Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 19 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Authordown Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subject
  106   Tuesday, June 26, 2012, 18:04 Anders MjosFEBIAD anode end cap test   Tube only38307-9In progressFEBIAD anode end cap test - ready

Testing FEBIAD anode end cap as per dwg ITD0304 REV C

Target with TUBE ONLY. Do not use target heater.


Tuesday, June 26, 2012, 18:03: Roughing

Tuesday, June 26, 2012, 18:24: Turbos started

Tuesday, June 26, 2012, 18:31 : Turbos at speed. Vacuum at 1.8E-5

Wednesday, June 27, 2012, 08:48: Cooling opened. Vacuum stable at 4.2E-7. Ready for testing.

 

  107   Tuesday, June 26, 2012, 18:30 Anders Mjos      Problems/SolutionsCrack in source tray insulator

 A crack in the insulator ITD0054 was observed while mounting the target assembly. See attachment.

Attachment 1: Cracked_insulator.pdf
Cracked_insulator.pdf
  124   Wednesday, July 04, 2012, 13:07 Anders Mjos      Problems/Solutionswater lines purged

Friedhelm Ames wrote:

turbo pumps stopped to prepare for venting for anode short investigation.

 Wednesday, July 04, 2012, 13:07: Water lines purged

  125   Wednesday, July 04, 2012, 15:33 Anders Mjos      Problems/Solutionsshort in anode

Friedhelm Ames wrote:

A short in the anode has developed during the heater ramp up. Increasing the current limit did not cure it. Start heater ramp down to investigate.

 Wednesday, July 04, 2012: short found between anode and target. probably caused by the target tube coming in contact with the anode due to bending of the tube caused by heating and deformation of the grid retaining ring. see attachements

Attachment 1: photo_1.JPG
photo_1.JPG
Attachment 2: photo_3.JPG
photo_3.JPG
  126   Wednesday, July 04, 2012, 15:37 Anders MjosFEBIAD anode end cap test     In progressPumping down

Replaced grid containing ring (target side) with new ring. No contact between target and anode measured in lab.

NOTE: While closing up the VCR fittings the tube rotated causing the tube to flatten in a bend. This may reduce water flow on the heat shield circuit. (see attachment)

Wednesday, July 04, 2012, 15:33: Started roughing.

Wednesday, July 04, 2012, 15:57 : Started turbos

Wednesday, July 04, 2012, 16:03: Turbos at speed. Vacuum at 3E-5

Attachment 1: photo_8.jpg
photo_8.jpg
  127   Thursday, July 05, 2012, 08:41 Anders MjosFEBIAD anode end cap test     In progressWater opened - reduced flow heat shield

Anders Mjos wrote:

Replaced grid containing ring (target side) with new ring. No contact between target and anode measured in lab.

NOTE: While closing up the VCR fittings the tube rotated causing the tube to flatten in a bend. This may reduce water flow on the heat shield circuit. (see attachment)

Wednesday, July 04, 2012, 15:33: Started roughing.

Wednesday, July 04, 2012, 15:57 : Started turbos

Wednesday, July 04, 2012, 16:03: Turbos at speed. Vacuum at 3E-5

 Thursday, July 05, 2012, 08:39: Water supply open. Vacuum stable at 5.9E-7. Due to the kink in the heat shield cooling line, flow in the heat shield line is lower than other lines (visually inspecting speed of paddle wheels).

  137   Monday, July 09, 2012, 12:57 Anders Mjos      DoneVented
  138   Tuesday, July 10, 2012, 16:01 Anders Mjos      Problems/SolutionsTurbo replaced - cleaning chamber recommended

A new turbo has been installed. Eddie said the other one had crashed but not catastrophically. He recommends the test stand be wiped clean before pumping because there is a fine layer of Aluminum dust on the chamber base.

