  2540   Friday, February 09, 2024, 12:52 Adam NewsomeSpent Target VaultStandard Operation  F-308 flask loading - five flasks loaded

Today (2024-02-09), five flasks were loaded in preparation for shipment with the following targets: SiC#41, SiC#42, Nb#9, UC#36, Ta#58.

Note: prior to shipping, the pails within these flasks will need to have a crimped lifting loop added to them.

The mini-storage vault is now EMPTY.

The target index spreadsheet has been updated.

Attachment 1: Target_Index_2024-02-09.xlsm
  2542   Wednesday, February 14, 2024, 11:32 Adam NewsomeSpent Target VaultStandard Operation UCx#43Spent Target Move

Spent target UCx#43 (pail 289) was moved from the South Hot Cell to the Storage Vault, placed in location 2A. Dose rate at 1m was approximately 22.6 mSv/hr.

Target index spreadsheet updated, attached.

Attachment 1: Target_Index_2024-02-14.xlsm
  2543   Wednesday, February 14, 2024, 11:34 Adam NewsomeSpent Target VaultStandard Operation Misc.Three pails moved from main vault to mini vault

In preparation for F-308 loading, three pails were moved from the main storage vault to the mini storage vault. The following pails were moved:

  • Pail 270 (C#3)
  • Pail 276 (UC#39)
  • Pail 231 (UC#41)

 

Target Index spreadsheet updated, attached.

Attachment 1: Target_Index_2024-02-14.xlsm
  2546   Friday, February 16, 2024, 10:57 Adam NewsomeSpent Target VaultStandard Operation  F-308 flask loading - three flasks loaded

Today (2024-02-16), three flasks were loaded in preparation for shipment with the following targets: UCx#39, UCx#41 and C#3.

Note: prior to shipping, the pails within these flasks will need to have a crimped lifting loop added to them.

The mini-storage vault is now EMPTY.

The target index spreadsheet has been updated.

Attachment 1: Target_Index_2024-02-16.xlsm
  2582   Friday, May 03, 2024, 12:20 Travis CaveSpent Target VaultStandard Operation Ta#66Target repacked

 The Ta#66 target was repacked after the parasitic target was removed it was place in a new pail (#290) and place back in spot 5B of the vault. See attached PDF for further details.

Attachment 1: Target_Index_2024-05-03.pdf
Target_Index_2024-05-03.pdf
  2584   Tuesday, May 07, 2024, 12:39 Eric LaheSpent Target VaultRepair  ISAC Storage Vault Re-alignment

 

ISAC Storage Vault Door Re-alignment (April-May 2024) 

Issue

  • Rollers gouging and marking on roller supports, testing shows door shifts at least 185 thou on structural beam when fully open vs. fully closed
  • door misaligned: 1/4" laterally, slight rotation (~1/16" difference across closed door gap).

 

Repair

  • Moved left structural beam (facing front of door) inward 1/4" at post.
  • Loosened drive system to shift door over via crane to average laterally (1/8" shift) towards center,
  • Attempted to fix door rotation with crane, door would not settle down perfectly flush, but got slight improvement 
  • Adjusted limit switches for fully open and closed (due to the adjustments made previously, needed to realign limit switches) - adjusted flag for final close back by ~1/4"; adjusted limit switch at back of vault forward ~1/4" 

 

Verification 

  • Unloaded vault door actuation tested multiple times with no issues, door returned to same position every cycle, no interferences during travel
  • Vault Door actuation tested with trays 4 and 6 engaged, no issues
  • All pails accessible when open
  • Tested open and closed limit switches: the open limit switches are working properly; the closing soft and hard limit switches are slightly close together, causing the door to just "bump" the vault when closing, The scale of this is OK for current operation, will be adjusted when the ISAC Target Hall Controls Overhaul is done
  • Tested and reset Emergency override mechanism - works properly

 

Outstanding Tasks

  • Will paint marks on structural supports to track if problem reoccurs - update ELog when complete 

 

System State: Operational

See attached file for details

 

 

Attachment 1: Testing_and_updates_to_storage_vault_2024-05-01.pdf
Testing_and_updates_to_storage_vault_2024-05-01.pdf Testing_and_updates_to_storage_vault_2024-05-01.pdf Testing_and_updates_to_storage_vault_2024-05-01.pdf Testing_and_updates_to_storage_vault_2024-05-01.pdf Testing_and_updates_to_storage_vault_2024-05-01.pdf Testing_and_updates_to_storage_vault_2024-05-01.pdf Testing_and_updates_to_storage_vault_2024-05-01.pdf Testing_and_updates_to_storage_vault_2024-05-01.pdf
  2592   Wednesday, May 15, 2024, 10:06 Travis CaveSpent Target VaultStandard Operation UC#38,40 Ta#62,63 SiC#44Targets moved to the mini vault.

 Targets UC#38,40 Ta#62,63 SiC#44 have been moved from the spent target vault to the mini vault in preparation for F-308 loading. See attached PDFs for details.

Attachment 1: Mini_Vault_Index_2024-05-15.pdf
Mini_Vault_Index_2024-05-15.pdf Mini_Vault_Index_2024-05-15.pdf
Attachment 2: Target_Index_2024-05-15.pdf
Target_Index_2024-05-15.pdf
  2588   Thursday, May 09, 2024, 13:52 Riley SykesWaste Package/ShipStandard Operation  F308 Service/Inspection

 F308 Inspection and service complete on #06, #08, #13, #15, #16, #19, #20, #21, #22.

All in good condition with new gasket material installed on #20.

Prepped for move to ISAC B3 for storage.