358
|
Friday, January 10, 2025, 18:36 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 cooling packages drained | The T1 and T2 cooling packages were drained
starting at 14:36, by 14:48 both expansion
tanks had dried, meaning the draining rate |
|
|
357
|
Friday, November 29, 2024, 11:57 |
Adam Newsome | Maintenance | Other | Hot Cell | Hot cell and warm cell maintenance tasks | The following maintenance tasks were completed
on 2024-11-29 by A. Newsome, A. Kong, A.
Tam, M. Dalla Valle: |
|
|
356
|
Wednesday, October 30, 2024, 15:10 |
Albert Kong | Standard Operation | Target 1 | Target | T1-MK1 Electrical Check on Hot Cell | T1-MK1 electrical checks were completed
on the hot cell. Specifically the profile
and protect monitors were checked (assistance |
7x |
|
355
|
Thursday, October 10, 2024, 12:24 |
Adam Newsome | Other | Other | Hot Cell | Safety Walkaround Complete - Meson Hall HC/WC Area | A safety walkaround was completed for the
Meson Hall Hot/Warm Cells.
The resulting spreadsheet can be |
|
|
354
|
Monday, September 09, 2024, 16:31 |
Albert Kong | Standard Operation | Other | Active Sump | Active Sump High Level Sensor Testing | The active sump high level sensor was tested
and correctly alarmed locally. However the
alarm in the MHESA RCR lab did not make any |
|
|
353
|
Monday, September 09, 2024, 09:39 |
Albert Kong | Other | Target 2 | Cooling | B1A:T2CS:FGSEC:RDFLOW noisy, CYCLOTRON Fault 17321 | Secondary flow sensor B1A:T2CS:FGSEC:RDFLOW
on the T2 cooling station suddenly became
very noisy at around 11 pm, 01 September |
|
|
352
|
Thursday, August 22, 2024, 15:16 |
Adam Newsome | Standard Operation | Other | Active Sump | Active sump filled ~600L with grey water from RCR1 sump replacement | During a replacement of the RCR1 active
sump (mechanical services group), approximately
600L of non-active grey water was released |
|
|
351
|
Tuesday, August 06, 2024, 11:35 |
Albert Kong | Standard Operation | Other | BL1A Holding Tank | BL1A and RH Active Sump Draining | The RH active sump was drained (over Jul
31-Aug 01), in total approximately 5500 L
of water was sent to city sewage. |
|
|
350
|
Wednesday, July 17, 2024, 15:05 |
Adam Newsome | Standard Operation | Other | Other | Safety Walkaround Complete - Meson Hall HC/WC Area | A safety walkaround for July 2024 was completed
by A. Kong.
Results can be found in the master |
|
|
349
|
Friday, June 28, 2024, 15:44 |
Albert Kong | Other | Other | Transfer Flask | Inspection of Primary Target Transfer Flask |
Normal
0
|
|
|
348
|
Thursday, May 23, 2024, 17:10 |
Albert Kong | Standard Operation | Target 1 | Target | T1-MK1 Target Exchange (+ leak fix, service panel changes, coupler exchange) | On May 23, 2024 two sets of plugs from
position 1 and 3 and a 12mm Be target from
position 5 (serial #109) was removed from |
36x |
|
347
|
Tuesday, May 07, 2024, 13:21 |
Albert Kong | Repair | Target 2 | Cooling | T2 Cooling System Expansion Tank Ultrasonic Level Sensor Repair | At ~8am on May 06, the expansion tank level
sensor for the T2 cooling system suddenly
became noisy. |
|
|
346
|
Wednesday, April 03, 2024, 10:48 |
Adam Newsome | Other | Other | BL1A Holding Tank | BL1A Holding Tank - water level check | As of 2024-04-03, the BL1A Holding Tank
water level is approximately 580L. It is
recommended to drain the tank prior to the |
|
|
345
|
Thursday, February 15, 2024, 14:53 |
Albert Kong | Maintenance | Target 2 | Air amplifiers | T2 Lower Air Amplifier Maintenance/Rebuild | The lower amplifier for the T2 target station
air supply was removed for teardown, inspection,
and rebuild. |
|
|
344
|
Thursday, February 15, 2024, 12:38 |
Riley Sykes | Repair | Other | Hot Cell | Indium Extruder Hand Pump | Feb 1 2024
Hand Pump observed to be losing pressure
at full extension of cylinder, seals likely |
|
|
343
|
Thursday, February 01, 2024, 11:16 |
Albert Kong | Standard Operation | Other | Cooling | Spent resin can rinse, purge, and drying | The recently removed resin can from
the T2 target station was rinsed with city
water and flushed with compressed air for |
|
|
342
|
Thursday, February 01, 2024, 11:14 |
Albert Kong | Standard Operation | Target 1 | Hot Cell | T1-MK1 Flush and Purge on Hot Cell | The recently removed T1-MK1 target ladder
was flushed with city water for ~30s at all
target positions. It was then purged with |
|
|
341
|
Friday, January 19, 2024, 17:07 |
Albert Kong | Standard Operation | Other | Target | T1/T2 Profile Monitor, TGT Ladder, CUNO filter leak, Motor Coupling Inspection, + M9/M20 Blocker Actuation | The following tasks were completed:
Yesterday (Jan 18), the
T1/T2 cooling packages were inspected for |
7x |
|
340
|
Monday, January 15, 2024, 16:47 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 Cooling Pkg. Prep for Refill + Leak Check At Pressure | The following tasks were completed
in preparation of re-filling the T1 and T2
cooling packages: |
7x |
|
339
|
Monday, January 15, 2024, 16:36 |
Albert Kong | Standard Operation | Target 2 | Cooling | T2 Resin Flask Exchange | The resin flask on the T2 cooling package
was exchanged today (new resin can prepped
in the morning). |
|