Entry  Friday, March 18, 2016, 13:13, Travis Cave, Conditioning Station, Standard Operation, TM2, SiC#32, Electrical Check TM2_SiC32_postbeam.PDFTM2_elec_chk_notgt_CS.PDF

Electrical checks of the TM#2 with the old SiC#32 and without the target. See attached PDFs.

Entry  Friday, March 18, 2016, 11:43, chad fisher, South Hot-Cell, Standard Operation, , , SiC#32 dissection 20160318_105519_1.jpg20160318_105311.jpg20160318_105248.jpg20160318_105428.jpg

SiC#32 has been open for inspection.

Entry  Friday, March 18, 2016, 09:42, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum sysytem has been connected at TCS 

TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far.

Entry  Friday, March 18, 2016, 09:34, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Sep) Target_Hall_shedule_130_Apr_to_Sep_2016.xlsxTarget_Hall_shedule_130_Apr_to_Sep_2016.pdf

I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for  beam schedule 130 is under construction, and will be posted later.

Entry  Friday, March 18, 2016, 08:34, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, module moved 

TM#2 with no target has been moved to the conditioning station from the south hot cell.

Entry  Thursday, March 17, 2016, 14:57, David Wang, South Hot-Cell, Repair, TM2, , TM2 first round leak check in SHC 

Chad and I finished the first round check on Tm2 water lines. The lines and spots checked are: Target oven + and - (front side braze joints) , Tube heater+and -(front side braze joints and water blocks), coil2 and coil 1(front side braze joints and area close to water blocks),. No leak has been found on all above of them.  The last, we checked   the GE which has the biggest leak so far. The leak detector base leak rate only can get to 4XE-9 atm.cc/sec. Chad sprayed helium very close to GE water block, and I got a quick response on leak detector. The leak rate climbed from 4Xe-9 atm.cc/sec to 1.4 atm.cc/sec. We confirmed the GE is leaking now. The exact location need to be pinpointed later once the containment box is out after the module is back to SHC. The module will be moved to TCS tomorrow morning and pressurized again there. Anders will use RGA to monitor the helium response during the check.  

Entry  Wednesday, March 16, 2016, 14:23, chad fisher, South Hot-Cell, Standard Operation, TM2, SiC#32, SiC#32 removal Target Module Inspection 20160316_141127.jpg20160316_141146.jpg

SiC#32 has been removed from TM2. Quick inspection shows some troubling discoloration on the water cooled connection blocks of C and D as well as the left target heater A.

As for the target, both legs are broken and is has the normal "charge up" marks on the 9 pin connector.

Entry  Wednesday, March 16, 2016, 09:20, Travis Cave, ITE, Standard Operation, TM2, SiC#32, module moved 

TM#2 with SiC#32 has been moved from the west station to the south hot cell.

Entry  Monday, March 14, 2016, 15:22, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp

update schedule according to change. See attachment 1,2

 

Entry  Monday, March 14, 2016, 11:24, David Wang, ITE/ITW Cooling, Maintenance, , , HALCW resin tank filter cartridges are changed today 002.JPG003.JPG006.JPG

Two of resin tank filter cartridges(supply and return) are changed today. Old cartridges and bagged and tagged. The contact field on them are 650usv/hr. The new cartridges are fiber-glass, Triumf store item. After replacement, the field on contact with the filter case are about 10 usv/hr. But the field on contact with top resin tank  has been increased from 45usv/hr  to 225 usv/hr

 The flow rate is relatively stable before and after change. See attachment

Entry  Friday, March 04, 2016, 13:58, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule 8x

Update Schedule according to changes.See attachment1, 2.

 Re-post it after some minor correction See attachment 3,4.

Update schedule according changes. See attachments 5,6

 update schedule according to changes. See attachment 7,8

Entry  Friday, March 04, 2016, 12:34, David Wang, ITE, Standard Operation, TM4, , TM4 ITE annual leak check 

Dan and I finished TM4 and ITE annual leak check on primary and secondary vacuum vessel. We found one leak on a KF25  blank off which is located on the top of the service cap. It is a low E-7 atm.cc/sec range leak. But, it is very close to turbo-pumps so ITE IG1 and other gauges are not affected by it very much. It is an easy fix. TheKF -25 center ring on the blank off  will be replaced  after vent . It be will leak checked again at CS after replacement.  That is only leak we found on TM4 and ITE primary and secondary vessel air to vaccum leak check.

