Entry  Friday, April 08, 2016, 13:16, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule 2016_winter_shut_down__target_hall_schedule.mpp2016_winter_shut_down__target_hall_schedule.pdf

Update schedule weekly .see attachment 1,2

Entry  Friday, April 08, 2016, 08:48, David Wang, ITW, Standard Operation, , , ITW water signal interlock check. 

I did a ITW water signals interlock check with ISAC opp. They are checked once a year before first beam on.

2016-04-13 Same test is done on ITE also. Everything is good.

Entry  Friday, April 08, 2016, 08:13, Anders Mjos, ITE/ITW Cooling, Maintenance, , , High Active Water Resistivity 2016-04-08_ISAC_High_Active_Water_Resistivity.png

The high active water resistivity took a long time to recover after the upgrade to the water cooling circuit. The system needed about a month (from end February to end March) to recover to nominal values. See attached plot of archiver data.

TM1 has now been connected in ITW and the water resistivity remains > 8 MOhm cm, which should allow normal operation. However, the resin is suspected to be approaching end of life. Work is ongoing to get a new replacement resin tank.

Entry  Friday, April 08, 2016, 07:13, David Wang, ITW, Standard Operation, TM1, UCx15, TM1 has been connected in ITW. 

After ITW HV test is done, TM1 has been connected to ITW. Water signals are checked in electrical room. They are good.

Entry  Friday, April 08, 2016, 07:10, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 vacuum has been connected in ITE. 

All turbo pumps are started yesterday. The pumping down is good over night.

Entry  Thursday, April 07, 2016, 09:24, Travis Cave, Conditioning Station, Maintenance, TM4, Ta#47, module moved 

TM#4 has been moved from the south hot cell to the conditioning station.

Entry  Wednesday, April 06, 2016, 14:52, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#14, No Target, Ta#47, Electrical Check TM4_elec_chk_notgt_SHC.PDFTM4_elec_chk_Ta47_SHC.PDFTM4_elec_chk_UC14_SHC_postbeam.PDF

Various electrical checks done on TM#4, one of post beam UC#14, of no target and with Ta#47. See PDFs for details.

Entry  Wednesday, April 06, 2016, 14:03, chad fisher, South Hot-Cell, Standard Operation, TM4, Ta#47, UCx#14 removed Ta#47 installed 

UCx#14 has been removed from TM4 and Ta#47 installed. No marks on 9 pin connector on UCx#14.

Entry  Wednesday, April 06, 2016, 09:37, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#14, module moved 

TM#4 with UC#14 has been moved from the east target station to the south hot cell.

Entry  Tuesday, April 05, 2016, 12:40, David Wang, ITE, Standard Operation, TM4, , I stopped ITE turbo pumps this morning 

The ITE and TM4 have been vented with Argon . TM4 vacuum system is disconnected in ITE.

Entry  Tuesday, April 05, 2016, 12:36, David Wang, ITW, Standard Operation, TM1, , TM1 vacuum system has been connected in ITW. 

 All turbo -pumps are started.

Entry  Tuesday, April 05, 2016, 09:33, Travis Cave, ITW, Standard Operation, TM1, UC#15, module moved 

TM#1 with UC#15 have been moved from the conditioning station to the west target station.

Entry  Tuesday, April 05, 2016, 07:12, David Wang, Conditioning Station, Standard Operation, TM1, UC#15, stop CS vacuum pumps. 

Stop TCS vacuum pumps . Preparing argon venting on TM1 and TCS.

7:34 AM, Disconnected TM1 at TCS, argon venting now.

Entry  Monday, April 04, 2016, 11:14, David Wang, Conditioning Station, Standard Operation, TM1, , Helium pressure test on TM1 HS line at CS 

New UCx target is installed on the module. 70psi helium,3 minutes. NO response on LD.  LD is pumped to bottom LR and LP during test.

Entry  Friday, April 01, 2016, 14:41, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 and TCS vacuum system has been connected. TCS control page white out. 

I can not start the TCS pumps due to control page white out. Control group is working on this issue.

Control group fixed the white out problem. I started all turbo-pumps. The pumping down is good so far. The TM1 IG1 is broken. I will check it on next Monday. It could be a broken filament. Then, the filament will be replaced.

Entry  Friday, April 01, 2016, 13:58, Travis Cave, Conditioning Station, Standard Operation, TM1, UC#15, module moved 

TM#1 has been moved from the conditioning station to the south hot cell, had UC#15 installed and then moved back to the conditioning station.

Entry  Friday, April 01, 2016, 11:41, Travis Cave, South Hot-Cell, Standard Operation, TM1, UC#15, Electrical Check TM1_elec_chk_UC#15_SHC.PDF

Electrical check of the target on TM#1, target in question is UC#15. See PDF for details.

Entry  Wednesday, March 30, 2016, 15:49, David Wang, Assembly/Bench Test, Repair, TM2, , TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo. 7x

On each water circuit in side the service cap, there are 4 soldering stems which two of them are inside blue nylon insulator and other two are connected to service tray. Each stem has two soldering spots. See attachment pictures for detail location. I sprayed 15 psi helium on each soldering spots on stems  for 20second on each circuit. I sprayed tons of helium inside each blue nylon.No any leak has been found during the check. The leak detector base leak rate:0.0 XE-9 atm.cc/sec, base pressure:0.0X E-4 torr. The circuit which I checked are :TA+, Ta-, Tube+, Tube-, PQ (coil 2), RU( coil1), EE, MSP, GE. The HS and window circuit are opened at this moment so they can not be checked.

Entry  Wednesday, March 30, 2016, 11:00, Travis Cave, Conditioning Station, Standard Operation, TM1, no target, Electrical Check TM1_elec_chk_notgt.PDF

The results of the TM#1 electrical check from the 29th of March 2016

Entry  Wednesday, March 30, 2016, 08:40, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp

update the schedule according to changes.See attachment1, 2.