ID Date Author Target/No.# Source Stationdown Module Target Oven W.O# Heat Shield W.O# Status Subject
  86   Tuesday, May 15, 2012, 08:08 Rick Maharajsic#27      Turbos off

Target needs to be removed form teststand to remove heatshielding around target oven. The chamber will be vented, water circuits flushed and target removed.

  87   Tuesday, May 15, 2012, 08:15 Rick Maharaj       Test Stand chamber venting
  88   Tuesday, May 15, 2012, 08:16 Rick Maharaj       Water circuits flushed
  89   Tuesday, May 15, 2012, 08:42 Rick Maharaj       target removed
  90   Tuesday, May 15, 2012, 09:46 Rick Maharaj       target reinstalled pumping started
  93   Wednesday, May 16, 2012, 16:01 Anders Mjos      Problems/SolutionsLoose chip of insulator material detected

 A chip of insulator material was detected below the lower target insulator stand-off (attachment - left picture). The chip may come from the tube heater insulator above (attachment - right picture). The chip will be further investigated when the target is removed.

  95   Wednesday, May 16, 2012, 19:55 Friedhelm Ames      Problems/SolutionsHall probe reading wrong

During the mass scan today it was discovered, that the mass calibration was off. Further investigation showed, that the Hall probe readings are a factor of 1.31 lower than during previous measurements. A fault report has been issued to controls.

  99   Thursday, May 17, 2012, 15:14 Anders Mjos       Pumping down empty chamber

Thursday, May 17, 2012, 15:14: Started roughing. Cooling lines blanked off.

Thursday, May 17, 2012, 16:52: Starting turbos.

Thursday, May 17, 2012, 17:00: Turbos at speed. Vacuum at 1.5E-5.

  100   Thursday, May 31, 2012, 14:46 Anders Mjos       Venting in preparation for Ta#38

Thursday, May 31, 2012, 14:46: Switching off turbos

Thursday, May 31, 2012, 15:05: Venting

  104   Monday, June 04, 2012, 11:40 Anders Mjos      In progressEmpty chamber

HS water lines blanked.

Monday, June 04, 2012, 11:40: Roughing.

Monday, June 04, 2012, 11:58: Starting turbos. 

Monday, June 04, 2012, 12:06 : Turbos at speed. Vacuum 1.5 E-5

  105   Tuesday, June 26, 2012, 16:06 Anders Mjos      DoneVented

Anders Mjos wrote:

HS water lines blanked.

Monday, June 04, 2012, 11:40: Roughing.

Monday, June 04, 2012, 11:58: Starting turbos. 

Monday, June 04, 2012, 12:06 : Turbos at speed. Vacuum 1.5 E-5

 Tuesday, June 26, 2012, 16:06: Turbos off.

Tuesday, June 26, 2012, 17:20: Vented.

  106   Tuesday, June 26, 2012, 18:04 Anders MjosFEBIAD anode end cap test   Tube only38307-9In progressFEBIAD anode end cap test - ready

Testing FEBIAD anode end cap as per dwg ITD0304 REV C

Target with TUBE ONLY. Do not use target heater.


Tuesday, June 26, 2012, 18:03: Roughing

Tuesday, June 26, 2012, 18:24: Turbos started

Tuesday, June 26, 2012, 18:31 : Turbos at speed. Vacuum at 1.8E-5

Wednesday, June 27, 2012, 08:48: Cooling opened. Vacuum stable at 4.2E-7. Ready for testing.

 

  107   Tuesday, June 26, 2012, 18:30 Anders Mjos      Problems/SolutionsCrack in source tray insulator

 A crack in the insulator ITD0054 was observed while mounting the target assembly. See attachment.

  108   Thursday, June 28, 2012, 11:04 Pierre BricaultTest FEBIADLP-FEBIAD    In progressReady to bias the high voltage.
  109   Thursday, June 28, 2012, 11:13 Pierre Bricault LP-FEBIAD     ISAC test stand ready for cathode heating

The ISAC test stand is ready for cathode heating.

Bias voltage: 30000 V

Bias current: 37 microAmp

Anode bias: 200 V

Anode current: 6.105 mA

Cathode current: 0 Amp

Cathode voltage: 0 V

Coil current: 30 A

Coil Voltage 0.2 V

EE Voltage: 1800 V

EE current: 30 microAmp

Einzel Lens voltage: 14000 V

Einzel lens current: 49 microAmp.

  110   Thursday, June 28, 2012, 11:19 Pierre Bricault LP-FEBIAD    In progressCathode ramping to 230 A in progress
  111   Thursday, June 28, 2012, 11:27 Pierre Bricault LP-FEBIAD    In progressCathode heating in progress, pressure 8.3e-7 T
  112   Thursday, June 28, 2012, 11:29 Pierre Bricault LP-FEBIAD    In progressLost all cnntrol interface, complete whiteout of the epics system.
  113   Thursday, June 28, 2012, 15:14 Aurelia Laxdal LP-FEBIAD     Quick check

Just a quick check at the Test Stand:

1. The system operational (  white out not present ) with TSH:TBHT heating in progress.

2. Started the Archivers: for Source and Optics.

3. Removed bypass on TSH:SV5 since it's not necessary anymore.

4. Currently: TSH:TBHT=107A

  114   Thursday, June 28, 2012, 17:00 Pierre Bricault LP-FEBIAD    In progressCathode heater reached its value of 230 A and stoped. good test.

Now ramp cathode current up to 290 A. The total current out is 1.e-7 A.

 