IDup Date Author Category Type Module Target/Number Subject
  2585   Wednesday, May 08, 2024, 12:36 David WangConditioning StationStandard OperationTM3UCx#44TCS was argon vented this morning between 7:00 to 8:30 am.

TCS was argon vented this morning between 7:00 to 8:30 am before module was moved to ITE.

  2586   Wednesday, May 08, 2024, 12:37 David WangITEStandard OperationTM3UCx#44Tm3 has been moved form TCS to ITE

The move is smooth and successful.

  2587   Wednesday, May 08, 2024, 14:01 Frank SongITWMaintenance  Annual clean up for ITW Faraday cage

The ITW Faraday Cage has been cleaned, this is part of Winter Shut Down job happens in ISAC-1 Electric maintenance room annually.

  2588   Thursday, May 09, 2024, 13:52 Riley SykesWaste Package/ShipStandard Operation  F308 Service/Inspection

 F308 Inspection and service complete on #06, #08, #13, #15, #16, #19, #20, #21, #22.

All in good condition with new gasket material installed on #20.

Prepped for move to ISAC B3 for storage.

  2589   Friday, May 10, 2024, 09:04 David WangITEStandard OperationTM3UCx#44Tm3 has been connected in ITE.

Tm3 has been connected in ITE.  see attachment.

Attachment 1: Scanned_from_a_Xerox_Multifunction_Printer.pdf
Scanned_from_a_Xerox_Multifunction_Printer.pdf Scanned_from_a_Xerox_Multifunction_Printer.pdf Scanned_from_a_Xerox_Multifunction_Printer.pdf Scanned_from_a_Xerox_Multifunction_Printer.pdf
  2590   Monday, May 13, 2024, 09:28 David WangITEStandard OperationTM4UCx#44ITE water signal annual interlock check.

ITE water signal annual interlock check is done. Ed helped me on this check. Everything works normal.

  2591   Tuesday, May 14, 2024, 15:27 Carla BabcockITEDevelopmentTM3UCx#44TM3 conditioning and testing in ITE

Tuesday, May 14, 2024, 10:26 :

Ramping up bias/EE/EL on ITE - will see if the HV cage in the pit can hold 60kV or not.

At around 50kV the bias read current starts to get jumpy. Doesn't look like its an issue for the voltage, but definitely instability increases.

Screenshot_from_2024-05-14_10-47-22.png

Occasional sparks seem to increase the EL current significantly...

David heard some sparks in the target hall. Looks like from heat shield feed through to the top of the cage. Several sparks heard in the TH also changed the einzel lens draw current significantly. These feethroughs are not far from each other so could be related.

Apparently the sparking also tripped off all the optics and heaters in ITW, by changing the state of the water flow interlock. Interesting and not seen ever before. Will test again with the cage off, rather than risk tripping ITW again.

Tried ramping up the voltage on just the EE. Seems the limit is 7kV - at that level it gets sparky and unstable. Should be investigated (should hold 10kV) but not critical for module function.

 

Wednesday, May 15, 2024, 10:05 :

HV cover was removed this morning and the MAA was locked out.

Started ramping things up, was very easy until around 58kV. At 59.5kV a spark tripped off the EL. Canbus controller had to be power cycled to fix it. Bias current is much more stable in this configuration.

Ramped up again while listening from the TH to see if it was sparking outside. Went slowly to 60kV (left EL at 29kV) and didn't see any outside sparks in the first 10 mins, couple sparks in vacuum. But after 15 mins a spark seems to have fried the EL canbus card. We were not in the TH so not sure if it was on the outside or not.

After 2 hours a spark tripped off both ITE and ITW. Looks like it makes a water interlock go bad momentarily, but after the trip the interlocks seem fine.

 

  2592   Wednesday, May 15, 2024, 10:06 Travis CaveSpent Target VaultStandard Operation UC#38,40 Ta#62,63 SiC#44Targets moved to the mini vault.

 Targets UC#38,40 Ta#62,63 SiC#44 have been moved from the spent target vault to the mini vault in preparation for F-308 loading. See attached PDFs for details.

Attachment 1: Mini_Vault_Index_2024-05-15.pdf
Mini_Vault_Index_2024-05-15.pdf Mini_Vault_Index_2024-05-15.pdf
Attachment 2: Target_Index_2024-05-15.pdf
Target_Index_2024-05-15.pdf