Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 91 of 135  Not logged in ELOG logo
Entry  Thursday, June 04, 2015, 07:44, Dan McDonald, Assembly/Bench Test, Development, TM2, , Movement of TM2 source tray to alignment area in ISAC 
Once the test stand was vented and all lines purged Anders Mjos and myself jigged up the water blocks and proceeded to remove the TM4 SiC#31 target used
during the testing, Einso lens and steerer.  Once these components where removed we transferred the source tray to the transport plate and moved it
to the alignment area.
Entry  Wednesday, June 03, 2015, 13:51, David Wang, Conditioning Station, Standard Operation, TM4, SiC #31, TM4 is connected at CS 007.JPG009.JPG008.JPG010.JPG
TM4 has been connected at CS. CS HV cover is installed.I made a pair of new cooling lines for TM window cooling at CS. The TM4 containment box window
cooling line is connected to the HVC spare circuit now. I checked water flow visually, and it is good. The TM4 is ready for conditioning.See attachment
for window cooling modification.
Entry  Wednesday, June 03, 2015, 13:01, Anders Mjos, Conditioning Station, Standard Operation, TM4, SiC#31, Conditioning SiC#31 SiC#31_Conditioning.docx
PNG1 connected to PNG in service cap (as per David W)
 Wednesday, June 03, 2015, 12:59: Water on
Wednesday, June 03, 2015, 13:04: Staging enabled.
Entry  Wednesday, June 03, 2015, 11:22, David Wang, Conditioning Station, Standard Operation, , , Target Hall Scheduled Activities April 07 - July 21 2015 Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
I revised the Target Hall schedule to July 21 2015. It is the time new TM2 with ZrC target started at ITW.
2015-06-04, Updated the schedule with   new PDF view. See attachments 3, 4
Entry  Tuesday, June 02, 2015, 14:39, David Wang, Conditioning Station, Standard Operation, TM4, SiC #31, TM4 and CS turbo- pumps are started . 
TM4 and CS turbo-pumps are started this afternoon. Everything is good so far.
Entry  Tuesday, June 02, 2015, 14:38, David Wang, Conditioning Station, Repair, TM4, , replace broken TM4 IG1 002.JPG006.JPG
 TM4 IG1 filament was broken during last run  at ITE.  The broken filament is replaced with a new one today when TM4 is located at CS.
2015-06-03 , Leak checked the new 25 conflat gasket today. No leak. See attachments
Entry  Tuesday, June 02, 2015, 14:32, David Wang, South Hot-Cell, Standard Operation, TM4, SiC #31, Leak check on TM4 HS water line with new SiC #31 target. at SHC 003.JPG005.JPG001.JPG
Chad and I leak checked TM4 HS water line with SiC #31 target installed. leak rate:0.0xE-9atm.cc/sec.  No leak.  The line will be helium pressurized
at CS later.
2015-06-03, helium pressure test the line at CS. 70psi 3 minutes. leak rate 0.0xE-9 atm.cc/sec. No leak.   See attachments
Entry  Tuesday, June 02, 2015, 11:54, Travis Cave, Conditioning Station, Standard Operation, TM4, SiC#31, Module moved 
TM#4 with SiC#31 has been moved from the south hot cell to the conditioning station.
Entry  Tuesday, June 02, 2015, 10:39, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#31, Electrical Check TM4_SiC31_elecchk_SHC.PDF
Electrical check on TM#4 with SiC#31. See attached PDF for details.
Entry  Tuesday, June 02, 2015, 09:43, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#31, SiC#31 installed 
Ta #45 has been removed from TM4 and SIC#31installed.
Entry  Tuesday, June 02, 2015, 06:51, David Wang, South Hot-Cell, Standard Operation, TM4, , Target Hall Scheduled Activities April 07 - June 26 2015 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target Hall schedule weekly update. All jobs are finished on time so far.
Entry  Monday, June 01, 2015, 14:24, Travis Cave, South Hot-Cell, Standard Operation, TM4, Ta#45, Electrical Check TM4_Ta45_elecchk_postbeam.PDF
Post beam electrical check on the Ta#45 target installed on TM#4. See attached PDF.
Entry  Monday, June 01, 2015, 11:23, Travis Cave, ITE, Standard Operation, TM4, Ta#45, Module moved 
TM#4 with Ta#45 has been moved from the east target station to the south hot cell.
Entry  Friday, May 29, 2015, 09:16, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, Module moved 
TM#2 with no source tray has been moved from the conditioning station to the north east silo.
Entry  Wednesday, May 27, 2015, 08:57, Travis Cave, Conditioning Station, Standard Operation, TM2, , Module moved 
TM#2 with no source tray has been moved from the south hot cell to the conditioning station.
Entry  Tuesday, May 26, 2015, 14:34, chad fisher, South Hot-Cell, Repair, TM2, , Shutter replacement Shutter.jpg
The shutter in TM2 was successfully replaced today.
New lock washer and nut were installed onto shutter and nut torqued to 120 ft lbs.
Shutter guide alignment tool was used to insure tapped shutter guide holes were concentric with thru holes in shutter side mounting panel, button
Entry  Tuesday, May 26, 2015, 11:49, Grant Minor, Assembly/Bench Test, Repair, TM2, , TM2 New Source Tray - Braze & Solder Report - 22 May 2015 6x
Hello,

For reference, I have attached a list of all solder joints in the TM2  Source Tray, and the alloys used for the most recent build (as per  ITA6144).  
Entry  Friday, May 22, 2015, 15:44, David Wang, ITW, Standard Operation, TM1, UCx12, 5 Shielding blocks have been transferred from ITE to ITW. 
5 shielding blocks have been transferred from ITE to ITW. I  checked all ITW water signals, and they are good.  ITW is configured to take proton
beam.
Entry  Wednesday, May 13, 2015, 13:55, chad fisher, South Hot-Cell, Repair, TM2, , Shutter removal TM2_20150513_131339.jpgTM2_20150513_134232.jpg
TM2 has been successfully de-shuttered.
All went pretty much according to plan except I had to remove one fastener out of the upper wiring harness (the one that has just been installed)
to allow for enough clearance to rotated the shutter guide out of the way...I shutter to think what would have happened otherwise...anyways...
Entry  Monday, May 11, 2015, 11:20, David Wang, South Hot-Cell, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - June 26 2015 6x
The schedule has some changes due to  new TM2 source tray coil cooling line leaking at test stand. Now,It is re-scheduled in such an estimation 
that TM2 source tray could be ready at teat stand by this Friday(May-15th). see attachment 1,2.
2015-05-12,  Changed  and updated the TH activity schedule according to Dons new beam schedule which is re-arranged after the coil line
ELOG V2.9.2-2455