Entry  Wednesday, February 18, 2015, 14:49, Isaac Earle, Repair, Target 1, Target, T1-MK1 Repair Complete IMG_4638.JPGIMG_4646.JPGIMG_4647.JPG
Entry  Tuesday, March 26, 2013, 10:55, Isaac Earle, Maintenance, Target 1, Target, T1-MK1 Re-wiring and MRO Complete T1-MK1_Tgt_leak_check.PDF
Entry  Monday, April 02, 2012, 15:18, Isaac Earle, Repair, Target 1, Target, T1-MK1 Installed in Beam Line 
Entry  Thursday, February 01, 2024, 11:14, Albert Kong, Standard Operation, Target 1, Hot Cell, T1-MK1 Flush and Purge on Hot Cell IMG_3950.JPEGIMG_3975.JPEGIMG_3973.JPEGIMG_3971.JPEGT1&T2_Pump-Down_and_Leak_Check_Record_05_FEB_2024.pdf
Entry  Wednesday, October 30, 2024, 15:10, Albert Kong, Standard Operation, Target 1, Target, T1-MK1 Electrical Check on Hot Cell 7x
Entry  Thursday, May 11, 2023, 11:28, Adam Newsome, Repair, Target 1, Target, T1-MK1 - broken target ladder motor coupler repaired 
Entry  Friday, April 19, 2013, 09:55, Isaac Earle, Development, Target 1, Cooling, T1&T2 cooling package safety/standards compliance upgrade complete (SASP0120) 
Entry  Wednesday, January 10, 2024, 12:47, Albert Kong, Standard Operation, Target 1, Target, T1 target ladder exchange (T1-MK1 to hot cell roof, T1-MK2 from pit to station) T1_and_T2_Beryllium_Target_Beamtime_Spreadsheet_-_(10Jan2024).xlsxMeson_Hall_Storage_Pit_Target_Device_Location_Record_-_(10Jan2024).pptmVacuumAt2.56PM.PNG
Entry  Tuesday, October 11, 2022, 11:27, Adam Newsome, Maintenance, Target 1, Cooling, T1 inlet pressure transducer replacement T1_inlet_pressure.png
Entry  Monday, March 14, 2022, 14:08, Adam Newsome, Maintenance, Target 1, Cooling, T1 cooling system: filled, tuned, leak-checked 
Entry  Thursday, September 06, 2018, 13:49, Isaac Earle, Repair, Target 1, Cooling, T1 cooling package secondary side solenoid failed 
Entry  Thursday, August 23, 2018, 11:52, Isaac Earle, Repair, Target 1, Cooling, T1 cooling package pump failure and replacement TUS1801057_Triumf.pdf
Entry  Tuesday, July 03, 2018, 11:09, Isaac Earle, Repair, Target 1, Cooling, T1 cooling package outlet water pressure sensor replaced 
Entry  Thursday, October 25, 2018, 08:58, Keith C Ng, Repair, Other, Other, T1 collimator valve solenoid coil replaced again 
Entry  Thursday, October 26, 2017, 16:12, Isaac Earle, Repair, Target 1, Cooling, T1 collimator solenoid valve replaced 
Entry  Monday, July 23, 2018, 09:39, Isaac Earle, Repair, Target 1, Cooling, T1 collimator solenoid valve failed - Solenoid replaced 
Entry  Friday, June 01, 2018, 17:50, Isaac Earle, Repair, Target 1, Cooling, T1 collimator solenoid valve coil replaced 
Entry  Monday, June 24, 2019, 14:29, Isaac Earle, Development, Target 1, Target, T1 and T2 target alignment frames overhauled 8x
Entry  Thursday, January 10, 2019, 13:51, Isaac Earle, Maintenance, Target 1, Cooling, T1 and T2 cooling packages inspected 
Entry  Tuesday, April 10, 2018, 11:20, Isaac Earle, Maintenance, Other, Cooling, T1 and T2 cooling package shutdown MRO work 