240
|
Tuesday, December 04, 2012, 11:05 |
Anders Mjos | | | | | | | | Vented | In preparation for RFQ target and leak
troubleshooting.
Tuesday, December 04, 2012, 11:04: |
|
|
241
|
Tuesday, December 04, 2012, 17:27 |
Anders Mjos | RFQ empty | | | | | | In progress | Pumping down | The RFQ heating test target was installed
by Sebastian and Anders.
Tuesday, December 04, 2012, 17:26: |
|
|
242
|
Wednesday, December 05, 2012, 11:18 |
Anders Mjos | | | | | | | In progress | Leak checking 9-pin feed through | Vacuum at 4.4E-7T
Base leak rate 2 - 3 E-9 mbar-l/sec
No response above background. |
|
|
243
|
Thursday, December 06, 2012, 08:41 |
Anders Mjos | | | | | | | | Opened cooling water | Vacuum stable at 2.8E-7 T |
|
|
246
|
Thursday, December 13, 2012, 08:40 |
Anders Mjos | RFQ empty | | | | | | In progress | Venting | Thursday, December 13, 2012, 08:38: TBHT
and TGHT off
Thursday, December 13, 2012, 08:38 : |
|
|
247
|
Thursday, December 13, 2012, 14:38 |
Anders Mjos | | | | | | | | Pumping down empty chamber | Thursday, December 13, 2012, 14:36: Roughing
Thursday, December 13, 2012, 14:56
: Starting turbos |
|
|
249
|
Friday, December 14, 2012, 15:28 |
Anders Mjos | RFQ empty | | | | | | In progress | Venting |
|
|
|
255
|
Wednesday, December 19, 2012, 11:24 |
Anders Mjos | | | | | | | Problems/Solutions | Restarted turbos in TMS section after power bump | Sources arch restared |
|
|
257
|
Thursday, December 20, 2012, 14:19 |
Anders Mjos | | | | | | | | Power down for holidays | |
|
|
258
|
Thursday, January 03, 2013, 08:33 |
Anders Mjos | | | | | | | Problems/Solutions | Started archivers after holiday shut down | Started archivers. Controls whited out. |
|
|
259
|
Thursday, January 03, 2013, 11:39 |
Anders Mjos | | | | | | | Problems/Solutions | Starting pumps after holiday shut down - TMSRP2 replaced | Thursday,
January 03, 2013, 11:28: TMSRP2 is noisy.
Stopped. |
|
|
260
|
Friday, January 04, 2013, 10:52 |
Anders Mjos | | | | | | | In progress | Preparing for venting | Friday, January 04, 2013, 10:51:
Vacuum at 3.2E-7 T
Friday, January 04, 2013, 10:52: |
|
|
261
|
Friday, January 04, 2013, 15:07 |
Anders Mjos | RFQ empty | | | | | | In progress | Pumping down | Friday, January 04, 2013, 15:04: Roughing
Friday, January 04, 2013, 15:24:
Starting turbos |
|
|
263
|
Wednesday, January 09, 2013, 10:39 |
Anders Mjos | RFQ empty | | | | | | In progress | Venting | Wednesday, January 09, 2013, 10:38:
Turbos off. Vacuum at 1.7 E-7 T
Wednesday, January 09, 2013, 13:24 |
|
|
264
|
Wednesday, January 09, 2013, 14:13 |
Anders Mjos | Empty | | | | | | | Rouging | Wednesday, January 09, 2013, 14:12: Roughing
empty chamber |
|
|
265
|
Friday, January 11, 2013, 08:37 |
Anders Mjos | Empty | | | | | | In progress | Venting | Friday, January 11, 2013, 08:36: Venting
for installation of RFQ test target later
today |
|
|
266
|
Friday, January 11, 2013, 11:02 |
Anders Mjos | RFQ empty | | | | | | | Target installed, pumping down | Target installed with 120 in lbs torque
on target legs and on central support.
Friday, January 11, 2013, 11:01: |
|
|
270
|
Tuesday, January 15, 2013, 16:10 |
Anders Mjos | RFQ empty | | | | | | | Turbos off |
|
|
|
274
|
Friday, January 18, 2013, 15:34 |
Anders Mjos | empty | | | | | | | Pumping down empty chamber | Started roughing
Friday, January 18, 2013, 15:25:
Started turbos |
|
|
275
|
Friday, January 18, 2013, 15:57 |
Anders Mjos | | | | | | | Problems/Solutions | Conductor bolts to be replaced | After the last test at the test stand,
one of the conductor bolts (ITD0058) is damaged.
To prevent damage to the thread inserts, |
|
|