  Target Production, Page 3 of 8  Not logged in ELOG logo
  ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subjectdown
  65   Tuesday, August 02, 2016, 15:28 Laura LambertUCx#17LP-SIS  41790-3 ReadyUCx#17 Target Description

 Tuesday, August 02, 2016, 15:27

Attached please find the UCx#17 target description.


 

Attachment 1: UCx#17_description.jpg
UCx#17_description.jpg
  63   Wednesday, June 08, 2016, 15:55 Laura LambertUCx#16LP-IG-LIS  40860-2 ReadyUCx#16 Target Description

 Wednesday, June 08, 2016, 15:52

Attached please find the UCx#16 target description.


 

Attachment 1: Target_Description.JPG
Target_Description.JPG
  60   Friday, March 04, 2016, 14:57 Laura LambertUCx#15LP-SISITW 41077-1 ReadyUCx#15 Target Description

 Friday, March 04, 2016, 14:56

Attached please find the UCx#15 target description.

Note: This is the second UCx target using the new LP-SIS small center block design.


 

Attachment 1: UCx_15_description.jpg
UCx_15_description.jpg
  59   Monday, October 26, 2015, 16:33 Laura LambertUCx#14LP-SIS  41077-5 ReadyUCx#14 Target Description

 Monday, October 26, 2015, 16:23

Attached please find the UCx#14 target description.

Note: This is the first UCx target using the new LP-SIS small center block design.


 

 

 

 

Attachment 1: Capture.JPG
Capture.JPG
  55   Friday, July 10, 2015, 11:23 John WongUCx#13LP-IG-LISITETM440860-1 ReadyUCx#13 Target description

 Friday, July 10, 2015, 11:15

Attached please find the UCx#13 target description.   

Note:  Target container was coated/sintered with TaC twice.  Would like to see if this will improve the life-span of the target.  


 

Attachment 1: UCx_13_target_description.PNG
UCx_13_target_description.PNG
  50   Friday, April 17, 2015, 16:00 Laura LambertUCx # 12LP-SISITWTM141177-2 ReadyUCx#12 Target Description

 Thursday, April 16, 2015, 14:07

See attachment for target description

Attachment 1: UCx_12_target_description.PNG
UCx_12_target_description.PNG
  48   Thursday, November 06, 2014, 13:35 Laura LambertUCx # 11LP-SISITETM440282-5 ReadyUCx#11 Target Description

 Thursday, November 06, 2014, 13:29

See attachment for target description


 

Attachment 1: UCx_11_target_description.PNG
UCx_11_target_description.PNG
  44   Tuesday, July 15, 2014, 11:01 Laura LambertUCx # 10LP-SISITETM439165-10 ReadyUCx#10 Target Description

Tuesday, July 15, 2014, 10:58

See attachment for target description 

Attachment 1: UCx_10_target_description.PNG
UCx_10_target_description.PNG
  93   Wednesday, October 02, 2019, 11:18 Marla CervantesUCx#28LP-SIS  44062-4 ReadyUCx #28 Target description

 Wednesday, October 02, 2019, 11:17

Attached please find the UCx#28 target description. 

Attachment 1: UCx28-target_description.JPG
UCx28-target_description.JPG
  145   Tuesday, September 10, 2024, 09:53 Darwin Ortiz RosalesTiC#9HP-SIS  45447-2945235-19ReadyTiC#9_Description
Attachment 1: TiC#9.png
TiC#9.png
  144   Tuesday, September 03, 2024, 16:11 Darwin Ortiz RosalesTiC#8HP-FEBIAD  45447-2 ReadyTiC#8_Description

This was back-up target

Attachment 1: TiC#8_(2).png
TiC#8_(2).png
  142   Friday, June 14, 2024, 14:16 Darwin Ortiz RosalesTiC#7HP-FEBIAD  45447-545235-15ReadyTiC#7_Description

Please note that this target comes in a Graphite cartridge.

Attachment 1: TiC#7.png
TiC#7.png
  46   Monday, August 18, 2014, 14:39 Laura LambertThO2 #1LP-SIS     ThO2 #1 Target Description

Monday, August 18, 2014, 14:53

See attachment for target description


 

Attachment 1: ThO2#1_target_description.JPG
ThO2#1_target_description.JPG
  30   Tuesday, December 11, 2012, 15:44 Anders MjosSiCHP-FEBIADITWTM4nana (old style fittings)ReadyTest target for the Conditioning Station

 The target has been used for operator training previously at the ISAC Test Stand.

  • 9-pin connector was completed and grounded
  • RH gripper arms added to the heat shield

Further documentation on DocuShare

  12   Wednesday, July 06, 2011, 14:32 John WongTa#36LP-SISITETM438634-238307-10SpentTarget ready, will go online on July 27

Ta-LP-SIS (w.o#38634-2)

Target consists of 400 Ta foils, 4.4 cm in length.  Total mass + Ta wire = 40.87g.

Thursday, July 07, 2011, 15:43:  Begin target assembly. 

Friday, July 08, 2011, 14:24: assembly completed.  Std stds added for test-stand: Li, Na, Rb, K, Cs.

Friday, July 15, 2011, 09:09:  Target currently in test-stand.  Will come out on Monday next week.  Need to add std salts + Be. 

