Entry  Wednesday, August 01, 2012, 09:37, Pierre Bricault, ITE-TM4-UO#3, LP-FEBIAD, ITE, TM4, , , Problems/Solutions, Short has developed while lowering the cathode heater 

 On tuesday July we lower the cathode heater to swap the anode-cathode bias. While lowering the cathode heater a short on the anode developed. 

The polarity swap was not possible because the target/tube assembly has also a short to common. 

We return the configuration has it was and we added two 100 Ohms: 5 W resistor between the common and the heaters to prevent current to flow back to the common. 

The anode short disappear during the cathode and target heating. 

Entry  Tuesday, June 21, 2022, 15:34, Matthew Gareau, SiC#42, SiC#43, , , TM2, , , Problems/Solutions, Multipin guide pin issues 

 While removing the SiC#42 it became apparent that the multipin guide pin had become loose again and was not allowing the target to dismount from the module.

The multipin shoulder bolts were removed and then the multipin was able to be pried off.

However the NHC manipulator were not able to reach the guide pin to remove it, which would be required before the SiC#43 could be installed.

The target module was then moved to the SHC where the guide pin could be removed and the installation of SiC#43 took place, along with the transfer of the parasitic attachment onto the SiC#43.

This problem seems to suggest that the multipin could use some redesign to ensure smoother target exchanges.

Entry  Thursday, November 29, 2018, 14:23, Marla Cervantes, UCx#26, LP-IG-LIS, , , 42281-3, , Ready, UCx#26 Target description UCx_26-description.JPG

Thursday, November 29, 2018, 14:20

Attached please find the UCx#26 target description. 


 

Entry  Monday, July 22, 2019, 16:33, Marla Cervantes, UCx#27, LP-SIS, , , 49044-9, , Ready, UCx#27 Target Description UCx#27.JPG

 Monday, July 22, 2019, 16:31

Attached please find the UCx#27 target description. 


 

Entry  Wednesday, October 02, 2019, 11:18, Marla Cervantes, UCx#28, LP-SIS, , , 44062-4, , Ready, UCx #28 Target description UCx28-target_description.JPG

 Wednesday, October 02, 2019, 11:17

Attached please find the UCx#28 target description. 

Entry  Thursday, June 04, 2020, 15:00, Marla Cervantes, C#1, LP-SIS, , , 43044-8, , In progress, Target C#1 Description C1-Description.PNG

 Thursday, June 04, 2020, 15:00

See attached picture for description 

Entry  Tuesday, September 29, 2020, 11:50, Marla Cervantes, C#2, LP-SIS, ITW, TM2, 44139-9, , In progress, Target C#2 Description  C2-Description.JPG

 Tuesday, September 29, 2020, 11:49

See attached picture for description 

Entry  Tuesday, March 16, 2021, 17:05, Luca Egoriti, ITE-TM4-UC#32-P2N-SIS, HP-SIS, ITE, TM4, -, -, In progress, UO2 discs cutting UC32-P2N_material_info.jpgFume_hood.jpg

This afternoon, Darwin prepared in the hot lab fume hood the two UO2 slurries to be cut into P2N target discs. Later, I took over cutting both slurries. A total of 49 annular discs were cut and loaded into the P2N graphite container.

The discs thickness was measured by stacking 5 discs on each other, and measuring their thickness in two points.

#discs = 49

Average disc thickness = 0.453mm

Empty cartridge weight = 9.42 g

Full cartridge weight = 39.86 g

UO2+C weight = 30.44 g

The unused material plus the cutting scrap were left in a zip lock bag on a shelf in the right hand side of the fume hood. The center scraps and the loaded target were placed in a plastic tray on the top shelf. The used tools and scales were left on the right of the working area, the napkins on the bottom were put into the garbage bag (inside the fume hood) and replaced, while the only napkin left is the one with the target information (recorded in attached picture).

