463
|
Wednesday, September 25, 2013, 06:59 |
maicodallavalle | South Hot-Cell | Standard Operation | TM3 | | Containment box cover |
The containment box cover has had all the bolts installed and all bolts were checked with a mirror. TM3 has been raised and is ready for the last electrical test before it goes to the conditioning station. |
467
|
Thursday, September 26, 2013, 09:46 |
maicodallavalle | Conditioning Station | Repair | TM3 | | Leak check / Pressure Test |
TM3 has had all of the water lines pressurized with Helium and the Helium Leak detector was connected to the turbo pumps. There were no leaks detected. |
583
|
Monday, January 20, 2014, 13:40 |
maicodallavalle | Spent Target Vault | Maintenance | | F-308 | Empty F-308s |
Four empty F-308s just arrived back at Triumf. I moved them from shipping to the Remote Handling Shop for service and inspection. I will work on them when not busy with my other shutdown work. ( Cyclotron work) |
664
|
Tuesday, May 27, 2014, 09:38 |
maicodallavalle | Spent Target Vault | Maintenance | | F-308 Maintenance | F-308 Maintenance |
All the F-308's can back from being certified at Nordion. All of the F-308's have been serviced and are ready to be filled with spent targets. |
665
|
Tuesday, May 27, 2014, 09:42 |
maicodallavalle | Spent Target Vault | Maintenance | | | F-308 Maintenance |
All of the serviced F-308's have been moved to the South Hot cell area. |
685
|
Tuesday, June 24, 2014, 11:33 |
maicodallavalle | Spent Target Vault | Standard Operation | | | F-308 Maintenance |
Five F - 308 flasks containing five ISAC spent targets were moved from the anteroom into the south hot cell area. When the F - 308's were in the south hot cell area the rest of the bolts were installed on all the top covers. All the bolts were torqued and all the cable locks were also installed. All F - 308's were then moved into the Active Services Area. |
804
|
Monday, December 01, 2014, 12:05 |
maicodallavalle | Spent Target Vault | Maintenance | | | F-308 Maintenance |
F-308's have been serviced and are ready to be filled with spent targets. F-308's witch were serviced are #6,#13,#15,#16,and #19. |
1155
|
Friday, February 19, 2016, 06:58 |
maicodallavalle | Spent Target Vault | Maintenance | | | F-308's serviced/loaded/ bolts torqued |
Five F-308's were loaded with spent ISAC targets. All five F-308's were serviced two weeks ago. All bolts were torqued and security cables were installed for shipment. |