last test at the test stand, one of the conductor bolts (ITD0058) is damaged. To prevent damage to the thread inserts, all conductor bolts will be replaced with new ones. |
274
|
Friday, January 18, 2013, 15:34 |
Anders Mjos | empty | | | | | | | Pumping down empty chamber | Started roughing
Friday, January 18, 2013, 15:25: Started turbos
Friday, January 18, 2013, 15:33: Turbos at speed
Friday, January 18, 2013, 15:35: Vacuum at 1.5E-5 T |
273
|
Friday, January 18, 2013, 11:28 |
Sebastian Raeder | RFQ empty | | | | | | | stop turbos | Friday, January 18, 2013, 11:28: turbos stopped |
272
|
Thursday, January 17, 2013, 08:16 |
Sebastian Raeder | RFQ empty | | | | | | In progress | heating | Thursday, January 17, 2013, 08:16: started heating of the target, vacuum at 2.6E-7T
Thursday, January 17, 2013, 14:55: current at 572A/6.95V (panel reading), vacuum at 6.7E-7T
Thursday, January 17, 2013, 18:40: measurements done, vacuum at 5.3E-7T, current 572V/6.94V, start cooling down |
271
|
Wednesday, January 16, 2013, 01:06 |
Sebastian Raeder | RFQ empty | | | | | | | Target installed - pumping down | RFQ empty target installed
Wednesday, January 16, 2013, 01:05: roughing started
Wednesday, January 16, 2013, 01:34: turbos started
Wednesday, January 16, 2013, 01:43: turbos at speed
Wednesday, January 16, 2013, 01:44: vacuum at 1.7E-5T |
270
|
Tuesday, January 15, 2013, 16:10 |
Anders Mjos | RFQ empty | | | | | | | Turbos off |
Sebastian Raeder wrote: |
Start cooling of Target RFQ empty
|
Tuesday, January 15, 2013, 16:09: Turbos off
Tuesday, January 15, 2013, 21:15: Start venting with nitrogen- SR |
269
|
Tuesday, January 15, 2013, 15:12 |
Sebastian Raeder | RFQ empty | | | | | | | Start cooling | Start cooling of Target RFQ empty |
268
|
Monday, January 14, 2013, 18:18 |
Friedhelm Ames | | | | | | | | TMS:CBC1 not working | The optics at the teststand has been switched on, but TMS:CBC1 is not working. A fault report has been send to controls. |
267
|
Monday, January 14, 2013, 13:51 |
Sebastian Raeder | RFQ empty | | | | | | In progress | heating | Started heating the target, now Silica sleevings are installed for wire insulation and the gap target -- repeller is now 0.6mm (was 0.25mm) |
266
|
Friday, January 11, 2013, 11:02 |
Anders Mjos | RFQ empty | | | | | | | Target installed, pumping down | Target installed with 120 in lbs torque on target legs and on central support.
Friday, January 11, 2013, 11:01: Roughing
Friday, January 11, 2013, 11:25: Start turbos - SR
Friday, January 11, 2013, 11:34: turbos at speed - SR
Friday, January 11, 2013, 11:35: vacuum at 1.2E-5T - SR
|
265
|
Friday, January 11, 2013, 08:37 |
Anders Mjos | Empty | | | | | | In progress | Venting | Friday, January 11, 2013, 08:36: Venting for installation of RFQ test target later today |
|