  RH-ISAC, Page 1 of 130  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subject Text Attachments
  2591   Tuesday, May 14, 2024, 15:27 Carla BabcockITEDevelopmentTM3UCx#44TM3 conditioning and testing in ITETuesday, May 14, 2024, 10:26 :
Ramping up bias/EE/EL on ITE - will
see if the HV cage in the pit can hold 60kV
 Screenshot_from_2024-05-14_10-47-22.png 
  2590   Monday, May 13, 2024, 09:28 David WangITEStandard OperationTM4UCx#44ITE water signal annual interlock check.ITE water signal annual interlock check
is done. Ed helped me on this check. Everything
works normal. 
  
  2589   Friday, May 10, 2024, 09:04 David WangITEStandard OperationTM3UCx#44Tm3 has been connected in ITE. Tm3 has been connected in ITE.  see
attachment.
 Scanned_from_a_Xerox_Multifunction_Printer.pdf 
  2588   Thursday, May 09, 2024, 13:52 Riley SykesWaste Package/ShipStandard Operation  F308 Service/Inspection F308 Inspection and service complete
on #06, #08, #13, #15, #16, #19, #20, #21,
#22.
  
  2587   Wednesday, May 08, 2024, 14:01 Frank SongITWMaintenance  Annual clean up for ITW Faraday cage The ITW Faraday Cage has been cleaned,
this is part of Winter Shut Down job happens
in ISAC-1 Electric maintenance room annually.
  
  2586   Wednesday, May 08, 2024, 12:37 David WangITEStandard OperationTM3UCx#44Tm3 has been moved form TCS to ITEThe move is smooth and successful.   
  2585   Wednesday, May 08, 2024, 12:36 David WangConditioning StationStandard OperationTM3UCx#44TCS was argon vented this morning between 7:00 to 8:30 am.TCS was argon vented this morning between
7:00 to 8:30 am before module was moved to
ITE.
  
  2584   Tuesday, May 07, 2024, 12:39 Eric LaheSpent Target VaultRepair  ISAC Storage Vault Re-alignment 
 Testing_and_updates_to_storage_vault_2024-05-01.pdf 
  2583   Tuesday, May 07, 2024, 09:47 David WangITE/ITWMaintenanceTM2 Broken TM2:TP2 has been replaced. Broken TM2:TP2 has been replaced otday
by a new TV-1001 nav pump supplied by vacuum
group. replaced pump seris number:201281.
  
  2582   Friday, May 03, 2024, 12:20 Travis CaveSpent Target VaultStandard Operation Ta#66Target repacked The Ta#66 target was repacked after
the parasitic target was removed it was place
in a new pail (#290) and place back in spot
 Target_Index_2024-05-03.pdf 
  2581   Thursday, May 02, 2024, 18:48 Carla BabcockITWStandard Operation  ITW cage setupITW gas lines pumped down to 2e-3Torr on
leak detector with leak rate in the low e-7
atm-cc/s. Gas bottles opened at 3psi and
  
  2580   Thursday, May 02, 2024, 15:23 David WangSouth Hot-CellDevelopmentTM3 Leak check on TM3 new containment box window line VCR fittings. After new containment box installation
on TM3, Chad and I did a helium spray leak
check on two VCR fittings on front side water
  
  2579   Thursday, May 02, 2024, 14:58 David WangSouth Hot-CellStandard OperationTM3UCx#44TM3 with UCx#44 electrical check and leak check.TM3 with UCx#44 electrical check and leak
check are good. see attachment.
HS line 70 psi helium pressure test
 Scanned_from_a_Xerox_Multifunction_Printer_(11).pdf 
  2578   Thursday, May 02, 2024, 14:54 David WangConditioning StationStandard OperationTM3UCx#44TM3 has been moved from SHC to TCS.TM3 has been moved  from SHC to TCS
by David and Frank. The move is smooth. 
  
  2577   Thursday, May 02, 2024, 09:00 David WangITWStandard OperationTM4 Annual ITW water signal interlock check has been done. Annual ITW water signal interlock check
has been done. Renee helped me on it. Everything
works fine. 
  
  2576   Wednesday, May 01, 2024, 14:51 David WangSouth Hot-CellStandard OperationTM3 Tm3 has been moved form TCS to SHC.Travis and I moved TM3 from TCS to SHC
this afternoon. The move is smooth. 
  
  2575   Wednesday, May 01, 2024, 09:50 David WangITWStandard OperationTM4 TM4 has been connected to ITW.TM4 has been connected to ITW. see attachment.  Scanned_from_a_Xerox_Multifunction_Printer_(10).pdf 
  2574   Tuesday, April 30, 2024, 09:20 David WangITWDevelopmentTM4 A new SST gas line is using for ITW febiad gas staion in pit.A new SST gas line with swagelock tube
fittings and VCR fit is using for ITW febiad
gas staion in pit. Gas line is leak checked
  
  2573   Tuesday, April 30, 2024, 08:00 Frank SongSouth Hot-CellStandard OperationTM4Lp-Febiad emptyelectrical check/leak check David Wang made E/L checking before
module moving to ITW. read attachment pls.
 TM4_with_Lp-Febiad_empty_target_checking_on_SHC_2024-04-29.pdf 
  2572   Monday, April 29, 2024, 14:21 David WangITE/ITWStandard OperationTM4 TM4 has been moved from SHC to ITW.TM4 has been moved from SHC to ITW. Peter
did the move. Travis helped on him.  
The move is successful. 
  