346
|
Wednesday, April 03, 2024, 10:48 |
Adam Newsome | Other | Other | BL1A Holding Tank | BL1A Holding Tank - water level check | As of 2024-04-03, the BL1A Holding Tank
water level is approximately 580L. It is
recommended to drain the tank prior to the |
|
350
|
Wednesday, July 17, 2024, 15:05 |
Adam Newsome | Standard Operation | Other | Other | Safety Walkaround Complete - Meson Hall HC/WC Area | A safety walkaround for July 2024 was completed
by A. Kong.
Results can be found in the master |
|
352
|
Thursday, August 22, 2024, 15:16 |
Adam Newsome | Standard Operation | Other | Active Sump | Active sump filled ~600L with grey water from RCR1 sump replacement | During a replacement of the RCR1 active
sump (mechanical services group), approximately
600L of non-active grey water was released |
|
355
|
Thursday, October 10, 2024, 12:24 |
Adam Newsome | Other | Other | Hot Cell | Safety Walkaround Complete - Meson Hall HC/WC Area | A safety walkaround was completed for the
Meson Hall Hot/Warm Cells.
The resulting spreadsheet can be |
|
357
|
Friday, November 29, 2024, 11:57 |
Adam Newsome | Maintenance | Other | Hot Cell | Hot cell and warm cell maintenance tasks | The following maintenance tasks were completed
on 2024-11-29 by A. Newsome, A. Kong, A.
Tam, M. Dalla Valle: |
    |
365
|
Wednesday, April 23, 2025, 15:58 |
Adam Newsome | Other | Other | Hot Cell | Safety Walkaround Complete - Meson Hall HC/WC Area | A safety walkaround was completed for the
Meson Hall Hot/Warm Cells.
The resulting spreadsheet can be |
|
367
|
Tuesday, June 03, 2025, 11:39 |
Aaron Tam | Standard Operation | Other | BL1A Holding Tank | BL1A Active Water Holding Tank | June 3, 2025 - Albert Kong,
Aaron Tam
RPG finished analysis of |
   |