  83   Monday, May 14, 2012, 15:36 Aurelia Laxdal       Test Stand - IOC rebootDid a local IOC reboot to cure to white-out.
The test stand is now operational.
  
  84   Monday, May 14, 2012, 16:57 Aurelia Laxdal  ITETM4   SiC#27-HP-SIS installed in the Test StandRick and John installed the ITE-TM4-SiC#27-HP-SIS-May2012
in the Test Stand. Pumping down.
  
  85   Tuesday, May 15, 2012, 07:39 Rick MaharajSic #27HP-SISITETM4  In progressWater on at test standThe vacuum on TSGIG1 reads 2.85e-07. Turing
on water on teststand and observing any changes
in vacuum pressure.
  
  86   Tuesday, May 15, 2012, 08:08 Rick Maharajsic#27      Turbos offTarget needs to be removed form teststand
to remove heatshielding around target oven.
The chamber will be vented, water circuits
  
  87   Tuesday, May 15, 2012, 08:15 Rick Maharaj       Test Stand chamber venting    
  88   Tuesday, May 15, 2012, 08:16 Rick Maharaj       Water circuits flushed    
  89   Tuesday, May 15, 2012, 08:42 Rick Maharaj       target removed    
  90   Tuesday, May 15, 2012, 09:46 Rick Maharaj       target reinstalled pumping started    
  91   Tuesday, May 15, 2012, 10:14 Anders MjosSiC#27HP-SISITETM4  In progresstarget ready to be heated and biased Tuesday, May 15, 2012, 10:13: Turbo
pumps at speed. Vacuum at 1.4E-5.
Tuesday, May 15, 2012, 12:03: Cooling
  
  92   Tuesday, May 15, 2012, 16:18 Aurelia LaxdalSiC#27HP-SISITETM4  In progressTarget/Ion source conditioningDid the HV conditioning up to 30kV and
started to ramp up the heaters to 580A and
230A.
  
  93   Wednesday, May 16, 2012, 16:01 Anders Mjos      Problems/SolutionsLoose chip of insulator material detected A chip of insulator material was
detected below the lower target insulator
stand-off (attachment - left picture). The
 Ceramic_Chip.pdf 
  94   Wednesday, May 16, 2012, 18:10 Aurelia Laxdal  ITETM4   SiC#27 cooling downToday: did a mass scan at 580A on TGHT
and 230A on TBHT at 30kV. Found some A/q
units discrepancies on the mass scan page.
  
  95   Wednesday, May 16, 2012, 19:55 Friedhelm Ames      Problems/SolutionsHall probe reading wrongDuring the mass scan today it was discovered,
that the mass calibration was off. Further
investigation showed, that the Hall probe
  
  96   Thursday, May 17, 2012, 08:36 Anders MjosSiC#27HP-SISITETM4  DoneTarget removedThursday, May 17, 2012, 08:36: Turbo pumps
switched off in preparation of target removal.
Thursday, May 17, 2012, 08:51: Purging
  
  97   Thursday, May 17, 2012, 12:19 Anders MjosSiC#27HP-SISITETM4  Problems/SolutionsLoose chip of insulator material detected

    

       
            
 Chipped_insulator_stand-off.pdf 
  99   Thursday, May 17, 2012, 15:14 Anders Mjos       Pumping down empty chamberThursday, May 17, 2012, 15:14: Started
roughing. Cooling lines blanked off.
Thursday, May 17, 2012, 16:52: Starting
  
  100   Thursday, May 31, 2012, 14:46 Anders Mjos       Venting in preparation for Ta#38Thursday, May 31, 2012, 14:46: Switching
off turbos
Thursday, May 31, 2012, 15:05: Venting
  
  101   Thursday, May 31, 2012, 15:43 Anders MjosTa#38LP-SISITWTM1  In progressTarget ready to be heatedThursday, May 31, 2012, 15:42: Roughing
Thursday, May 31, 2012, 16:01 : Starting
turbos
  
  102   Friday, June 01, 2012, 12:23 Aurelia LaxdalTa#38LP-SISITWTM1  In progressHV & Heaters conditioning.Did the HV conditioning.
Heaters conditioning in progress.
The Hall probe is not working: couldn't
  
  103   Monday, June 04, 2012, 10:51 Anders MjosTa#38LP-SISITWTM1  DoneVenting chamber

    

       
            
  
ELOG V2.9.2-2455