Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand  Not logged in ELOG logo
Entry  Friday, September 23, 2011, 16:40, Anders Mjos, , , , , , , Problems/Solutions, 9-pin connectors swapped on source tray 
    Reply  Monday, September 26, 2011, 14:56, John Wong, , , , , , , Problems/Solutions, 9-pin connectors swapped on source tray 9-pin-connector.jpg
Message ID: 12     Entry time: Monday, September 26, 2011, 14:56     In reply to: 10
Author: John Wong 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: 9-pin connectors swapped on source tray 

Anders Mjos wrote:

Friday, September 23, 2011, 16:3: The connection on the 9-pin connector for FEBIAD targets showed burn marks from the previous FEBIAD tests. Corresponding mark was found on the connector on the target side. Because of this the upper and lower 9-pin connectors were swapped to have a clean connector for the next FEBIAD target.

 See attachment#1: 9-pin-connector.jpg 

Attachment 1: 9-pin-connector.jpg  721 kB  | Hide | Hide all
9-pin-connector.jpg
ELOG V2.9.2-2455