Entry  Thursday, December 13, 2012, 14:38, Anders Mjos, , , , , , , , Pumping down empty chamber 

Thursday, December 13, 2012, 14:36: Roughing

Thursday, December 13, 2012, 14:56 : Starting turbos

Thursday, December 13, 2012, 15:05 : turbos at speed

Thursday, December 13, 2012, 15:06 : vacuum at 2.3E-5 T

 

Entry  Friday, January 18, 2013, 15:34, Anders Mjos, empty, , , , , , , Pumping down empty chamber 

Started roughing

Friday, January 18, 2013, 15:25: Started turbos

Friday, January 18, 2013, 15:33: Turbos at speed

Friday, January 18, 2013, 15:35: Vacuum at 1.5E-5 T

Entry  Thursday, March 28, 2013, 13:55, Anders Mjos, Empty, , , , , , In progress, Pumping down empty chamber 

Thursday, March 28, 2013, 13:55: Roughing

Thursday, March 28, 2013, 14:36: Starting turbos (vacuum at ~0.100 T)

Thursday, March 28, 2013, 14:44: Both turbos at speed

Thursday, March 28, 2013, 14:46: Vacuum at 5.2E-6 Torr

Entry  Thursday, June 13, 2013, 10:19, Anders Mjos, , , , , , , Done, Pumping down empty chamber 

Thursday, June 13, 2013, 10:17: Roughing.

Thursday, June 13, 2013, 10:52: Turbos started

Thursday, June 13, 2013, 11:00 : Both turbos at speed.

Thursday, June 13, 2013, 11:02 : Vacuum at 7.5E-6 Torr

 

Entry  Friday, March 21, 2014, 13:55, Anders Mjos, , , , , , , In progress, Pumping down empty chamber 

Roughing

Friday, March 21, 2014, 13:59: Starting turbos

Friday, March 21, 2014, 14:08: Turbos at speed

Friday, March 21, 2014, 14:09: Vacuum at 7.5 E-6T

Entry  Friday, June 20, 2014, 11:44, Anders Mjos, , , , , , , In progress, Pumping down empty chamber 

Friday, June 20, 2014, 11:44: Roughing

Friday, June 20, 2014, 13:00: Strarting turbos 

Friday, June 20, 2014, 13:09: Turbos at speed.

Friday, June 20, 2014, 13:10 : Vacuum at 1.3E-5


Thursday, June 26, 2014, 08:52 : Turbos stopped. Vacuum at 1.3E-7 T

Thursday, June 26, 2014, 15:34: Venting 

Entry  Tuesday, October 07, 2014, 09:32, Anders Mjos, , , , , , , In progress, Pumping down empty chamber 

Tuesday, October 07, 2014, 09:30: Roughing

Tuesday, October 07, 2014, 10:24: Starting turbos

Tuesday, October 07, 2014, 10:32 : Turbos at speed. Vacuum at 3.3E-5 T

Entry  Tuesday, February 17, 2015, 14:41, Anders Mjos, , , , , , , In progress, Pumping down empty chamber 

Tuesday, February 17, 2015, 14:35: Roughing. Doors were difficult to get to seal.

Tuesday, February 17, 2015, 15:11: Started turbos

Tuesday, February 17, 2015, 15:34: Turbos at speed. Vacuum at 6.7E-6 T

Entry  Monday, July 06, 2015, 14:26, Anders Mjos, , , , , , , , Pumping down empty chamber 

Monday, July 06, 2015, 14:26: Roughing


Wednesday, July 08, 2015, 09:26: Venting


Thursday, July 09, 2015, 11:42: Roughing

Thursday, July 09, 2015, 13:16: Turbos started.


Friday, July 10, 2015, 08:54 : Stopped turbos

Friday, July 10, 2015, 11:29 : Venting

Friday, July 10, 2015, 16:56: Roughing

Entry  Thursday, August 16, 2012, 16:56, Anders Mjos, , , , , , , In progress, Pumping down after troubleshooting 

Thursday, August 16, 2012, 17:04 : Starting turbos

Thursday, August 16, 2012, 17:09 : TP1B at speed

Thursday, August 16, 2012, 17:13 : TP1A at speed (after 1 time out)

Thursday, August 16, 2012, 17:14 : Vacuum at 1.8E-5

Entry  Wednesday, July 11, 2012, 11:16, Anders Mjos, , , , , , , In progress, Pumping down - with new turbo pump 
 
Entry  Wednesday, September 12, 2012, 17:04, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Pumping down - w/replaced insulators 

Replaced swollen insulator and added Ta heat shield on insulator.

