  1118   Friday, November 06, 2015, 14:44 Anders MjosConditioning StationRepairTM3 O-rings replaced on service cap

O-rings were replaced on the service cap by Anders, Maico, Aurelia and Keith under work permit  I2015-11-05-5    


 

 One of the wires for the steerers had come loose and was reattached by Maico. Photo on DocuShare

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  1117   Friday, November 06, 2015, 14:36 Anders MjosConditioning StationDevelopmentTM3FEBIAD test targetTesting TM3

Friday, November 06, 2015, 14:35: Roughing

Turbos was started around 4pm. Later it was found that the manual valve for the two turbo pumps on the service cap was closed. The valve was open and pumping resumed. The roughing vacuum was high and increased into Saturday morning. The vacuum system was switched off on Saturday.


Purged MP1 using the purging function. Performance recovered. Started rouging.

Monday, November 09, 2015, 09:18: Started TP1S

Monday, November 09, 2015, 09:22: Started TP1 and TP2

Monday, November 09, 2015, 09:33: All 3 turbos at speed


Leak found on F/T for multipin connector

Tuesday, November 10, 2015, 09:53: stopped turbos

  1116   Thursday, November 05, 2015, 09:57 Travis CaveConditioning StationMaintenanceTM3no targetModule moved

TM#3 has been moved from the north west silo to the conditioning station.

  1115   Thursday, October 29, 2015, 13:59 Travis CaveSpent Target VaultStandard Operation  Filling F-308s

Five F-308s have been filled with the spent targets. The F-308s have been moved to the hall way between the north and south hot cell areas.

  1114   Friday, October 23, 2015, 11:40 Travis CaveSpent Target VaultStandard Operation ZrC #7Spent target moved

The spent ZrC#7 target has been moved from the south hot cell to the spent target vault. The target was placed in pail #129 and then placed in slot 3B of the vault, it was 157mSv/hr upon removal from the south hot cell.

Attachment 1: Vault_Storage_October_23_2015.pdf
Vault_Storage_October_23_2015.pdf Vault_Storage_October_23_2015.pdf Vault_Storage_October_23_2015.pdf Vault_Storage_October_23_2015.pdf
  1113   Friday, October 23, 2015, 11:30 chad fisherSouth Hot-CellStandard Operation ZrC#7ZrC#7 Spent Move and Febiad Coil

ZrC#7 was transfered to a spent target disposal pail today and removed from the hot cell. The "hot" end of the TM4 coil end was also disposed of in the same pail (#129)

  1112   Friday, October 23, 2015, 07:41 Dan McDonaldSpent Target VaultMaintenance  F-308's

Six F-308's where received from Nordion #6,#15,#13,#16 all contained contamination. Loose contamination was removed with some fixed contamination remaining levels are low enough to allow the transport of spent targets. flasks where serviced as per Nordion Document IS/PP 0009 F308, IS/PP 0981 F308. Flasks are now located in the north hot cell area.

  1111   Wednesday, October 21, 2015, 11:58 Anders MjosSouth Hot-CellDevelopmentTM2ZrC#7Extraction Electrode inspection

The failed extraction electrode was inspected in the hot cell this morning by Anders and Chad. The following electrical measurements were taken

  • EE on target assembly as recieved from TM after online operation. 14 Ohm
  • EE removed from target assembly and placed on conductive flat surface. ~1 G-Ohm at 1kV
  • EE installed back onto target assembly (fasteners not tightened).~ 0.8 G-Ohm at 1 kV

There was some material deposited on the EE. Some of which has fallen off - possibly during removal of the electrode from the target assembly. It seems the cause of the short was material build up between plasma electrode and extraction electrode. See photos.

The heat shield lid was removed after lunch. This revealed a broken target. The target may have broken after operation (in hot cell).

Photos are available on DocuShare

 

  1110   Wednesday, October 21, 2015, 09:49 chad fisherSouth Hot-CellRepair  Manipulator handle repair

Rebuild handle of manipulator serial 7986 (currently in the east position) and replaced broken snap ring 5555-18h on west side of the handle underneath motion switch.

  1109   Tuesday, October 20, 2015, 13:52 chad fisherSouth Hot-CellMaintenance  TM4 Febiad coil line disposal

The febiad coil line removed from TM4 has been cut into pieces small enough to be disposed of in a 5 gal pal. The line was cut with a Ridgid Model 104 manual pipe cutter (using the manipulators of course).

