Friday, January 10, 2025, 18:36, Albert Kong, Standard Operation, Other, Cooling, T1/T2 cooling packages drained
Friday, November 29, 2024, 11:57, Adam Newsome, Maintenance, Other, Hot Cell, Hot cell and warm cell maintenance tasks
Wednesday, October 30, 2024, 15:10, Albert Kong, Standard Operation, Target 1, Target, T1-MK1 Electrical Check on Hot Cell
7x
Thursday, October 10, 2024, 12:24, Adam Newsome, Other, Other, Hot Cell, Safety Walkaround Complete - Meson Hall HC/WC Area
Monday, September 09, 2024, 16:31, Albert Kong, Standard Operation, Other, Active Sump, Active Sump High Level Sensor Testing
Monday, September 09, 2024, 09:39, Albert Kong, Other, Target 2, Cooling, B1A:T2CS:FGSEC:RDFLOW noisy, CYCLOTRON Fault 17321
Thursday, August 22, 2024, 15:16, Adam Newsome, Standard Operation, Other, Active Sump, Active sump filled ~600L with grey water from RCR1 sump replacement
Tuesday, August 06, 2024, 11:35, Albert Kong, Standard Operation, Other, BL1A Holding Tank, BL1A and RH Active Sump Draining
Wednesday, July 17, 2024, 15:05, Adam Newsome, Standard Operation, Other, Other, Safety Walkaround Complete - Meson Hall HC/WC Area
Friday, June 28, 2024, 15:44, Albert Kong, Other, Other, Transfer Flask, Inspection of Primary Target Transfer Flask
Thursday, May 23, 2024, 17:10, Albert Kong, Standard Operation, Target 1, Target, T1-MK1 Target Exchange (+ leak fix, service panel changes, coupler exchange)
36x
Tuesday, May 07, 2024, 13:21, Albert Kong, Repair, Target 2, Cooling, T2 Cooling System Expansion Tank Ultrasonic Level Sensor Repair
Wednesday, April 03, 2024, 10:48, Adam Newsome, Other, Other, BL1A Holding Tank, BL1A Holding Tank - water level check
Thursday, February 15, 2024, 14:53, Albert Kong, Maintenance, Target 2, Air amplifiers, T2 Lower Air Amplifier Maintenance/Rebuild
Thursday, February 15, 2024, 12:38, Riley Sykes, Repair, Other, Hot Cell, Indium Extruder Hand Pump
Thursday, February 01, 2024, 11:16, Albert Kong, Standard Operation, Other, Cooling, Spent resin can rinse, purge, and drying
Thursday, February 01, 2024, 11:14, Albert Kong, Standard Operation, Target 1, Hot Cell, T1-MK1 Flush and Purge on Hot Cell
Friday, January 19, 2024, 17:07, Albert Kong, Standard Operation, Other, Target, T1/T2 Profile Monitor, TGT Ladder, CUNO filter leak, Motor Coupling Inspection, + M9/M20 Blocker Actuation
7x
Monday, January 15, 2024, 16:47, Albert Kong, Standard Operation, Other, Cooling, T1/T2 Cooling Pkg. Prep for Refill + Leak Check At Pressure
7x
Monday, January 15, 2024, 16:36, Albert Kong, Standard Operation, Target 2, Cooling, T2 Resin Flask Exchange