  Test-Stand, Page 22 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
  ID Date Authordown Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  240   Tuesday, December 04, 2012, 11:05 Anders Mjos       VentedIn preparation for RFQ target and leak
troubleshooting.
Tuesday, December 04, 2012, 11:04:
  
  241   Tuesday, December 04, 2012, 17:27 Anders MjosRFQ empty     In progressPumping downThe RFQ heating test target was installed
by Sebastian and Anders.
Tuesday, December 04, 2012, 17:26:
  
  242   Wednesday, December 05, 2012, 11:18 Anders Mjos      In progressLeak checking 9-pin feed throughVacuum at 4.4E-7T
Base leak rate 2 - 3 E-9 mbar-l/sec
No response above background.
  
  243   Thursday, December 06, 2012, 08:41 Anders Mjos       Opened cooling waterVacuum stable at 2.8E-7 T   
  246   Thursday, December 13, 2012, 08:40 Anders MjosRFQ empty     In progressVentingThursday, December 13, 2012, 08:38: TBHT
and TGHT off
Thursday, December 13, 2012, 08:38 :
  
  247   Thursday, December 13, 2012, 14:38 Anders Mjos       Pumping down empty chamberThursday, December 13, 2012, 14:36: Roughing
Thursday, December 13, 2012, 14:56
: Starting turbos
  
  249   Friday, December 14, 2012, 15:28 Anders MjosRFQ empty     In progressVenting

    

       
            
  
  255   Wednesday, December 19, 2012, 11:24 Anders Mjos      Problems/SolutionsRestarted turbos in TMS section after power bumpSources arch restared   
  257   Thursday, December 20, 2012, 14:19 Anders Mjos       Power down for holidays    
  258   Thursday, January 03, 2013, 08:33 Anders Mjos      Problems/SolutionsStarted archivers after holiday shut downStarted archivers. Controls whited out.   
  259   Thursday, January 03, 2013, 11:39 Anders Mjos      Problems/SolutionsStarting pumps after holiday shut down - TMSRP2 replacedThursday,
January 03, 2013, 11:28: TMSRP2 is noisy.
Stopped.
  
  260   Friday, January 04, 2013, 10:52 Anders Mjos      In progressPreparing for venting Friday, January 04, 2013, 10:51:
Vacuum at 3.2E-7 T
Friday, January 04, 2013, 10:52:
  
  261   Friday, January 04, 2013, 15:07 Anders MjosRFQ empty     In progressPumping downFriday, January 04, 2013, 15:04: Roughing
Friday, January 04, 2013, 15:24:
Starting turbos
  
  263   Wednesday, January 09, 2013, 10:39 Anders MjosRFQ empty     In progressVenting Wednesday, January 09, 2013, 10:38:
Turbos off. Vacuum at 1.7 E-7 T
Wednesday, January 09, 2013, 13:24
  
  264   Wednesday, January 09, 2013, 14:13 Anders MjosEmpty      RougingWednesday, January 09, 2013, 14:12: Roughing
empty chamber
  
  265   Friday, January 11, 2013, 08:37 Anders MjosEmpty     In progressVentingFriday, January 11, 2013, 08:36: Venting
for installation of RFQ test target later
today
  
  266   Friday, January 11, 2013, 11:02 Anders MjosRFQ empty      Target installed, pumping downTarget installed with 120 in lbs torque
on target legs and on central support.
Friday, January 11, 2013, 11:01:
  
  270   Tuesday, January 15, 2013, 16:10 Anders MjosRFQ empty      Turbos off

    

       
            
  
  274   Friday, January 18, 2013, 15:34 Anders Mjosempty      Pumping down empty chamberStarted roughing
Friday, January 18, 2013, 15:25:
Started turbos
  
  275   Friday, January 18, 2013, 15:57 Anders Mjos      Problems/SolutionsConductor bolts to be replacedAfter the last test at the test stand,
one of the conductor bolts (ITD0058) is damaged.
To prevent damage to the thread inserts,
 Model.jpgdamaged_bolt.JPG 