  115   Thursday, June 28, 2012, 17:18 Pierre Bricault LP-FEBIAD    In progressLeave the cathode heater at 275 A overninght.    
  116   Friday, June 29, 2012, 08:57 Pierre Bricault LP-FEBIAD    In progressContinue cathode heating This morning the pressure was 3.5E-7
T. Current at 275 A is 30nA.
Continue cathode heating to 290 A
  
  117   Friday, June 29, 2012, 13:39 Friedhelm Ames       start mass scanstart mass scan to do new mass calibration   
  118   Friday, June 29, 2012, 15:02 Friedhelm Ames       mass scan finishedmass spectrum saved as
plotdump-local-clean.txt_Jun29_12_14-55-43.txt


 mass_spectrum_2012_06_29.PNG 
  119   Friday, June 29, 2012, 15:03 Friedhelm Ames       start ramping down heater    
  120   Friday, June 29, 2012, 16:39 Friedhelm Ames       mass scan finished

    

       
            
  
  121   Tuesday, July 03, 2012, 09:23 Friedhelm Ames      In progressstart up againpurged Ne line and started cathode heater
ramp up to 295 A
  
  122   Tuesday, July 03, 2012, 19:05 Friedhelm Ames      Problems/Solutionsshort in anodeA short in the anode has developed during
the heater ramp up. Increasing the current
limit did not cure it. Start heater ramp
  
  123   Wednesday, July 04, 2012, 09:22 Friedhelm Ames      Problems/Solutionsturbo pumps stoppedturbo pumps stopped to prepare for venting
for anode short investigation.
  
  124   Wednesday, July 04, 2012, 13:07 Anders Mjos      Problems/Solutionswater lines purged

    

       
            
  
  125   Wednesday, July 04, 2012, 15:33 Anders Mjos      Problems/Solutionsshort in anode

    

       
            
 photo_1.JPGphoto_3.JPG 
  126   Wednesday, July 04, 2012, 15:37 Anders MjosFEBIAD anode end cap test     In progressPumping down Replaced grid containing ring (target side)
with new ring. No contact between target
and anode measured in lab.
 photo_8.jpg 
  127   Thursday, July 05, 2012, 08:41 Anders MjosFEBIAD anode end cap test     In progressWater opened - reduced flow heat shield

    

       
            
  
  128   Thursday, July 05, 2012, 10:59 Friedhelm Ames      Problems/Solutionswater tripping in front of HV power suppliesFound some water tripping in front of the
high voltage power supplies rack from the
water lines at the ceiling. Plastic sheets
  
  129   Thursday, July 05, 2012, 11:00 Friedhelm Ames      In progresssource started up againtube heater ramping started   
  130   Thursday, July 05, 2012, 18:02 Friedhelm Ames      Problems/Solutionsfluctuations in magnet currentThe current at the magnet power supply
TMS:MB1 shows fluctuations every 1-2 minutes.
The same can be seen in the Hall probe read
 TMSMB1_2012_07_05.PNG 
  131   Thursday, July 05, 2012, 18:10 Friedhelm Ames      Problems/Solutionsfluctuations in magnet current

    

       
            
  
  132   Friday, July 06, 2012, 11:04 Friedhelm Ames       source tripped off over nightA big vacuum excursion tripped the source
off at about 1am. The vacuum did not fully
recover afterwards only down to about 1.3e-6T.
  
  133   Friday, July 06, 2012, 11:05 Friedhelm Ames       start source againheater ramping up again with Ne leak closed.   
  134   Friday, July 06, 2012, 11:18 Friedhelm Ames       TSG:TP1B off source off again.turbo pump TSG:TP1B has tripped off. Cannot
be restarted. Fault report to vacuum. Everything
switched off again
  