Entry  Tuesday, May 15, 2012, 08:08, Rick Maharaj, sic#27, , , , , , , Turbos off 
Entry  Tuesday, May 15, 2012, 08:15, Rick Maharaj, , , , , , , , Test Stand chamber venting 
Entry  Tuesday, May 15, 2012, 08:16, Rick Maharaj, , , , , , , , Water circuits flushed 
Entry  Tuesday, May 15, 2012, 08:42, Rick Maharaj, , , , , , , , target removed 
Entry  Tuesday, May 15, 2012, 09:46, Rick Maharaj, , , , , , , , target reinstalled pumping started 
Entry  Wednesday, May 16, 2012, 16:01, Anders Mjos, , , , , , , Problems/Solutions, Loose chip of insulator material detected Ceramic_Chip.pdf
Entry  Wednesday, May 16, 2012, 19:55, Friedhelm Ames, , , , , , , Problems/Solutions, Hall probe reading wrong 
Entry  Thursday, May 17, 2012, 15:14, Anders Mjos, , , , , , , , Pumping down empty chamber 
Entry  Thursday, May 31, 2012, 14:46, Anders Mjos, , , , , , , , Venting in preparation for Ta#38 
Entry  Monday, June 04, 2012, 11:40, Anders Mjos, , , , , , , In progress, Empty chamber 
    Reply  Tuesday, June 26, 2012, 16:06, Anders Mjos, , , , , , , Done, Vented 
Entry  Tuesday, June 26, 2012, 18:04, Anders Mjos, FEBIAD anode end cap test, , , , Tube only, 38307-9, In progress, FEBIAD anode end cap test - ready 
Entry  Tuesday, June 26, 2012, 18:30, Anders Mjos, , , , , , , Problems/Solutions, Crack in source tray insulator Cracked_insulator.pdf
Entry  Thursday, June 28, 2012, 11:04, Pierre Bricault, Test FEBIAD, LP-FEBIAD, , , , , In progress, Ready to bias the high voltage. 
Entry  Thursday, June 28, 2012, 11:13, Pierre Bricault, , LP-FEBIAD, , , , , , ISAC test stand ready for cathode heating 
Entry  Thursday, June 28, 2012, 11:19, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Cathode ramping to 230 A in progress 
Entry  Thursday, June 28, 2012, 11:27, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Cathode heating in progress, pressure 8.3e-7 T 
Entry  Thursday, June 28, 2012, 11:29, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Lost all cnntrol interface, complete whiteout of the epics system. 
Entry  Thursday, June 28, 2012, 15:14, Aurelia Laxdal, , LP-FEBIAD, , , , , , Quick check 
Entry  Thursday, June 28, 2012, 17:00, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Cathode heater reached its value of 230 A and stoped. good test. 