153
|
Thursday, July 19, 2012, 11:32 |
Anders Mjos | | | | | | | Done | Pumping down | Thursday, July 19, 2012, 11:29: roughing
Thursday, July 19, 2012, 11:49: starting
turbos |
|
177
|
Friday, August 17, 2012, 12:53 |
Pierre Bricault | | | | | | | Done | | Test completed.
exel file on My Documents in folder
FEBIAD Test Aout2012/TestFEBIAD |
|
182
|
Friday, August 24, 2012, 08:28 |
Anders Mjos | NiO#1 | HP-FEBIAD | ITE | TM4 | | | Done | NiO#1 installed |
|
|
190
|
Friday, August 31, 2012, 11:12 |
Aurelia Laxdal | | HP-FEBIAD | ITE | TM4 | | | Done | Finished testing NiO#1 | Turned off the HV and the optics in the
first section. Couldn't turn off the optics
in the second section: left a message for |
|
191
|
Friday, August 31, 2012, 11:39 |
Anders Mjos | NiO#1 | HP-FEBIAD | ITE | TM4 | | | Done | Venting vacuum chamber - source change | Friday, August 31, 2012, 11:39: Stopped
turbos.
Friday, August 31, 2012, 13:06: Venting. |
|
193
|
Tuesday, September 04, 2012, 08:11 |
Anders Mjos | Nb#7 | LP-SIS | ITW | TM1 | | | Done | Nb#7 installed |
|
|
196
|
Friday, September 07, 2012, 13:10 |
Friedhelm Ames | Nb#7 | | | | | | Done | mass scan finished | mass scan is finished saved as
Normal
0
|
|
199
|
Tuesday, September 11, 2012, 19:48 |
Friedhelm Ames | NB#7 | HP-SIS | | | | | Done | cool down finished, all source power supplies off. | |
|
204
|
Friday, September 14, 2012, 15:27 |
Anders Mjos | Nb#7 | LP-SIS | ITW | TM1 | | | Done | Venting | Target cooled down. Power supplies off.
Friday, September 14, 2012, 15:27:
Turbos off. |
|
212
|
Monday, September 24, 2012, 15:25 |
Anders Mjos | | | | | | | Done | TMS RP and TP started | |
|
214
|
Tuesday, September 25, 2012, 13:25 |
Anders Mjos | | | | | | | Done | Started turbos after replaced roughing pump | |
|
224
|
Friday, October 26, 2012, 08:29 |
Anders Mjos | TiC#3 | LP-SIS | ITW | TM1 | | | Done | Target ready for conditioning |
|
|
228
|
Friday, November 02, 2012, 15:40 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | Done | SiC#3 cooldown started | Started the cooldown for SiC#3. |
|
229
|
Monday, November 05, 2012, 09:47 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | Done | TPS optics cannot be turned off. | All TPS optics, with the exception of TPS:Q4
cannot be turned off. E-Fault#6395 for Controls.
Same for the TSG optics: CB1, VCB1 |
|
230
|
Monday, November 05, 2012, 13:26 |
Aurelia Laxdal | | LP-SIS | ITW | TM1 | | | Done | Venting the Test Stand | Venting the Test Stand.
TiC#3 will be ready to be removed
in few minutes. |
|
231
|
Monday, November 05, 2012, 14:41 |
Anders Mjos | TiC#3 | LP-SIS | ITW | TM1 | | | Done | Target Removed | Target looks OK. The right leg was a bit
much out of center and will be adjusted in
the lab. |
|
232
|
Monday, November 05, 2012, 14:42 |
Anders Mjos | Test SiC | HP-FEBIAD | | | | | Done | Pumping down | Monday, November 05, 2012, 14:41: Roughing
Monday, November 05, 2012, 14:58:
Started turbos |
|
245
|
Tuesday, December 11, 2012, 13:40 |
Sebastian Raeder | RFQ empty | | | | | | Done | Heating test for Ion guide Laser ion source | new ion guide laser ion source installed.
Pure target container without targetmaterial
and without surface ion source. |
|
250
|
Friday, December 14, 2012, 20:34 |
Sebastian Raeder | RFQ empty | | | | | | Done | pumping down | Friday, December 14, 2012, ~ 17:00: start
roughing pumps
Friday, December 14, 2012, 20:33: |
|
253
|
Tuesday, December 18, 2012, 16:00 |
Sebastian Raeder | RFQ empty | | | | | | Done | target heating | Tuesday, December 18, 2012, ~ 13:00 start
ramping the TGHT current, vacuum at 1.7E-7T
Tuesday, December 18, 2012, 15:56: |
|
|