264
|
Wednesday, June 10, 2020, 08:58 |
Isaac Earle | Development | Other | M9 | T2-M9 and M9-B1 flange scan data | Laser tracker scan data from 2017
and 2019 attached as a backup. Original
files from Beamlines Group who also keep |
 |
|
265
|
Friday, June 12, 2020, 13:54 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 water header installed | The Q1Q2 water header (TB23481) was mounted
this morning as per installation drawing
TB23400. |
 |
|
266
|
Tuesday, July 07, 2020, 13:22 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 | The M9 Q1Q2 magnet assembly lift
beam has been installed according to drawing
TB23401. The side-to-side as well as |
   |
|
267
|
Tuesday, July 07, 2020, 15:13 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand Lemo connector wiring | The diagram below shows the wiring for
the two connectors on the service stand (the
wires running from the stand to the power |
|
|
268
|
Thursday, July 09, 2020, 06:44 |
Isaac Earle | Development | Other | M9 | Alignment of M9 Q1Q2 magnets complete | Mike Vogel reported that alignment
of the Q1Q2 assembly w.r.t. the T2 and B1
flanges was completed on July 7. This |
|
|
272
|
Wednesday, February 17, 2021, 10:39 |
Isaac Earle | Development | Other | UCN | UCN Target Cask Testing | A trial run of remote removal of the UCN
target was performed using the shielded target
cask (TTA0335) developed in 2020. The |