Message ID: 671     Entry time: Tuesday, July 03, 2018, 12:46
Author: Aaron Schmidt 
Target/No.#: Ta#56 
Source: HP-SIS 
Station: ITE 
Module: TM4 
Target Oven W.O#: 42218-9 
Heat Shield W.O#: 42752-3 
Status: In progress 
Subject: Conditioning Ta#56 

Tuesday, July 03, 2018, 12:44: Roughing

Tuesday, July 03, 2018, 13:32: Turbo pumps started.

Tuesday, July 03, 2018, 13:38: Ion gauge on.


Wednesday, July 04, 2018, 06:57: Waterlines opened. Vacuum ok @ 1.08e-06T. No response on RGA.

Wednesday, July 04, 2018, 06:59: Power/sources on

Wednesday, July 04, 2018, 07:00: Vacuum not yet low enough to begin ramping.

Wednesday, July 04, 2018, 07:10: BIAS / EZL / EE @ 30 / 13 / 1.5 kV .


Thursday, July 05, 2018, 06:29: Note* TMS:IG6 has higher than usual vacuum @ 9.22e-07T. Typically below 6.0e-07T.

Thursday, July 05, 2018, 06:30:  Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.

Thursday, July 05, 2018, 06:31: IV4 opened.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 24.5 3.90
 TBHT 24.7 3.06
 COIL + EE 24.7 4.97
 TGHT  24.9 5.61

Thursday, July 05, 2018, 06:35: Optics set.

Thursday, July 05, 2018, 11:23: Auto ramping  TBHT to 230 A @ 2A per min.

Thursday, July 05, 2018, 11:34: Auto ramp aborted on TBHT @ 221 A. Read back is at 230.3 A.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 32.9 3.82
 TBHT 28.0 3.13
 COIL + EE 24.7 4.97
 TGHT  24.9 5.61

 Thursday, July 05, 2018, 14:32: RGA froze. Restart


Friday, July 06, 2018, 08:24: Spark noted. RGA restarted.

Friday, July 06, 2018, 14:05: Auto-cooling @ 2A/min


Monday, July 09, 2018, 07:50: Power/sources brought to 0. Turned off.

Monday, July 09, 2018, 07:52: RGA off. IV4 closed (reset).

Monday, July 09, 2018, 07:56: Ion gauge, Turbo pumps off.

Monday, July 09, 2018, 07:58: Waterlines purged.

Monday, July 09, 2018, 09:19: Venting. 

Attachment 1: ER-580-230-30kV-m7.txt  3 kB  Uploaded Monday, July 09, 2018, 14:23  | Show | Show all
Attachment 2: ER-580-230-30kV-m38.txt  3 kB  Uploaded Monday, July 09, 2018, 14:24  | Show | Show all
Attachment 3: ER-580-230-30kV-m129.txt  3 kB  Uploaded Monday, July 09, 2018, 14:24  | Show | Show all
Attachment 4: TS-2018-07-03-13-50.rga  1.472 MB  Uploaded Monday, July 09, 2018, 14:24
Attachment 5: TS-2018-07-05-14-35.rga  280 kB  Uploaded Monday, July 09, 2018, 14:24
Attachment 6: TS-2018-07-06-08-25.rga  2.177 MB  Uploaded Monday, July 09, 2018, 14:24
Attachment 7: ITE-TM4-Ta#56-HP-SIS_Test_Stand.docx  770 kB  Uploaded Monday, July 09, 2018, 15:05
Attachment 8: Ta#56.docx  1.853 MB  Uploaded Tuesday, July 24, 2018, 14:51