Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 34 of 53  Not logged in ELOG logo
ID Date Authordown Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subject
  587   Wednesday, May 24, 2017, 11:12 Anders Mjos      Problems/SolutionsFEBIAD Anode bias configuration

 The Test Stand has been configured for Anode bias. John Chow changed the power supply and the electrical connections have been wired according to ISK4523D REV 6.

 

Wednesday, May 24, 2017, 17:37: Anode current reduce to 285 A. Anode drain current limited  to a maximum of 300 A. This will be left overnight to see if there is an increase in anode drain current. as was seen today.

Attachment 1: 20170524-ST-currentvscoil-CHT300A.PNG
20170524-ST-currentvscoil-CHT300A.PNG
  589   Saturday, June 03, 2017, 09:34 Anders Mjos      Problems/SolutionsFEBIAD Cathode bias configuration

Anders Mjos wrote:

 The Test Stand has been configured for Anode bias. John Chow changed the power supply and the electrical connections have been wired according to ISK4523D REV 6.

 

Wednesday, May 24, 2017, 17:37: Anode current reduce to 285 A. Anode drain current limited  to a maximum of 300 A. This will be left overnight to see if there is an increase in anode drain current. as was seen today.

 The Test Stand has been  configured for Cathode bias. John Chow changed the power supply and the electrical connections have been wired according to ISK4563 REV 5.

  601   Thursday, August 03, 2017, 17:00 Anders Mjos      Problems/SolutionsVacuum system tripped on power interruption

 Thursday, August 03, 2017, 17:00: Restarted TPs

  603   Thursday, August 17, 2017, 12:45 Anders Mjos      Problems/SolutionsTBHT power supply removed

 The Xantrex 10V 600 A power supply for the TBHT has been moved to ITE to replace the failed TGHT power supply

  604   Monday, August 21, 2017, 16:20 Anders Mjos      Problems/SolutionsTBHT power supply removed

Anders Mjos wrote:

 The Xantrex 10V 600 A power supply for the TBHT has been moved to ITE to replace the failed TGHT power supply

 A spare EMI-EMS 10 V - 500 A power supply was installed last Friday by John Chow. Dave Morris has connected the controls today and updated EPICS. The local voltage readback on the power supply does not work.

  612   Tuesday, October 24, 2017, 11:38 Anders Mjos       FEBIAD coil magnetic field measurment

with Fernando

Tuesday, October 24, 2017: Testing setup with triple coil

Wednesday, October 25, 2017: Field mapping at 70 A and current/field measurements on triple coil.

Attachment 1: FEBIAD_Coil_Field_Measurement_2017-10-25.xlsx
Attachment 2: 171025-First-Run.xlsx
  613   Monday, October 30, 2017, 08:54 Anders Mjos      Problems/SolutionsTMS:TP6 shut down due to high noise

The turbo pump will need replacement.

  619   Thursday, December 21, 2017, 15:12 Anders Mjos       Powered down devices

Powered down vacuum gauge and turbo pump controllers

  620   Tuesday, January 02, 2018, 09:18 Anders Mjos      Problems/SolutionsStarting system

Tuesday, January 02, 2018

Cycled power for TCSIOC and PLCIOC

TP2 and TP6 started

TP1B does not start. TP1B controller does not start up correctly - controller will have to be replaced. E-fault submitted (10739).

Controller for PS for Q1,6 was switching constantly. Unplugged and plugged back in resolved the problem

TP1A started


(Aaron Schmidt)

Wednesday, January 03, 2018, 08:15:  TSG:TP1B Still non-responsive.

Wednesday, January 03, 2018, 08:20: Power/sources on. Add Voltage/Amp and check power supplies.

BIAS - 300V Reads 290V - OK

EE - 300V Reads 298V - OK

EZL - 300V Reads 293 V - OK

CB1 - 10V Reads 10V - OK

VCB1 - 10V Reads 10V - OK

CBC (both)  - 10V Reads 9V - OK

TBHT - 10A Reads 9.9A (009 direct off PS) - OK

TGHT - 10A Reads 9.8A (007 direct off PS) - OK

Optics Check:

Magnet ok - Some optics start, some do not respond. Submit fault report for communications issues.

Fault Report submitted - 10742

 


Thursday, January 04, 2018, 14:38:

Kyle and Dave were able to get all the canbus optics for ISAC test stand re-configured except one device: TMS:Q2

"We investigated and it looks like the controller board for the TMS:Q2 supply is toast. Unfortunately these boards are a very old style so we don't have a surplus of replacements on hand. Our electronics shop did have some spares but the spares are not ready for use and need to have a few components soldered on. " - Kyle

The repaired controller board should be ready for next week.


Wednesday, January 10, 2018, 13:22: TS optics all fixed. Turbo pump TP1B is still out.

