  958   Tuesday, June 23, 2015, 14:19 chad fisherSouth Hot-CellRepairTM2 TM2 Water Block Jigs RemovedBoth halves of the water block jigs have
been removed and the module is now ready
for base vacuum leak and electrical checks.
 20150623_140917.jpg 
  957   Tuesday, June 23, 2015, 10:55 chad fisherSouth Hot-CellRepair  Left Manipulator RepairThe master wrist/tong cable has been replaced
on the left manipulator. Everything appears
to function well so far.
  
  956   Friday, June 19, 2015, 13:00 chad fisherSouth Hot-CellRepairTM2 TM2 Source Tray Install StatusLeft manipulator now broken. Master side
however, so repair can take place Monday
or Tuesday.
  
  955   Friday, June 19, 2015, 11:57 chad fisherSouth Hot-CellRepairTM2 TM2 Source Tray ProgressWindow waterline has been successfully
connected using 1 1/2 inch long non-blunt
start 1/4-28 bolts.
  
  954   Friday, June 19, 2015, 11:52 David WangITEStandard OperationTM4SiC #315 Shielding blocks have been transferred from ITW to ITE.5 shielding blocks have been transferred
from ITW to ITE. The ITE is configured to
take proton beam.
  
  953   Friday, June 19, 2015, 11:43 David WangITWRepairTM1 ITW external water leak on dump circuitThere was an external water leak in ITW
during the last beam running time. The leak
started after the shielding blocks transfer(May
 6x 
  952   Friday, June 19, 2015, 09:37 Isaac EarleSouth Hot-CellRepairTM2 TM2 Source Tray Installation - June 18, 2015 The following work was done on
June 18 2015:
- Finished cleaning and polishing
  
  951   Thursday, June 18, 2015, 08:03 chad fisherSouth Hot-CellRepairTM2 TM2 Optics Tray TransferThe TM2 optics tray has been transferred
from the source tray to the transfer fixture
in preparation for installation of the source
 20150618_075326_1.jpg 
  950   Wednesday, June 17, 2015, 14:21 chad fisherSouth Hot-CellRepairTM2 TM2 Waterblock Clean PolishFiberglass that fell out yesterday was
put back in place (as well as possible).
Cleaning took place this morning
 20150617_080236_1.jpg20150617_081538_1.jpg20150617_083830.jpg 
  949   Tuesday, June 16, 2015, 14:28 chad fisherSouth Hot-CellRepairTM2 TM2 Source Tray Installation/Water Block Sealing Surface CleanToday cleaning and polishing pads were
inserted into the hot cell.
Module side waterblock jig installation
 20150616_104240.jpg20150616_140505.jpg20150616_140506.jpg 
  948   Monday, June 15, 2015, 14:14 David WangSouth Hot-CellStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015Weekly update Target Hall schedule 2015-06-15.
See attachment 1,2
 2015-06-19, Update the schedule
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf 
  947   Monday, June 15, 2015, 10:16 chad fisherSouth Hot-CellRepairTM2 C.B. offAs per scedule TM2 containment box has
been removed.
 
 20150615_101043_1.jpg 
  946   Monday, June 15, 2015, 09:42 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule movedTM#2 is now in the south hot cell.   
  945   Friday, June 12, 2015, 13:27 David WangSouth Hot-CellStandard Operation  TM2 new source tray has been remotely transferred from TH into SHC successfully.TM2 new source tray has been remotely transferred
into SHC successfully. The transfer table
has been moved back to TH within 1 hour. 
  
  944   Friday, June 12, 2015, 07:49 chad fisherAssembly/Bench TestRepairTM2 New TM2 Source Tray Ground to HV MeasurementsAfter bending and leak checking the new
measurements from ground to HV on the TM2
source tray are:
  
  943   Thursday, June 11, 2015, 13:43 Dan McDonaldAssembly/Bench TestRepairTM2 Leak check following tweaking of cooling line gapsMaico, Chad and I conducted a leak check
on all affected lines following tweaking
of cooling line gaps. All lines pumped down
  
  942   Thursday, June 11, 2015, 13:11 chad fisherAssembly/Bench TestRepairTM2 Measurements beyween ground Plane and HV TM2 Source taryI've taken measurements between HV and
ground circuit on TM2 source tray as instructed.
At their closest points:
  
  941   Wednesday, June 10, 2015, 16:49 Grant MinorAssembly/Bench TestRepairTM2 TM2 New Source Tray - *HOLD* on installation into Hot Cell until HV approvalDon Jackson brought to my attention some
potential HV minimum spark     gap issues
with the source tray cooling lines. 
 ITA6144_RevC_markup_10Jun2015.pdfTM2_cooling_lines_too_close_GE_HS_10June2015.jpgTM2_cooling_lines_too_close_Window_MSP_10June2015.jpg 
  940   Wednesday, June 10, 2015, 13:17 David WangITEStandard OperationTM1 Target Hall Scheduled Activities April 07 - July 26 2015Weekly update the schedule after some jobs
have been finished in this week.
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp 
  939   Wednesday, June 10, 2015, 11:49 David WangITEStandard OperationTM4SiC #31TM4 has been connected in ITEDan and I connected TM4 in ITE. At this
stage, water is supplied to TM4 only. We
checked the TM4 water signals from electrical
  