This pieces constitute the bulk of the field in the hot cell and will be disposed of with the next spent target.

Attachment 1: 20151020_133045.jpg
20151020_133045.jpg
Attachment 2: 20151020_134303.jpg
20151020_134303.jpg
  1108   Tuesday, October 20, 2015, 12:49 Dan McDonaldITWStandard Operation SiC#32Tm2 hook up In ITW

Lower and disconnect TM2 from crane in ITW, proceed with hooking up TM2 as per checklist with Anders. Double check flow meters and coils, reset TP1 and TP2

  1107   Tuesday, October 20, 2015, 10:18 Travis CaveITWStandard OperationTM2SiC#32Module moved

TM#2 with SiC#32 has been moved from the south hot cell to the west target station.

  1106   Monday, October 19, 2015, 15:52 Anders MjosSouth Hot-CellStandard OperationTM2SiC#32Electrical and leak check

 An electrical check was completed by Travis C and Anders M. Note ~250 kOhm between Target and 60 kV common. Leak check was done by Dan M and Chad F on HS and Window circuits. No leaks found

Attachment 1: ITW-TM2-SiC#32-HP-FEBIAD_Electrical_Check_SHC_(pre).pdf
ITW-TM2-SiC#32-HP-FEBIAD_Electrical_Check_SHC_(pre).pdf
  1105   Monday, October 19, 2015, 11:53 chad fisherSouth Hot-CellStandard OperationTM2SiC#32SiC#32 installed on TM2

SiC#32 has been installed on TM2. High current fasteners torqued to 130 in lbs.

  1104   Thursday, October 15, 2015, 14:17 chad fisherSouth Hot-CellRepairTM2 Anode Connector Install and adjustment

The TM2 containment box was removed this morning for installation of the 9 pin connector...connection.

The 9 pin connector copper tube connection was made and Anders advised on routing of the cable to the banana plug water block connection.

Short was diagnosed (short disappeared when water block was pushed slightly towards center of module) and thicker Ultem spacer installed and tested again. All good.

Attachment 1: 20151015_085914.jpg
20151015_085914.jpg
  1103   Thursday, October 15, 2015, 08:07 David WangSouth Hot-CellStandard OperationTM2no targetTM2 no target electrical check at SHC.

I did a TM2 no target electrical check at SHC this morning. A to RU at 500v  is 250K which is low.   anode- x pin is dead short to 60kv bias. RU is dead short to 60kv bias( as before).   see attachment

Attachment 1: TM2_electrical_check_2015-10-16_no_target.pdf
TM2_electrical_check_2015-10-16_no_target.pdf
  1102   Wednesday, October 14, 2015, 14:49 David WangSouth Hot-CellStandard OperationTM2 Install new high current cables to TM2

I installed a set of new high current cables for TM2 Febiad run. The top of TM2  is configured to Febiad mode. See attachments

Attachment 1: TM2_Febiad_High_current_cables_047.JPG
TM2_Febiad_High_current_cables_047.JPG
Attachment 2: TM2_Febiad_High_current_cables_048.JPG
TM2_Febiad_High_current_cables_048.JPG
Attachment 3: TM2_Febiad_High_current_cables_049.JPG
TM2_Febiad_High_current_cables_049.JPG
  1101   Wednesday, October 14, 2015, 14:03 chad fisherSouth Hot-CellStandard OperationTM2ZrC#7ZrC#7 removed

ZrC#7 has been removed from TM2. Everything looks good.

Attachment 1: 20151014_134022.jpg
20151014_134022.jpg
Attachment 2: 20151014_135127.jpg
20151014_135127.jpg
  1100   Wednesday, October 14, 2015, 12:48 David WangSouth Hot-CellStandard OperationTM2ZrC#7TM2 ZrC#7 after run electrical check at SHC.

I did an electrical check on TM2 with ZrC #7 on it. The EE is short to 60KV bias. See attachment

Attachment 1: ZrC_#7_after_run_electrical_check.pdf
ZrC_#7_after_run_electrical_check.pdf
  1099   Wednesday, October 14, 2015, 12:44 David WangITWStandard OperationTM2ZrC#7TM2 has been moved from ITW to SHC

Bill and I remotely removed TM2 from ITW to SHC. The move is smooth.