  189   Friday, August 31, 2012, 10:19 Anders Mjos      Problems/SolutionsReplaced TMSRP2 (again)

Anders Mjos wrote:

Thursday, August 23, 2012, 10:40: Replacing TMSRP2 with Edi. E-fault 6261.

Thursday, August 23, 2012, 10:49: TMSRP2 replaced and started.

Edi will replace TMSRP2 again as it became noisy since yesterday morning. Vacuum should not be affected by the work.

  190   Friday, August 31, 2012, 11:12 Aurelia Laxdal HP-FEBIADITETM4  DoneFinished testing NiO#1

Turned off the HV and the optics in the first section. Couldn't turn off the optics in the second section: left a message for Evgeniy.

Also TMS:RP2 is very noisy. Talked to Edi D. from vacuum group. He would work on it this afternoon. E-Fault#6282

  191   Friday, August 31, 2012, 11:39 Anders MjosNiO#1HP-FEBIADITETM4  DoneVenting vacuum chamber - source change

Friday, August 31, 2012, 11:39: Stopped turbos.

Friday, August 31, 2012, 13:06: Venting.

Friday, August 31, 2012, 13:23: Water lines purged.

Friday, August 31, 2012, 13:25 : Vented

  192   Friday, August 31, 2012, 13:59 Anders MjosNb#7LP-SISITWTM1  In progressNb#7 installed

Friday, August 31, 2012, 15:19: roughing

Friday, August 31, 2012, 15:39 : starting turbos

Friday, August 31, 2012, 15:44 : TP1B at speed

Friday, August 31, 2012, 15:48 : TP1A timed out

Friday, August 31, 2012, 15:48 : TP1A restarted. at speed.

Friday, August 31, 2012, 15:49 : both turbos at speed. Vacuum @2.7E-5

  193   Tuesday, September 04, 2012, 08:11 Anders MjosNb#7LP-SISITWTM1  DoneNb#7 installed

Anders Mjos wrote:

Friday, August 31, 2012, 15:19: roughing

Friday, August 31, 2012, 15:39 : starting turbos

Friday, August 31, 2012, 15:44 : TP1B at speed

Friday, August 31, 2012, 15:48 : TP1A timed out

Friday, August 31, 2012, 15:48 : TP1A restarted. at speed.

Friday, August 31, 2012, 15:49 : both turbos at speed. Vacuum @2.7E-5

 Tuesday, September 04, 2012, 08:10: Opened cooling water. Vacuum stable @ 2.2E-7

  194   Thursday, September 06, 2012, 09:23 Friedhelm AmesNB#7       

start high voltage and heaters

  195   Friday, September 07, 2012, 12:11 Friedhelm AmesNB#7LP-SIS    In progressmass scan started

mass scan has been started after optimization on 23Na

  196   Friday, September 07, 2012, 13:10 Friedhelm AmesNb#7     Donemass scan finished

mass scan is finished saved as

http://isacwserv.triumf.ca/onlylocal/isactdata/save_restore/masscorr/plotdump-local-clean.txt_Sep7_12_13-01-51.txt

  197   Friday, September 07, 2012, 14:34 Anders MjosNb#7LP-SISITWTM1  Problems/SolutionsInsulator ITD0342 overheated - swelling

 See attached photo

Attachment 1: Nb#7_swelling_insulator.pdf
Nb#7_swelling_insulator.pdf
  198   Tuesday, September 11, 2012, 13:13 Friedhelm AmesNb#7LP-SIS    In progressstart cool down

start cooldown. Found computer at teststand off. Somebody tried to login with username ARIEL.

  199   Tuesday, September 11, 2012, 19:48 Friedhelm AmesNB#7HP-SIS    Donecool down finished, all source power supplies off.
  200   Wednesday, September 12, 2012, 08:02 Anders MjosNb#7LP-SISITWTM1  In progressVenting

Wednesday, September 12, 2012, 08:01: Turbos off

Wednesday, September 12, 2012, 13:35: Venting, water off and purged.

Wednesday, September 12, 2012, 13:55: Vented

  201   Wednesday, September 12, 2012, 17:04 Anders MjosNb#7LP-SISITWTM1  In progressPumping down - w/replaced insulators

Replaced swollen insulator and added Ta heat shield on insulator.

 

Wednesday, September 12, 2012, 17:03: Roughing

Wednesday, September 12, 2012, 17:23 : Starting turbos

Wednesday, September 12, 2012, 17:32 : Turbos at speed

Wednesday, September 12, 2012, 17:33 : Vacuum at 3.2E-5

  202   Thursday, September 13, 2012, 08:24 Anders MjosNb#7LP-SISITWTM1  In progressWater on

Thursday, September 13, 2012, 08:16: Opened up cooling water. Vacuum (IG1) increased from 5.9E-7 to 6.2E-7 before returning to 5.9E-7. Similar response on IG6 (valve closed). Response is however similar to previous (short time ~5 min) vacuum fluctuations.

  203   Thursday, September 13, 2012, 13:05 Friedhelm AmesNb#7LP-SIS     heater ramping up started
  204   Friday, September 14, 2012, 15:27 Anders MjosNb#7LP-SISITWTM1  DoneVenting

Target cooled down. Power supplies off.

Friday, September 14, 2012, 15:27: Turbos off.

Friday, September 14, 2012, 15:32: Water purged.

 Friday, September 14, 2012, 16:00: Venting

Friday, September 14, 2012, 16:26: Vented

  205   Friday, September 14, 2012, 16:33 Anders Mjos      In progressPumping down empty chamber

Friday, September 14, 2012, 16:33: Roughing

Friday, September 14, 2012, 16:57: Starting turbos

Friday, September 14, 2012, 17:05 : Turbos at speed

Friday, September 14, 2012, 17:07: Vacuum at 8.7E-6

 

  206   Thursday, September 20, 2012, 14:24 Anders Mjos      In progressVenting - installation of FEBIAD test target for operator training

Thursday, September 20, 2012, 14:24: Turbos off

Thursday, September 20, 2012, 15:20: Venting

  207   Thursday, September 20, 2012, 15:52 Anders MjosTEST SiCHP-FEBIAD    In progressInstallilng SiC-HP-FEBIAD target for operator training

Thursday, September 20, 2012, 15:50: Roughing

Thursday, September 20, 2012, 15:54: Aborting. VCR for gas line not connected.

Thursday, September 20, 2012, 16:09: Roughing

Thursday, September 20, 2012, 16:29: Starting turbos

Thursday, September 20, 2012, 16:38 : Turbos at speed

Thursday, September 20, 2012, 16:39 : Vacuum at 1.3E-5 torr

 

  208   Friday, September 21, 2012, 08:20 Anders MjosTEST SiCHP-FEBIAD    In progressInstallilng SiC-HP-FEBIAD target for operator training

Anders Mjos wrote:

Thursday, September 20, 2012, 15:50: Roughing

Thursday, September 20, 2012, 15:54: Aborting. VCR for gas line not connected.

Thursday, September 20, 2012, 16:09: Roughing

Thursday, September 20, 2012, 16:29: Starting turbos

Thursday, September 20, 2012, 16:38 : Turbos at speed

Thursday, September 20, 2012, 16:39 : Vacuum at 1.3E-5 torr

 

 Friday, September 21, 2012, 08:19: Cooling water on. Vacuum stable at 2.3E-7 torr.