338
|
Thursday, January 11, 2024, 15:10 |
Albert Kong | Maintenance | Other | Cooling | T1/T2 Cooling Pkg. Proteus Paddle Wheel Maintenance, CUNO Filter Replacement, and Fitting Inspection | The following tasks were performed:
All electrical, water,
and pneumatic connections to the T1 target |
|
339
|
Monday, January 15, 2024, 16:36 |
Albert Kong | Standard Operation | Target 2 | Cooling | T2 Resin Flask Exchange | The resin flask on the T2 cooling package
was exchanged today (new resin can prepped
in the morning). |
|
340
|
Monday, January 15, 2024, 16:47 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 Cooling Pkg. Prep for Refill + Leak Check At Pressure | The following tasks were completed
in preparation of re-filling the T1 and T2
cooling packages: |
7x |
341
|
Friday, January 19, 2024, 17:07 |
Albert Kong | Standard Operation | Other | Target | T1/T2 Profile Monitor, TGT Ladder, CUNO filter leak, Motor Coupling Inspection, + M9/M20 Blocker Actuation | The following tasks were completed:
Yesterday (Jan 18), the
T1/T2 cooling packages were inspected for |
7x |
342
|
Thursday, February 01, 2024, 11:14 |
Albert Kong | Standard Operation | Target 1 | Hot Cell | T1-MK1 Flush and Purge on Hot Cell | The recently removed T1-MK1 target ladder
was flushed with city water for ~30s at all
target positions. It was then purged with |
|
343
|
Thursday, February 01, 2024, 11:16 |
Albert Kong | Standard Operation | Other | Cooling | Spent resin can rinse, purge, and drying | The recently removed resin can from
the T2 target station was rinsed with city
water and flushed with compressed air for |
|
345
|
Thursday, February 15, 2024, 14:53 |
Albert Kong | Maintenance | Target 2 | Air amplifiers | T2 Lower Air Amplifier Maintenance/Rebuild | The lower amplifier for the T2 target station
air supply was removed for teardown, inspection,
and rebuild. |
|
347
|
Tuesday, May 07, 2024, 13:21 |
Albert Kong | Repair | Target 2 | Cooling | T2 Cooling System Expansion Tank Ultrasonic Level Sensor Repair | At ~8am on May 06, the expansion tank level
sensor for the T2 cooling system suddenly
became noisy. |
|
348
|
Thursday, May 23, 2024, 17:10 |
Albert Kong | Standard Operation | Target 1 | Target | T1-MK1 Target Exchange (+ leak fix, service panel changes, coupler exchange) | On May 23, 2024 two sets of plugs from
position 1 and 3 and a 12mm Be target from
position 5 (serial #109) was removed from |
36x |
349
|
Friday, June 28, 2024, 15:44 |
Albert Kong | Other | Other | Transfer Flask | Inspection of Primary Target Transfer Flask |
Normal
0
|
|
351
|
Tuesday, August 06, 2024, 11:35 |
Albert Kong | Standard Operation | Other | BL1A Holding Tank | BL1A and RH Active Sump Draining | The RH active sump was drained (over Jul
31-Aug 01), in total approximately 5500 L
of water was sent to city sewage. |
|
353
|
Monday, September 09, 2024, 09:39 |
Albert Kong | Other | Target 2 | Cooling | B1A:T2CS:FGSEC:RDFLOW noisy, CYCLOTRON Fault 17321 | Secondary flow sensor B1A:T2CS:FGSEC:RDFLOW
on the T2 cooling station suddenly became
very noisy at around 11 pm, 01 September |
|
354
|
Monday, September 09, 2024, 16:31 |
Albert Kong | Standard Operation | Other | Active Sump | Active Sump High Level Sensor Testing | The active sump high level sensor was tested
and correctly alarmed locally. However the
alarm in the MHESA RCR lab did not make any |
|
356
|
Wednesday, October 30, 2024, 15:10 |
Albert Kong | Standard Operation | Target 1 | Target | T1-MK1 Electrical Check on Hot Cell | T1-MK1 electrical checks were completed
on the hot cell. Specifically the profile
and protect monitors were checked (assistance |
7x |
358
|
Friday, January 10, 2025, 18:36 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 cooling packages drained | The T1 and T2 cooling packages were drained
starting at 14:36, by 14:48 both expansion
tanks had dried, meaning the draining rate |
|
277
|
Thursday, March 10, 2022, 11:18 |
Adam Newsome | Maintenance | Target 2 | Cooling | Changed paddle wheel, o-ring, and shaft in flow sensors at T2 cooling package | The paddle wheels, o-rings, and shafts
were changed at the T2 cooling package for
the following sensors: |
|
278
|
Thursday, March 10, 2022, 13:57 |
Adam Newsome | Maintenance | Target 1 | Cooling | Changed paddle wheel, o-ring, and shaft in flow sensors at T1 cooling package | The paddle wheels, o-rings, and shafts
were changed at the T1 cooling package for
the following sensors: |
|
279
|
Friday, March 11, 2022, 15:05 |
Adam Newsome | Maintenance | Target 1 | Cooling | O-rings on T1 cooling package water reservoir changed | The four o-rings on top of the T1 cooling
package water reservoir were changed as per
the recommended 5 year replacement schedule. |
|
280
|
Friday, March 11, 2022, 15:06 |
Adam Newsome | Maintenance | Target 2 | Cooling | O-rings on T2 cooling package water reservoir changed | The four o-rings on top of the T2 cooling
package water reservoir were changed as
per the recommended 5 year replacement schedule. |
|
281
|
Friday, March 11, 2022, 15:08 |
Adam Newsome | Maintenance | Target 1 | Cooling | Filters replaced: T1 cooling system | All filters were replaced for the T1 cooling
system: demineralizing resin circuit, target
water system, and M15. |
|