1278
|
Friday, July 08, 2016, 08:20 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 has been connected at TCS | I connected TM2 to TCS and started water
system. |
|
1281
|
Tuesday, July 12, 2016, 09:59 |
Travis Cave | ITW | Standard Operation | TM2 | SiC#33 | module moved | TM#2 with SiC#33 has been moved from the
conditioning station to the west target station. |
|
1282
|
Tuesday, July 12, 2016, 12:40 |
David Wang | ITW | Standard Operation | TM2 | | TM2 has been connected in ITW | All turbo-pumps are started. Everything
is good so far. |
|
1285
|
Thursday, July 14, 2016, 10:54 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall schedule for beam schedule 130 (Apr- Oct, 2016) | Update TH schedule 130 according to mini-shut
down change.See attachment 1,2,3,4 |
   |
1327
|
Tuesday, August 23, 2016, 10:39 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | SiC#33 | module moved | TM#3 with SiC#33 has been moved from the
west station to the south hot cell. |
|
1328
|
Tuesday, August 23, 2016, 13:31 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | SiC#33 | SiC#33 Removed | SiC#33 has been removed from TM2. |
|
1329
|
Wednesday, August 24, 2016, 09:17 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | | Ta#49 | Ta#49 has been installed on TM2 and tested.
All high current fasteners torqued to 130
in lbs. |
|
1331
|
Wednesday, August 24, 2016, 10:41 |
David Wang | ITW | Standard Operation | TM2 | | TM2 was disconnected in ITW yesterday. | TM2 was disconnected in ITW yesterday and
moved to SHC. |
|
1332
|
Wednesday, August 24, 2016, 10:44 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | SHC, TM2 leak check on HS line. | Chad and I leak checked Tm2 Hs line with
new target installed. Base LR 0.0Xe-9 atm.cc/sec.
No leak has been found. This line will be |
|
1333
|
Wednesday, August 24, 2016, 10:45 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 vacuum system has been connected at TCS | Start of roughing now. |
|
1334
|
Wednesday, August 24, 2016, 11:06 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | Ta#49 | module moved and electrical check | TM#2 with Ta#49 has had its electrical
check and was moved to the conditioning station.
see the attached pdf for the electrical check |
|
1336
|
Wednesday, August 24, 2016, 14:42 |
Anders Mjos | Conditioning Station | Standard Operation | TM2 | Ta#49 | Conditioning | Wednesday, August 24, 2016, 14:42: RGA
on
Wednesday, August 24, 2016, 20:27: |
 |
1337
|
Thursday, August 25, 2016, 08:36 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 HS water lline | I did a helium pressure test on TM2 HS
water line at TCS. Leak detector base leak
rate only could get to 1.8x e-8 atm.cc/sec |
|
1338
|
Thursday, August 25, 2016, 08:43 |
David Wang | Conditioning Station | Standard Operation | TM2 | | All TM2 connections to TCS are done. | The HV cover is installed. The Faraday
cage at B2 level is locked also.The TCS and
TM2 are still pumping down. Everything is |
|
1341
|
Monday, August 29, 2016, 13:34 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 has been disconnected at TCS | I stopped TCS water pumps and vacuum pumps
also. TM2 and TCS will be vented tomorrow
morning. |
|
1342
|
Tuesday, August 30, 2016, 10:35 |
Travis Cave | ITW | Standard Operation | TM2 | Ta#49 | module moved | TM#2 with Ta#49 has been moved to the west
target station from the conditioning station. |
|
1343
|
Tuesday, August 30, 2016, 13:17 |
David Wang | ITW | Standard Operation | TM2 | | TM2 has been connected at ITW | ITW turbo pumps have been
started. |
|
1344
|
Tuesday, September 06, 2016, 10:05 |
David Wang | ITW | Standard Operation | TM2 | | 5 Shielding blocks have been transferred from ITE to ITW. | 5shielding blocks have been transferred
from ITE to ITE. ITW is configured to take
proton beam. |
|
1369
|
Tuesday, October 11, 2016, 10:36 |
Travis Cave | ITW | Standard Operation | TM2 | Ta#49 | module moved | TM#2 with Ta#49 has been moved from the
west target station to the south hot cell. |
|
1370
|
Wednesday, October 12, 2016, 10:00 |
David Wang | ITW | Standard Operation | TM2 | | TM2 was disconnected at ITW | TM2 was disconnected at ITW. 3 water circuits
in ITW gave been looped to keep 75 GPM water
flow to ITW. HS line was purged at HS. RPG |
|