Dan and I also finished the helium pressure test on all TM4 using water circuits. 70 psi helium. base LR 0.0xE-9 atm.cc/sec. All of them are leak free. No any response has been found on leak detector during test.

Entry  Wednesday, March 02, 2016, 10:04, David Wang, ITW, Standard Operation, TM2, , Leak check on ITW and TM2. 

Dan and I leak checked TM2 and ITW primary vacuum vessel. It was found a 1X E-7 atm.cc/sec leak on top T flange seal between TM2 and dump module in first time check. But it is not a repeatable leak. I checked the same spot and around area two more times with increased helium volume.It did not show up again. The first response could  be a helium drift to dry scroll pump. I will check it again later. The primar vacuum vessel on ITW and TM2 are leak free. 

Dan and I found a small  leak on ITW dump module  top flange seal. The leak detector got a response  to 7xE-9 atm.cc/sec when I spray the helium to west side of dump module top flange. We tested again, and got same result. The o-ring which seals ITW dump module top flange is deteriorating. It need to be replaced at a proper time. This is the only air to vacuum leak we confirm so far on primary and secondary vacuum vessel on TM2 and ITW. The module and station no other air to vacuum leak.

The TM2 water lines helium pressure tested started in ITW. The helium pressure 70psi. The result so far is: Window: good, GE: huge leak directly shoot over E-7 atm.cc/sec( need to be confirmed tomorrow), HS: good, EE: good, MSP: tiny leak which is response to 3-4xE-9 atm.cc/sec. Coil 1 : small leak which is response to 1.3XE-8 atm.cc/sec. Tomorrow, We will test the rest water lines on TM2which are TA+, TA-, Tube+, Tube-, and coil 2. And We will confirm the GE huge leak at the last.

Finished the helium pressure test on TM2 water line.70 psi helium, The result of the rests 5 circuits: coil 1: leak 7.2xE-8atm.cc/sec,Ta(+): small leak 1.7XE-8 atm.cc/sec, Ta(-) small leak 8.7xE-9atm.cc/sec,Tube(-) 1.5 x E-8 atm.cc/sec. Tube(+)small leak 3.7xE-8 atm.cc/sec.    We repeated the helium pressure test on GE. There is a huge leak on TM2 GE circuit. The leak detector shoot up to E-7  atm.cc/sec right after the helium was applied.It went up to E-6 range in less than 1 minutes.

 

 

Entry  Wednesday, March 02, 2016, 09:51, David Wang, ITW, Standard Operation, TM2, , all water lines on TM2 and TM4 are purged. 

All water lines on TM2 and TM4 are purged for upcoming water lines helium pressure test.

Entry  Thursday, February 25, 2016, 09:29, David Wang, ITE, Standard Operation, TM4, , TM4 has been disconnected in ITE. 

TM4 has been disconnect in ITE(except  vacuum lines). The ITE vacuum system is still operating.

Entry  Thursday, February 25, 2016, 09:27, David Wang, ITW, Standard Operation, TM2, , TM2 has been disconnected in ITW 

TM2 has been disconnected in ITW (except vacuum lines). The vacuum system is still operating.

Entry  Thursday, February 25, 2016, 06:52, David Wang, Conditioning Station, Standard Operation, , , stop CS vacuum pumps. 

I stopped the conditioning station vacuum pumps. The CS is still under vacuum without venting.

Entry  Thursday, February 25, 2016, 06:48, David Wang, ITE, Standard Operation, , , 4 Shielding blocks have been transferred from ITE to block storage area. 

Dan and I transferred 4 shielding blocks from ITE to block storage area. The ITE pit is opened now.

Entry  Friday, February 19, 2016, 06:58, maicodallavalle, Spent Target Vault, Maintenance, , , F-308's serviced/loaded/ bolts torqued 

Five F-308's were loaded with spent ISAC targets. All five F-308's were serviced two weeks ago. All bolts were torqued and security  cables were installed  for shipment.

Entry  Friday, February 12, 2016, 13:00, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule  6x

2016 Winter shut down target hall schedule. See attachments1,2.

 update the schedule weekly. Everything is on time so far. see attachment 3,4.

Update the schedule according to beam new beam schedule and target process. see attachment 5,6