 

Wednesday, September 12, 2012, 17:03: Roughing

Wednesday, September 12, 2012, 17:23 : Starting turbos

Wednesday, September 12, 2012, 17:32 : Turbos at speed

Wednesday, September 12, 2012, 17:33 : Vacuum at 3.2E-5

Entry  Wednesday, July 04, 2012, 15:37, Anders Mjos, FEBIAD anode end cap test, , , , , , In progress, Pumping down  photo_8.jpg

Replaced grid containing ring (target side) with new ring. No contact between target and anode measured in lab.

NOTE: While closing up the VCR fittings the tube rotated causing the tube to flatten in a bend. This may reduce water flow on the heat shield circuit. (see attachment)

Wednesday, July 04, 2012, 15:33: Started roughing.

Wednesday, July 04, 2012, 15:57 : Started turbos

Wednesday, July 04, 2012, 16:03: Turbos at speed. Vacuum at 3E-5

Entry  Monday, July 16, 2012, 15:46, Anders Mjos, , , , , , , In progress, Pumping down 

Monday, July 16, 2012, 15:11: Roughing.

Monday, July 16, 2012, 15:38: Turbos started.

Monday, July 16, 2012, 15:46: TSGTP1B at speed TSGTP1A timeout.

Monday, July 16, 2012, 15:54: Both turbos at speed. Vacuum 3.6E-5.

 

Entry  Thursday, July 19, 2012, 11:32, Anders Mjos, , , , , , , Done, Pumping down 

Thursday, July 19, 2012, 11:29: roughing

Thursday, July 19, 2012, 11:49: starting turbos

Thursday, July 19, 2012, 11:54: TP1B at speed

Thursday, July 19, 2012, 11:58: TP1A timed out

Thursday, July 19, 2012, 11:58 TP1A restarted. at speed.

Thursday, July 19, 2012, 11:59: both turbos at speed. Vacuum. 2E-5

 

 

 

Entry  Thursday, October 25, 2012, 13:02, Anders Mjos, TiC#3, LP-SIS, ITW, TM1, , , In progress, Pumping down 

Thursday, October 25, 2012, 13:00: Roughing

Thursday, October 25, 2012, 13:19 : Turbos on

Thursday, October 25, 2012, 13:28 : Turbos at speed

Thursday, October 25, 2012, 13:29 : Vacuum at 1.6E-5 T

Entry  Monday, November 05, 2012, 14:42, Anders Mjos, Test SiC, HP-FEBIAD, , , , , Done, Pumping down 

Monday, November 05, 2012, 14:41: Roughing

Monday, November 05, 2012, 14:58: Started turbos

Monday, November 05, 2012, 15:06 : Turbos at speed

Monday, November 05, 2012, 15:068: Vacuum at 2.2E-5 T

Wednesday, November 07, 2012, 08:26: Cooling water open. Vacuum stable at 1.8E-7 T

Entry  Thursday, November 29, 2012, 16:21, Anders Mjos, , , , , , , , Pumping down 

Thursday, November 29, 2012, 16:21: Roughing

Entry  Tuesday, December 04, 2012, 17:27, Anders Mjos, RFQ empty, , , , , , In progress, Pumping down 

The RFQ heating test target was installed by Sebastian and Anders.

Tuesday, December 04, 2012, 17:26: roughing

Tuesday, December 04, 2012, 17:45: starting turbos

Tuesday, December 04, 2012, 17:55 : turbos at speed

Tuesday, December 04, 2012, 17:55 : vacuum at 3.3E-5 T

Entry  Friday, January 04, 2013, 15:07, Anders Mjos, RFQ empty, , , , , , In progress, Pumping down 

Friday, January 04, 2013, 15:04: Roughing

Friday, January 04, 2013, 15:24: Starting turbos

Friday, January 04, 2013, 15:33 : Turbos at speed

Friday, January 04, 2013, 15:34 : Vacuum at 1.7E-5 T