  ID Date Author Categorydown Type Specific Subject Text Attachments
  264   Wednesday, June 10, 2020, 08:58 Isaac EarleDevelopmentOtherM9T2-M9 and M9-B1 flange scan data Laser tracker scan data from 2017
and 2019 attached as a backup.  Original
files from Beamlines Group who also keep
 2017-03-28_meson_hall_t2_with_import_of_2015_data.xit642019-25-01_meson_hall_t2_data.xit64 
  265   Friday, June 12, 2020, 13:54 Isaac EarleDevelopmentOtherM9M9 Q1Q2 water header installedThe Q1Q2 water header (TB23481) was mounted
this morning as per installation drawing
TB23400.
 2.jpg1.jpg 
  266   Tuesday, July 07, 2020, 13:22 Isaac EarleDevelopmentOtherM9M9 Q1Q2 The M9 Q1Q2 magnet assembly lift
beam has been installed according to drawing
TB23401.  The side-to-side as well as
 8.jpg1.jpg4.jpg6.jpg 
  267   Tuesday, July 07, 2020, 15:13 Isaac EarleDevelopmentOtherM9M9 Q1Q2 service stand Lemo connector wiringThe diagram below shows the wiring for
the two connectors on the service stand (the
wires running from the stand to the power
 Lemo_pin_wiring.PNG 
  268   Thursday, July 09, 2020, 06:44 Isaac EarleDevelopmentOtherM9Alignment of M9 Q1Q2 magnets complete Mike Vogel reported that alignment
of the Q1Q2 assembly w.r.t. the T2 and B1
flanges was completed on July 7.  This
  
  272   Wednesday, February 17, 2021, 10:39 Isaac EarleDevelopmentOtherUCNUCN Target Cask TestingA trial run of remote removal of the UCN
target was performed using the shielded target
cask (TTA0335) developed in 2020.  The
 8x 
  1   Wednesday, June 29, 2011, 15:27 John Wong   testblah blah blah....   