  RH-Meson Hall  Not logged in ELOG logo
Message ID: 273     Entry time: Wednesday, March 31, 2021, 16:15
Author: Matthew Gareau 
Category: Standard Operation 
Type: Target 1 
Specific: Target 
Subject: T1-MK1 target exchange 

 March 29 Monday

- moved T1-MK1 target from beamline to hotcell  (field from target 15mSv/hr @ 0.5m)

- flushed water through position 4

- flushed air through all positions

- left air running @ 5psi overnight through position 5

- potentiometer reading "O/L" at position 3, all other positions OK

- all micro switches OK

- removed the left plug (when facing ladder) at position 1 , but after reading elogs it was found that the right plug at position 1 was having issues. Will have to replug left with new plug

 

March 30 Tuesday

- pumped down with cold trap, started at 10:00

- test port 2.0 E-1 Torr after 1 hour

- cold trap removed, cleared, dried, refilled

- 11:10, started pumping, found leak at lab vac tubing joint. Fixed.

- 11:16, started pump again

- 11:24, 1.0 E-3 Torr TPP, 1.4 E-9 L/s leak rate

- preformed leak check, no response at all locations

- position 4 Be target removed (required hammering). Damaged spot, potential start of hole observed at center of beam spot (see attached photos)

- position 5 graphite target removed (required hammering)

- New 12 mm Be target #108 installed at position 4

- New 12 mm Be target #109 installed at position 5

- leaving position 3 plugged as the potentiometer is reading "O/L" as indicated from the multimeter 

- New plug installed on left side of position 1

- 15:47, stated leak check pump down

- 15:57, 2.0 E-3 Torr 

leak check results

All positions were no response (NR) except

Position 1, Right side plug) 5.9 E-8 Torr

Position 3, Left side fitting) 5.3 E-9 Torr

Position 4, Left side fitting) 4.2 E-9 Torr

All locations should be H2O tight

 

March 31 Wednesday

- took vertical and horizontal measurements of the new position of 4 and 5 targets (updated elevations PDF sheet included)

tested profile monitor activation

- started moving at 15 psi 

- reached limit at 35 psi

- both limit switches OK

- Cleaned base of vacuum flange and top of support ring

- prepared target ready for transport with flask (ladder in position 0)

- contacted MCR to update XTPAGE 7L target details

- emailed Tony Tateyama to have PLC lookup tables updated with new target info

 

Attachment 1: IMG_20210330_140744.jpg  183 kB  | Show | Hide all
Attachment 2: IMG_20210330_141059.jpg  167 kB  | Show | Hide all
Attachment 3: IMG_20210330_141455.jpg  142 kB  | Show | Hide all
Attachment 4: T1-MK1_-_2021.pdf  32 kB  | Hide | Hide all
T1-MK1_-_2021.pdf
ELOG V2.9.2-2455