 

  139   Wednesday, July 11, 2012, 11:16 Anders Mjos      In progressPumping down - with new turbo pump
  140   Wednesday, July 11, 2012, 15:30 Anders Mjos      Problems/SolutionsRestarting turbos after power bump

Wednesday, July 11, 2012, 15:27: Started TSGTP1A and 1B

Wednesday, July 11, 2012, 15:31: Started TSMTP2 and 6

Wednesday, July 11, 2012, 15:33: TMS tubos at speed. Vacuum 4.8E-7

Wednesday, July 11, 2012, 15:34: TSG turbos at speed. Vacuum 9.5E-6

  141   Thursday, July 12, 2012, 09:05 Anders Mjos      Problems/SolutionsShut down TSGTP1A - bearing noise

Shut down TSGTP1A due to noise (possibly from bearings) after consulting Edi.

  142   Thursday, July 12, 2012, 09:44 Anders Mjos      In progressVenting

System will be vented and gas lines purged with air, then nitrogen.

Thursday, July 12, 2012, 09:43: Shut down TSGTP1B.

  143   Thursday, July 12, 2012, 12:23 Anders Mjos      DoneTSH:SV5 bypass on

Thursday, July 12, 2012, 15:48: bypass removed

  144   Thursday, July 12, 2012, 13:41 Anders Mjos      Donepurging gas lines with air
  • gas lines purged with air for 60 min (through TSHUHV1 and TSHSV4).
  • gas line allowed to fill with nitrogen to 300 torr and evacuated. repeated 3 times.
  145   Thursday, July 12, 2012, 13:49 Anders Mjos      Problems/SolutionsAluminum oxide found inside TSHSV1

Aluminum oxide found inside TSHSV1 and the copper line to TSHUHV1.

SV1 replaced and copper line cleaned.

  146   Thursday, July 12, 2012, 15:49 Anders Mjos       test stand vented for TP1A replacement

see e-fault 6142

  147   Monday, July 16, 2012, 15:46 Anders Mjos      In progressPumping down

Monday, July 16, 2012, 15:11: Roughing.

Monday, July 16, 2012, 15:38: Turbos started.

Monday, July 16, 2012, 15:46: TSGTP1B at speed TSGTP1A timeout.

Monday, July 16, 2012, 15:54: Both turbos at speed. Vacuum 3.6E-5.

 

  148   Tuesday, July 17, 2012, 10:10 Anders Mjos      Problems/SolutionsGas lines leak checked - air supply leak on manifold

Leak found on the Ne supply line. 1E-4 - 1E-5 range. Replaced fittings. Had to use one brass piece. Leak rate 6E-9 (probably due to Ne response). No response to He.

Leak rate around low E-8 with regulation valve open.

When closing the HV rack, an air supply leak developed on the manifold for the valves. Shut off air supply. Valves still operational, but requires opening up air supply to actuate.

 

  149   Wednesday, July 18, 2012, 14:08 Anders Mjos      Problems/SolutionsAir supply leak on manifold fixed

Anders Mjos wrote:

Leak found on the Ne supply line. 1E-4 - 1E-5 range. Replaced fittings. Had to use one brass piece. Leak rate 6E-9 (probably due to Ne response). No response to He.

Leak rate around low E-8 with regulation valve open.

When closing the HV rack, an air supply leak developed on the manifold for the valves. Shut off air supply. Valves still operational, but requires opening up air supply to actuate.

 

 With the help of Rick, the leak was fixed.

The vacuum pump for the gas lines was removed for repairing the leaking hose.

  150   Thursday, July 19, 2012, 08:42 Anders Mjos      Problems/SolutionsLeak checking source chamber - leak found on front door

Due to high vacuum a leak check will be done on the system.

Thursday, July 19, 2012, 09:00 : Base leak rate 4E-9 atm-cc/sec

Thursday, July 19, 2012, 09:07: Leak detected on side door. Mid 1E-8 range.

Thursday, July 19, 2012, 09:08: Leak detected on front door. Mid 1E-6 range. Main leak left or bottom side.

Thursday, July 19, 2012, 09:20: Leak on side door could not be reproduced. Previous response possibly due to  "cross-talk" with front door.

ELOG V2.9.2-2455