Monday, July 18, 2011, 10:58:  Target removed from test-stand.  Std salts added (Li, Na, Rb, K, Cs) & Be (as requested by Jens).  Maico D.V will do a final inspection on the target before it goes into the hotcell

 

  11   Wednesday, July 06, 2011, 14:29 John WongNb/SpareHP-SIS  38817-2 In progressTarget ready for Assembly

Target oven w.o# 38817-2:

inner diameter: left = 18.29mm, right = 18.16mm.

Filled with 400 foils Nb (16pk, 5 foils/pk).  

Discs spec: 18.65mm/14.65mm, thickness = 0.022mm  

Total mass + Ta-wire = 22.66g

total length = 4.5cm

Rn foil inserted for ionization.  (0.1mm, 0.004", 1cm x 1cm)  

 

 

  8   Thursday, June 16, 2011, 17:26 John WongNbHP-SIS  38817-1 SpentTarget is ready and stored in cabinet

 Thu Jun 16 17:21:10 2011

Two targets of Nb-HP-SIS are complete and ready to be installed in the heat shields:

-----------------------------------------------------------------------------------

Target oven w.o# 38817-1:

inner diameter: left = 18.27mm, right = 18.25mm.

Filled with 400 foils Nb (16pk, 5 foils/pk).  

Discs spec: 18.65mm/14.65mm, thickness = 0.022mm  

Total mass + Ta-wire = 22.74g

Total length = 4.5cm

Rn foil inserted for ionization.  (0.1mm, 0.004", 1cm x 1cm)  

 

------------------------------------------------------------------------------------

Wednesday, July 06, 2011, 14:35: Salts were added and tested in test-stand last 2 weeks.

 

  7   Friday, June 03, 2011, 09:16 John WongTa#37LP-SISITWTM138634-536833-7SpentTarget is done

 Fri Jun 3 12:40:30 2011

Ta#37-LP-SIS (w.o#38634-5)

Filled with 400 Ta foils (25/pk), 4.0 cm in length.  Total mass + Ta wire = 42.32g.  The heat shield was assembled and tested, and the standard salts were added.  Target was installed in the test stand on Jun 1, 2011.  

Fri Jun 17 09:19:46 2011: The following salts have been added: Li, Na, Rb @ 10uL, K @ 5uL, Cs @ 15uL, and Be @ 10uL.

Wednesday, July 06, 2011, 14:08:  TM1 is still under repairing.  It was tested at the test-stand. Target is on the shelve and ready to be used.

Tuesday, July 26, 2011, 15:58:  Salt added before going into the hotcell: Li,Na,Rb,K,Cs.  Target is ready to be used for TM1 test.

Wednesday, July 27, 2011, 10:48:  It was found that the extraction electrode had some arc marking on it (see attachment: EE).  Investigating... 

Wednesday, July 27, 2011, 12:51: After further investigation on the extraction electrode,  we found some black and blue(or green) deposit on the outside surface and inside of the EE.  This deposit is most likely copper oxide, which formed during the HV test.  The EE was removed, and wiped clean with methanol.  (see attachment: EE_CuO).  This target will be used in TM1. 

 

Friday, August 26, 2011, 09:48:  As per Friday Aug 26 TIS meeting, bNMR is very satisfied with the beam; the count rate is very stable.

 

Attachment 1: EE.JPG
EE.JPG
Attachment 2: EE-CuO.jpg
EE-CuO.jpg
  14   Tuesday, September 06, 2011, 13:19 John WongTaC#1LP-SISITETM138634-6 SpentTarget is done

Tuesday, September 06, 2011, 13:14: 

Average mass = 0.206g

Average Thickness = 0.0189 cm

Area of D-shaped disc = 2.21 cm2

D-shape discs diameter = 18.5mm (14.5mm cut-out length)

Oven ID, L= 18.22mm, R = 18.20mm 

Density = 4.9266 g/cm3

% Yield Density = 47.20%

Attachment#1 - TaC density measurements.

 Loaded target with 125 discs --> 9.6g Ta/cm2

Total discs mass = 30.41g

Total length = 4.5 cm


 Thursday, September 15, 2011, 10:45

Na & Li were added.

Re foil inserted.

No Ta-heat shields required.


Friday, September 30, 2011, 14:10

After the test-stand, 10uL of Na and Li were added yesterday.   

Target is now ready, and will be moved into the hotcell next week. 


Wednesday, November 16, 2011, 15:51 

After the target was finished and transferred into the hotcell, it was found that the target broke apart from the center block.  This might have happened during the end of the target cooldown. See link for more details: 

http://documents.triumf.ca/docushare/dsweb/View/Collection-7438


 

 

Attachment 1: TaC_density_measurements.xls
  10   Wednesday, July 06, 2011, 14:13 John WongTa#40HP-SIS  38295-4 SpentTarget description

Details about Ta Hp surface, w.o#38295-4 (spare):

This target was built as a spare.

 

Note: Left side target arm replaced, Nov 18, 2010.  Weld prep on centre block misaligned.  (Marik has more details about this).

Packs of Ta foils were prepared by JW. 

Target was filled with 400 of 0.025mm foils (25 foils/pk) in 4.0cm length. 

Total Mass of 16 packs of Ta foils + Ta wires = 42.70g.  

See attachment#1 for the measurement.

 


Friday, April 19, 2013, 09:44 

Target was tested at the Teststand.  Result Good. 

Ready for use.


 