  661   Tuesday, May 22, 2018, 08:48 Anders Mjos      Problems/SolutionsTSG:TP1A not running

Pump found off on Tuesday morning.

Tuesday, May 22, 2018, 08:40: Starting TP1A

Tuesday, May 22, 2018, 08:47: TP1A at speed


Tuesday, May 22, 2018, 16:33: Source and optics off


Wednesday, May 23, 2018, 08:30: Stopped TP

Wednesday, May 23, 2018, 14:10: Water purged

  662   Thursday, May 24, 2018, 08:38 Anders Mjos      Problems/SolutionsVenting beamline for IG6 replacement

Thursday, May 24, 2018, 08:38: TPs stopped

Thursday, May 24, 2018, 09:18: Venting

Thursday, May 24, 2018, 14:30: IG6 replaced (second attempt) by Anthony. System pumping down

  663   Thursday, May 24, 2018, 15:28 Anders Mjos      Problems/SolutionsReconfigured FEBIAD coil for testing new source tray

Thursday, May 24, 2018: Configured coil to be (-) E&F, (+) G&H. Water should be supplied to both terminals in either configuration.

  665   Monday, June 04, 2018, 16:02 Anders Mjos      Problems/SolutionsMB1 timeout

Mass separator magnet timed out. Tried reconfigure. Called Kyle from controls who power cycled the CANbus card. This resolved the issue


(From the Source tray swap out.) - AS

Tuesday, June 05, 2018, 11:25: BIAS / EZL / EE @ 52 / 24 / 2.8 kV. SPARK *knocked out optics, magnet & Turbo TMS:TP6. IV4 closed/opened/reset. TP6/optics restarted. Magnet still off.

Complete failure of the communications with the magnet.


Wednesday, June 06, 2018, 13:40: Canbus contoller was swapped by Kyle L from Controls group. The old card was dead and replaced with a new one. The magnet is back and running.

  670   Thursday, June 21, 2018, 16:32 Anders Mjos LP-FEBIAD  41790-942752-5In progressHeating target

Thursday, June 21, 2018, 16:30: Short between ANODE and EE. Do not use until repaired.

Thursday, June 21, 2018, 16:32: Ramping TBHT/TGHT to 290 / 580 Aat 2 A/min


Friday, June 22, 2018, 07:49: Target at temperature. Vacuum at 1.0E-7 T


Monday, June 25, 2018, 09:10: Auto-cooling at 2A/min - AS.


Friday, June 29, 2018, 08:52: Turbos/PS/Sources/RGA/Ion gauge off.

Friday, June 29, 2018, 10:03: Venting.

Friday, June 29, 2018, 14:32: Roughing. Anode to EE short fixed.

Attachment 1: TS-2018-06-19-10-30.rga
Attachment 2: TS_Source_tray_2018_-_Check_2.docx
  679   Tuesday, August 21, 2018, 12:54 Anders Mjos      Problems/Solutions9-pin connection configuration

Pin configuration between top 9-pin connector on Source Tray and terminal in high voltage rack. Measured 2018-08-21 by Aaron and Anders

Grounded     X            
Source Tray Side (looking head on) 1 2 3 4 5 6 7 8 9
High Voltage Cage Side 5 4 3 2 1 9 8 7 6

 

  720   Friday, May 03, 2019, 08:30 Anders Mjos      In progressTraining

Training: Venting and pump down

Friday, May 03, 2019, 08:30: Turbo pumps stopped.

  764   Friday, October 25, 2019, 12:04 Anders Mjos      Problems/SolutionsISG:TP1A found stopped

Restarted TP. Note that CG1A is above 50 mTorr. CG1B shows 15 mTorr

  776   Friday, January 03, 2020, 11:56 Anders Mjos      Problems/SolutionsUpgrading BIAS Power Supply

A new power supply was installed today by John Chow. Due to differences in pin configuration of the controls, a change to the cabling is required. Contacted controls (Julie) for support.

  779   Thursday, January 23, 2020, 16:05 Anders Mjos      Problems/SolutionsVacuum tripped due to PLC/EPICS for for the new BIAS

Thursday, January 23, 2020, 16:05: Restarting vacuum and TPs

  780   Friday, January 24, 2020, 16:01 Anders Mjos      Problems/SolutionsUpgrading BIAS Power Supply

Anders Mjos wrote:

A new power supply was installed today by John Chow. Due to differences in pin configuration of the controls, a change to the cabling is required. Contacted controls (Julie) for support.

 Ray from controls has updated EPICS and changed the cabling today. The power supply is operational.

NOTE: Current limit will need to be set in EPICS. Default value should be 0.1 mA for now.

ELOG V2.9.2-2455