Thursday, July 11, 2013, 08:38, Anders Mjos, , , , , , , Problems/Solutions, Bias & EL P/S cleaned
|
The power supplies were "de-dusted" yesterday by Ray Dube and team. |
Wednesday, July 10, 2013, 10:21, Anders Mjos, SiC#29, HP-FEBIAD-CTL, ITE, TM4, 38481-6, 39956-4, Done, Testing SiC#29 CTL Target
|
Wednesday, July 10, 2013, 10:20 : Turbos off. Vacuum at 1.3 E-7 T
Wednesday, July 10, 2013, 11:23: Venting chamber
Wednesday, July 10, 2013, 12:00: Vented |
Thursday, June 13, 2013, 11:04, Anders Mjos, , , , , , , Problems/Solutions, Viton seals on vacuum chamber doors replaced
|
See PO# TR193650 |
Thursday, June 13, 2013, 10:19, Anders Mjos, , , , , , , Done, Pumping down empty chamber
|
Thursday, June 13, 2013, 10:17: Roughing.
Thursday, June 13, 2013, 10:52: Turbos started
Thursday, June 13, 2013, 11:00 : Both turbos at speed. |
Wednesday, June 12, 2013, 20:38, Friedhelm Ames, , , , , , , Problems/Solutions, target heater power supply removed
|
The target heater power supply at the teststand has been removed to replace one in ITE. |
Friday, June 07, 2013, 08:47, Anders Mjos, , , , , , , Problems/Solutions, TPS:Q2, TPSQ4 and TMS:MB1 found off
|
Friday, June 07, 2013, 08:42: Restarted Q2, Q4 and MB1 |
Monday, June 10, 2013, 08:16, Anders Mjos, , , , , , , Problems/Solutions, TPS:Q2, TPSQ4 and TMS:MB1 found off
|
Anders Mjos wrote:
Friday, June 07, 2013, 08:42: Restarted Q2, Q4 and MB1 |
Monday, June 10, 2013, 16:46, Anders Mjos, , , , , , , Problems/Solutions, TPS:Q2, TPSQ4 and TMS:MB1 found off
|
Anders Mjos wrote:
|
Tuesday, June 11, 2013, 08:41, Anders Mjos, , , , , , , Problems/Solutions, TPS:Q2, TPSQ4 and TMS:MB1 found off
|
Anders Mjos wrote:
|
Monday, June 03, 2013, 15:00, Anders Mjos, , , , , , , Problems/Solutions, SOURCES ARCH Restarted
|
SOURCES ARCH was found not running |
Wednesday, May 29, 2013, 12:10, Anders Mjos, CTL FEBIAD, HP-FEBIAD, , , 38481-5, , Done, CTL Test
|
Wednesday, May 29, 2013, 12:09: Debiased to insert temp logger
Wednesday, May 29, 2013, 14:40: Temp logger installed
CH1 COIL |
Tuesday, May 28, 2013, 09:53, Anders Mjos, , , , , , , Problems/Solutions, TPS:Q4 and TPS:Q2 restarted
|
|
Tuesday, May 28, 2013, 09:51, Anders Mjos, , , , , , , Problems/Solutions, Archivers restarted
|
COIL and ANODE data added to ISACT Data Archiver |
Friday, May 24, 2013, 15:13, Aurelia Laxdal, CLT FEBIAD, , , , , , , CLT FEBIAD conditioning started
|
Purged the gas lines, turned on the HV and started the heaters for CLT FEBIAD: TGHT up to 580A and TBHT up to 230A. |
Tuesday, May 21, 2013, 19:38, Friedhelm Ames, , , , , , , Problems/Solutions, magnet power supply water leak
|
The cyclotron operators discovered a water leak in the magnet power supply. The water is valved off and the power is off. A fault report has been issued
to the power supplies group. |
Tuesday, May 21, 2013, 15:50, Rick Maharaj, CTL Febiad, , , , , , , Cooling Water Turned On
|
Cooling water turned on when vacuum reading 5.54e-06 T. Vacuum steadily increasing. Ion gauge reading steadily decreasing now reading 4.48e-06 T. |
Tuesday, May 21, 2013, 15:14, Rick Maharaj, CTL Febiad, , , , , , , Turbos Started
|
Turbos started |
Tuesday, May 21, 2013, 14:58, Rick Maharaj, CTL Febiad, , , , , , , CTL Febiad Installed
|
Ceramic coated coil development target removed. CTL Febiad target installed.
Roughing chamber. |
Tuesday, May 21, 2013, 10:09, Rick Maharaj, , , , , , , , Test stand Vented
|
Turbos stopped, waterlines flushed, chamber vented |
Thursday, May 09, 2013, 15:28, Anders Mjos, , , , , , , Problems/Solutions, TSGRP1 showing signs of reduced performance
|
TSG:CG1A and TSG:CG1B shows an increase in vacuum.
See attached archived data for details. |
Wednesday, May 08, 2013, 08:52, Anders Mjos, , , , , , , Problems/Solutions, TMS and TPS P/S problems
|
Wednesday, May 08, 2013, 08:52: TMS:CB5 found off this morning. Switched back on.
Wednesday, May 08, 2013, 12:14: Lost the following devices during a mass scan
Normal
0
|
Monday, March 25, 2013, 16:50, Sebastian Raeder, , , , , , , Problems/Solutions, RFQ powersupplies removed - Anode PS still connected to ground
|
The powersupplies added to the teststand for operation of the IGLIS source have been removed from the HV cage as well as the RFQ driver.. The connections
of the 9PIN connector in the HV cage have been grounded and the wire used for an voltage offset of the source has been removed.
|
Friday, May 03, 2013, 14:32, Anders Mjos, , , , , , , Problems/Solutions, Cathode PS cable reconnected
|
Sebastian Raeder wrote:
|
Thursday, April 25, 2013, 13:32, Anders Mjos, Empty, LP-FEBIAD, , , Tube Only, 38307-9 , In progress, FEBIAD Coil test
|
Same target as in e-log entry https://elog.triumf.ca/TIS/Test-Stand/106
Thursday, April 25, 2013, 13:54: Roughing
Thursday, April 25, 2013, 14:25: Started turbos |
|