141
|
Wednesday, February 18, 2015, 14:49 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Repair Complete | This is a continuation of work detailed
in E-Log #129 and #140.
- Static water test performed on |
|
75
|
Tuesday, March 26, 2013, 10:55 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK1 Re-wiring and MRO Complete | The following work was performed
on the T1-MK1 target:
- Unused proximity sensor removed |
|
25
|
Monday, April 02, 2012, 15:18 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Installed in Beam Line | The T1-MK1 target was transferred
from the storage pit to the beam line. Services
were hooked up and the cooling package was |
|
342
|
Thursday, February 01, 2024, 11:14 |
Albert Kong | Standard Operation | Target 1 | Hot Cell | T1-MK1 Flush and Purge on Hot Cell | The recently removed T1-MK1 target ladder
was flushed with city water for ~30s at all
target positions. It was then purged with |
|
356
|
Wednesday, October 30, 2024, 15:10 |
Albert Kong | Standard Operation | Target 1 | Target | T1-MK1 Electrical Check on Hot Cell | T1-MK1 electrical checks were completed
on the hot cell. Specifically the profile
and protect monitors were checked (assistance |
7x |
329
|
Thursday, May 11, 2023, 11:28 |
Adam Newsome | Repair | Target 1 | Target | T1-MK1 - broken target ladder motor coupler repaired | See Cyclotron Fault 15787. The target ladder
motor failed to move to the commanded position
during a test. The T1 area was uncovered |
|
81
|
Friday, April 19, 2013, 09:55 |
Isaac Earle | Development | Target 1 | Cooling | T1&T2 cooling package safety/standards compliance upgrade complete (SASP0120) | Yesterday (April 18th) the T1 and T2 cooling
package PRV outlet lines were routed to the
active drain in the 1A tunnel. All |
|
337
|
Wednesday, January 10, 2024, 12:47 |
Albert Kong | Standard Operation | Target 1 | Target | T1 target ladder exchange (T1-MK1 to hot cell roof, T1-MK2 from pit to station) | T1-MK1 was moved from the target station
to the hot cell roof.
Radiation surveys report 140 mSv/hr |
|
305
|
Tuesday, October 11, 2022, 11:27 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 inlet pressure transducer replacement | A fault was reported June 21, 2022 (Fault
15033) regarding T1 inlet pressure warnings... |
|
283
|
Monday, March 14, 2022, 14:08 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 cooling system: filled, tuned, leak-checked | The T1 cooling system was refilled with
water via the expansion tank until the tank
level read approximately 38 cm. |
|
244
|
Thursday, September 06, 2018, 13:49 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package secondary side solenoid failed | On Friday Aug 31 at approximately
3am T1CS:FGSEC dropped to 0gpm flow.
This was confirmed to be a real reading when |
|
242
|
Thursday, August 23, 2018, 11:52 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package pump failure and replacement | On Wednesday August 15th the T1 cooling
package tripped off, and could not be restarted.
On the EPICS screen the pump device went |
|
240
|
Tuesday, July 03, 2018, 11:09 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package outlet water pressure sensor replaced | The T1 cooling package outlet water
pressure sensor (B1A:T1CS:PGOUT) was replaced
this morning with a new unit. Over |
|
245
|
Thursday, October 25, 2018, 08:58 |
Keith C Ng | Repair | Other | Other | T1 collimator valve solenoid coil replaced again | On
23rd October we restarted the T1 and T2 water
packages after the mini shutdown and after |
|
230
|
Thursday, October 26, 2017, 16:12 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve replaced | Around 10pm on Sunday Oct 22 beam
was tripped multiple times due to low flow
for the T1 collimator cooling circuit (B1A:T1:FGCOL). |
|
241
|
Monday, July 23, 2018, 09:39 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve failed - Solenoid replaced | On Saturday July 21st the T1 Collimator
solenoid valve would not re-open after tripping
closed due to a (planned) loss of vacuum. |
|
239
|
Friday, June 01, 2018, 17:50 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve coil replaced | Flow stopped through the T1 collimator
cooling loop around the same time as a power
bump this afternoon. The problem was |
|
252
|
Monday, June 24, 2019, 14:29 |
Isaac Earle | Development | Target 1 | Target | T1 and T2 target alignment frames overhauled | The following work was completed on both
the T1 and T2 target alignment frames
One of the short taper |
8x |
247
|
Thursday, January 10, 2019, 13:51 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 cooling packages inspected | The T1 and T2 cooling packages were inspected
today while running. No water leaks
were observed at either package including |
|
236
|
Tuesday, April 10, 2018, 11:20 |
Isaac Earle | Maintenance | Other | Cooling | T1 and T2 cooling package shutdown MRO work | The following work was performed
on the T1 and T2 cooling packages during
the 2018 shutdown: |
|