Entry  Tuesday, July 15, 2014, 10:54, Laura Lambert, Ta # 43, LP-SIS, ITW, TM1, 40282-2, , Ready, Ta # 43 Target Description 

 Tuesday, July 15, 2014, 9:45

Ta#42 LP-SIS target description:

Total Ta foils = 400

Foil Thickness = 0.025mm

Target density = 16.69 g/cm3

Target length = 4.9cm

Total Mass (400 foils + Ta wire) = 45.920g

 

 

 

 

 

 

Entry  Tuesday, July 15, 2014, 11:01, Laura Lambert, UCx # 10, LP-SIS, ITE, TM4, 39165-10, , Ready, UCx#10 Target Description UCx_10_target_description.PNG

Tuesday, July 15, 2014, 10:58

See attachment for target description 

Entry  Monday, August 18, 2014, 14:39, Laura Lambert, ThO2 #1, LP-SIS, , , , , , ThO2 #1 Target Description ThO2#1_target_description.JPG

Monday, August 18, 2014, 14:53

See attachment for target description


 

Entry  Thursday, September 25, 2014, 16:01, Laura Lambert, Ta#44, HP-SIS, ITE, TM4, 38817-9, 40316-11, Ready, Ta#44 target description 

Thursday, September 25, 2014, 15:59

Ta#44 HP-SIS target description:

Total Ta foils = 400

Foil Thickness = 0.025mm

Target density = 16.69 g/cm3

Target length = 4.5cm

Total Mass (400 foils + Ta wire) = 47.49g


 

Entry  Thursday, November 06, 2014, 13:35, Laura Lambert, UCx # 11, LP-SIS, ITE, TM4, 40282-5, , Ready, UCx#11 Target Description UCx_11_target_description.PNG

 Thursday, November 06, 2014, 13:29

See attachment for target description


 

Entry  Wednesday, April 01, 2015, 11:27, Laura Lambert, Ta # 45, HP-SIS, , , 38817-5, , In Use, Ta#45 target description 

 Wednesday, April 01, 2015, 11:25

Ta#45 HP-SIS target description:

Total Ta foils = 400

Foil Thickness = 0.025mm

Target density = 13.48 g/cm3

Target length = 3.4cm

Total Mass (400 foils + Ta wire) = 45.8181g


 
Entry  Friday, April 17, 2015, 16:00, Laura Lambert, UCx # 12, LP-SIS, ITW, TM1, 41177-2, , Ready, UCx#12 Target Description UCx_12_target_description.PNG

 Thursday, April 16, 2015, 14:07

See attachment for target description

Entry  Wednesday, April 29, 2015, 15:39, Laura Lambert, SiC#31, HP-SIS, , , 38817-7, , Ready, SiC#31 Target description final_density_measurements.JPGdensity_measurements.xlsxSiC_density_Jan_10_'14_cast_-_Copy.xlsxSiC_density_Oct_31_'14_cast.xlsx

 Wednesday, April 29, 2015, 15:30

SiC#31 HP-SIS target description: 

Total SiC foils = 520 discs 

Total mass SiC + C_grv foils = 60.2441 g (before sintering, expecting ~13% loss of organic mass after burnt off) 

Average mass SiC/disc (without C_grv) = 0.0853g

Average thickness SiC (without C_grv) = 0.2093mm 

Total packed length = 17cm

See attachment #1 for the density measurement.  


 

Entry  Wednesday, June 03, 2015, 10:55, Laura Lambert, ZrC#7, LP-SIS, ITW, TM2, 41177-1, , Ready, ZrC#7 target description  target_production_elog_ZrC#7.JPGZrC#7_final_density.xlsx

 Wednesday, June 03, 2015, 10:53

Total length packed = 12.3cm

See attachment for target description.


 

Entry  Thursday, September 10, 2015, 13:33, Laura Lambert, Ta # 46, HP-SIS, , , 41369-3, , Ready, Ta#46 target description 

 Thursday, September 10, 2015, 13:31

Ta#46 HP-SIS target description:

Total Ta foils = 505

Foil Thickness = 0.025mm

Target density = 15.85 g/cm3

Target length = 3.4cm

Total Mass = 75.2772g


 

Entry  Thursday, September 24, 2015, 13:42, Laura Lambert, SiC#32, HP-FEBIAD, , , 39530-5, , Ready, SiC#32 target description elog_snapshot.JPG

 Thursday, September 24, 2015, 11:46

See attachment for target description.


 

Entry  Monday, October 26, 2015, 16:33, Laura Lambert, UCx#14, LP-SIS, , , 41077-5, , Ready, UCx#14 Target Description Capture.JPG

 Monday, October 26, 2015, 16:23

Attached please find the UCx#14 target description.

Note: This is the first UCx target using the new LP-SIS small center block design.


 

 

 

 