ID Date Author Target/No.# Source Station Moduledown Target Oven W.O# Heat Shield W.O# Status Subject
  216   Thursday, September 27, 2012, 12:27 Aurelia Laxdal      In progressSiC-HP-FEBIAD for operator training

The source was used yesterday for operator training.

Today, I found the source off: the ISAC PLC Status was stopped. Kazuya re-started the PLC. I will re-start the source.

  217   Friday, September 28, 2012, 09:59 Aurelia Laxdal      In progressSiC-HP-FEBIAD for operator training - Source Off

Checked with ISAC Ops this morning and they are not available for FEBIAD training. Turned off the source until next week.

  218   Monday, October 01, 2012, 10:41 Aurelia Laxdal HP-FEBIAD    In progressSiC-HP-FEBIAD for operator training - Source ON

Turned the source back ON. Heaters are ramping up.

  219   Wednesday, October 03, 2012, 13:50 Aurelia Laxdal HP-FEBIAD    In progressTraining updates

On Monday October 1, the HP-FEBIAD source was turned ON again, to complete the operator training. The last session was yesterday and for the time being the ISAC operators can play with the source when time allows, and from the ISAC Control room. For this purpose the source will be kept on this week and also over the week-end.

  220   Wednesday, October 10, 2012, 10:47 Friedhelm Ames      Failedfound teststand tripped off

turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown.

  221   Wednesday, October 10, 2012, 17:35 Aurelia Laxdal      Failedfound teststand tripped off

Friedhelm Ames wrote:

turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown.

 Checked the Archiver and the striptool: TSG:TP1A & TP1B tripped on Oct. 10, at 7:53am. Both pumps showed timeout, but the AC breakers were not tripped. Also, checked with MCR: they were no power bumps or cooling water problems around that time. 

Discussed it with Kazuya Negishi from Controls: there were no PLC problems. Kazuya and I would monitor the trips. 

  222   Thursday, October 25, 2012, 11:13 Anders MjosTestHP-FEBIAD    In progressVenting chamber for installation of TiC#3

Thursday, October 25, 2012, 11:11: Vacuum at 1.3E-7 T

Thursday, October 25, 2012, 11:12: Turbos off

Thursday, October 25, 2012, 11:50: Venting

  232   Monday, November 05, 2012, 14:42 Anders MjosTest SiCHP-FEBIAD    DonePumping down

Monday, November 05, 2012, 14:41: Roughing

Monday, November 05, 2012, 14:58: Started turbos

Monday, November 05, 2012, 15:06 : Turbos at speed

Monday, November 05, 2012, 15:068: Vacuum at 2.2E-5 T

Wednesday, November 07, 2012, 08:26: Cooling water open. Vacuum stable at 1.8E-7 T

  233   Monday, November 19, 2012, 10:20 Aurelia LaxdalTest-SiCHP-FEBIAD     Preparations for E-Fault#6389 investigations

Prepared the Test Stand for Controls to investigate E-Fault#6389.


Evgeniy increased the current limit on the power supply TSH:TGHT from 2 rotations to 7 rotations, after talking to Ray Dube.

I turned on the HV at 30kV and started the Auto-ramping.

  234   Thursday, November 22, 2012, 12:52 Aurelia LaxdalTest-SiCHP-FEBIAD     E-Fault#6389 re-directed to PS

Evgeniy and Kazuya investigated the problem with TSH:TGHT readbacks and they came to the conclusion that the PS is faulty, and the PLC reads correctly the signal sent by the PS.  Kazuya is redirecting the E-Fault from Controls to PS.

Ray Dube estimated few weeks (4-6) to send the PS offsite for repairs. This needs to be scheduled. For the time being, one can use the Test Stand with the PS setpoints, displayed on its front panel, as a reference.

  235   Thursday, November 29, 2012, 14:15 Anders Mjos      In progressVenting in preparation for RFQ work

 Thursday, November 29, 2012, 14:15: Stopping turbos

Thursday, November 29, 2012, 15:57: Venting

  236   Thursday, November 29, 2012, 16:21 Anders Mjos       Pumping down

Thursday, November 29, 2012, 16:21: Roughing

  237   Friday, November 30, 2012, 10:42 Anders Mjos       Venting
  238   Friday, November 30, 2012, 12:04 Anders Mjos      In progress9-pin connector installation work in progress

in preparation for RFQ testing. By Sebastian and Anders

An insulated  9-pin D-sub connector was installed on the service cap in port Q (as labeled in ISK4523). The connector mating to the target assembly was placed in the upper slot on the source tray.

Friday, November 30, 2012, 14:57: Rouging in preparation for leak check (next week).

Friday, November 30, 2012, 15:16: Turbos on

Friday, November 30, 2012, 15:25 : Turbos at speed

Friday, November 30, 2012, 15:26 : Vacuum at 3.4E-5 T

  239   Monday, December 03, 2012, 15:33 Anders Mjos      In progressLeak check of 9-pin feed through

Base leak rate 6 - 7 E-9 mbar-l/s

A leak was found around the 9-pin feed through.

  240   Tuesday, December 04, 2012, 11:05 Anders Mjos       Vented

In preparation for RFQ target and leak troubleshooting.

Tuesday, December 04, 2012, 11:04: Turbos off (vacuum at 3.8E-7 T)

Water lines purged.

Tuesday, December 04, 2012, 15:03: Venting

Tuesday, December 04, 2012, 15:32 : Vented

  241   Tuesday, December 04, 2012, 17:27 Anders MjosRFQ empty     In progressPumping down

The RFQ heating test target was installed by Sebastian and Anders.

Tuesday, December 04, 2012, 17:26: roughing

Tuesday, December 04, 2012, 17:45: starting turbos

Tuesday, December 04, 2012, 17:55 : turbos at speed

Tuesday, December 04, 2012, 17:55 : vacuum at 3.3E-5 T

  242   Wednesday, December 05, 2012, 11:18 Anders Mjos      In progressLeak checking 9-pin feed through

Vacuum at 4.4E-7T

Base leak rate 2 - 3 E-9 mbar-l/sec

No response above background.

  243   Thursday, December 06, 2012, 08:41 Anders Mjos       Opened cooling water

Vacuum stable at 2.8E-7 T

  244   Tuesday, December 11, 2012, 13:27 Sebastian Raeder       9 PIN connector

A Sub D 9 Pin connector on a HV insulator was installed on Port Q of the target box at the teststand. The insulator is leak tested and OK, vacuum is below 2E-7 T

The feed through is connected (1to1) to the upper 9 Pin connector of the target tray. Since the existing upper 9 Pin connector was damaged from a previous FEBIAD test, this connector was replaced. For wiring 4 twisted pair Capton insulated and shielded wires (identical to ITE and TM4) of about 50cm length are used.

 

View on top of the feedthrough and the connector on the source tray (male connectors)

     __________________

    \    1     2      3      4      5   /

      \     6      7     8      9    /

          ----------------------  

1to1 connection for pins 1,2,4-9

Pin 3 is NOT CONNCTED

The pin pairs 1&2, 4&5, 6&7, 8&9 each use a line of twisted pairs

 

Monday, December 17, 2012, 22:21

Connection to the HV added. The wires end in the HV cage on a screw terminal with labels 1--12. The numbers 1,2,4-9 are used in corresponding notation to the sketch above. Since 3 is not connected at all this terminal is used for grounding the wire shielding.

As cable 2 Capton isolated pairs of wire (1&2, 4&5) and two "normal" pairs for thermocouple (6&7, 8&9) reading are used. So all connections have shielded twisted pair cable, while  (6&7, 8&9)change the cable type at the 9Pin connector