  159   Tuesday, August 07, 2012, 14:06 David WangITWRepair  ITW TP4S has been replaced
 

 Normal
  0

 
   
  
  162   Tuesday, August 14, 2012, 14:27 David WangITWStandard OperationTM1UCxTM1connection in ITWConnected TM1 in ITW,started 6 turbo pumps,
and finished TM1 water interlock check .
Every thing is good so far.
  
  163   Monday, August 20, 2012, 12:28 David WangITWStandard OperationTM1 I moved 5 shielding blocks from ITE to ITW,I moved 5 shielding blocks from ITE 
to ITW.ITW is configured to take proton beam
now.
  
  164   Thursday, August 23, 2012, 07:34 David WangITWRepair  Replaced broken air lines on ITW HARP5B cylinder.Prob guys replaced broken air lines on
ITW HARP 5B Cylinder.Several shielding blocks
had been moved out to make the cylinder accessible.
  
  165   Thursday, August 30, 2012, 13:57 David WangITEStandard OperationTM4 Disconnected TM4 in ITE.I disconnected TM 4 in ITE on AUG 29th
morning.The vacuum lines stay untouched and
they will be disconnected on SEP 04th.
  
  168   Tuesday, September 04, 2012, 14:34 David WangSouth Hot-CellStandard OperationTM4NiO #1TM4 heat shield circuit leak check with NiO#1 targetChad and i did a leak check on TM4 heat
shield circuit with new NiO#1 target installed.
It took about 40 mins(much longer than usual)
  
  172   Friday, September 07, 2012, 08:54 David WangConditioning StationStandard OperationTM4NiO #1TM4 NiO #1 target heat shield helium pressure check is done.leak detector pumped down to 0.0xE-9 atm.cc/sec,
and 0.0xE-4 torr. All high vacuum gauge readings
at CS and TM4 are at low -6 range from 2.2xE-6torr
  
  175   Wednesday, September 12, 2012, 07:00 David WangITEStandard OperationTM4NiO #1ITM4 in ITE connected and pumping downTM4 had been connected in ITE. Six turbo
pump had been started . thepumpming diwn
is very good so far. The water interlock
  
  176   Wednesday, September 12, 2012, 11:59 David WangITWStandard OperationTM1UCxTM1 disconnected in ITWI removed 5 shielding blocks from ITW to
block storage area, and disconnected TM1
in ITW. After UCx run,  the radioactive
  
  181   Tuesday, September 18, 2012, 13:41 David WangSouth Hot-CellStandard OperationTM1Nb#7leak check heat shield circuitChad  and i did a leak check on TM1 heat
shield circuit with new Nb#7 target  installed.
It took about 5 mins pump down  the circuit
  
  186   Thursday, September 20, 2012, 09:16 David WangConditioning StationStandard OperationTM1Nb#7TM1 Nb#7 target heat shield helium pressure check is done.Leak detector pumped down to base LR1.3xE-9
atm.cc/sec, and BP 8xE-3 torr. All  high
vacuum gauge readings at CS and TM1 are at
  
  188   Tuesday, September 25, 2012, 14:33 David WangITWStandard OperationTM1Nb#7TM1connected in ITWTM 1 is in ITW now. All connections are
done. The turbo pumps had been started  this
afternoon. The vacuum looks good so far.
  
  189   Thursday, September 27, 2012, 09:13 David WangITERepairTM4 ITE MSP water circuit flow wheel had been replaced ITE MSP water circuit flow wheel was replaced
yesterday due to poor performance. 
  
  190   Tuesday, October 02, 2012, 11:47 David WangITWStandard OperationTM1Nb#7I moved 5 shielding blocks from ITE to ITW.5 shielding blocks have been moved from
ITE to ITW. ITW is configured to take proton
beam now.
  
  191   Thursday, October 04, 2012, 11:06 David WangConditioning StationRepair  Replace conditioning station scroll pump in target hallGrant and I replaced the conditioning station
broken  srcoll pump with a refurbished
scroll pump which is supplied by vacuum group.
  
  192   Tuesday, October 09, 2012, 10:35 David WangITEStandard OperationTM4NiO #1Disconnected TM4 in ITE.I disconnected TM4 in ITE this morning.
The heat shield circuit has been purged with
air.
  
  196   Tuesday, October 16, 2012, 07:14 David WangConditioning StationStandard OperationTM4UCX#5TM4 heat shield helium pressure test and electrical check at CSTM4 heat shield helium pressure test and
electrical check were done  at CS 
last week. The results are good. NO leak
  
  199   Wednesday, October 31, 2012, 11:24 David WangITEStandard OperationTM4 Transfer five shielding blocks from ITW to ITE.Bevan and I transferred five shielding
blocks from ITW to ITE. ITE is ready for
taking proton beam.
  
  204   Tuesday, November 06, 2012, 12:08 David WangITWStandard OperationTM1Nb#7TM1 disconnected in ITWBevan and I disconnected TM1 in ITW this
morning. The TM1 was moved to south hot cell
later.   
  
  208   Wednesday, November 07, 2012, 11:09 David WangSouth Hot-CellStandard OperationTM1TiC TM1 heat shield circuit leak check with TiC target at hot cellChad and i did a leak check on TM1(Lp-TiC)
heat shield water circuit at south hot cell.
There is no leak had been found on it. The
  