  RH-ISAC, Page 67 of 141  Not logged in ELOG logo
ID Date Author Category Type Moduledown Target/Number Subject
  1246   Wednesday, May 25, 2016, 14:08 David WangITWStandard OperationTM2Ta#48TM2 has been connected in ITW

TM2 has been connected in ITW by Dan.M and David.W. All turbo-pumps have been started. Everything is good so fine.

  1271   Wednesday, July 06, 2016, 07:03 David WangITWStandard OperationTM2 TM2 was connected in ITW.

TM2 was disconnected in ITW and moved to SHC.

  1273   Wednesday, July 06, 2016, 09:16 chad fisherSouth Hot-CellStandard OperationTM2SiC#33Ta#48 removed SiC#33 installed

Ta#48 has been removed from TM2 and SiC#33 installed.

  1274   Wednesday, July 06, 2016, 09:59 Travis CaveSouth Hot-CellStandard OperationTM2Ta#48 and SiC#33Electrical Check

Electrical check done on TM#2 with Ta#48, no target and SiC#33 the short on the coils to 60kV is still present it is on the R-U coil line. See attached PDFs for details.

Attachment 1: TM2_elechk_Ta48_SHC_postbeam.PDF
TM2_elechk_Ta48_SHC_postbeam.PDF
Attachment 2: TM2_elechk_SiC33_SHC.PDF
TM2_elechk_SiC33_SHC.PDF
Attachment 3: TM2_elechk_notgt_SHC.PDF
TM2_elechk_notgt_SHC.PDF
  1275   Wednesday, July 06, 2016, 13:38 Travis CaveConditioning StationStandard OperationTM2SiC#33module moved

TM#2 with SiC#33 has been moved from the south hot cell to the conditioning station.

  1276   Wednesday, July 06, 2016, 14:25 David WangConditioning StationStandard OperationTM2 TCS and TM2 turbo-pumps have been started.

The TCS and TM2 are pumping down.

  1277   Wednesday, July 06, 2016, 15:23 Anders MjosConditioning StationStandard OperationTM2SiC#33Conditioning SiC#33

 Wednesday, July 06, 2016, 15:23: RGA on. IGs on


Friday, July 08, 2016, 17:07: Stopped cooling system due to a problem with the chiller. Will continue with HV conditioning on Monday.


Monday, July 11, 2016, 08:08: Cooling system started. Operating CP1 manually to control temperature

Monday, July 11, 2016, 09:38: BIAS / EL / EE to 10 / 5 / 1 kV

Monday, July 11, 2016, 09:41: BIAS / EL / EE to 20 / 10 / 1.5 kV

Monday, July 11, 2016, 09:47: BIAS / EL / EE to 30 / 15 / 1.5 kV

Monday, July 11, 2016, 10:01: BIAS / EL / EE to 40 / 20 / 2.0 kV - one spark at 40 kV

Monday, July 11, 2016, 10:38: BIAS / EL / EE to 45 / 22.5 / 2.0 kV - conditioning from 40 kV

Monday, July 11, 2016, 10:40: BIAS / EL / EE to 45 / 22.5 / 2.3 kV

Monday, July 11, 2016, 12:21 : No sparks for the last 60 min.

Monday, July 11, 2016, 12:21: BIAS / EL / EE off to investigate TGHT / TBHT PS problem (power surge this morning)

Monday, July 11, 2016, 13:07: Power cycled TGHT / TBHT PS. Alarm cleared. Tested both to 10 A

Attachment 1: SiC#33.docx
Attachment 2: TCS-2016-07-06-SiC#33.rga
  1278   Friday, July 08, 2016, 08:20 David WangConditioning StationStandard OperationTM2 TM2 has been connected at TCS

I connected TM2 to TCS and started water system.

  1281   Tuesday, July 12, 2016, 09:59 Travis CaveITWStandard OperationTM2SiC#33module moved

TM#2 with SiC#33 has been moved from the conditioning station to the west target station.

  1282   Tuesday, July 12, 2016, 12:40 David WangITWStandard OperationTM2 TM2 has been connected in ITW

All turbo-pumps are started. Everything is good so far.

  1285   Thursday, July 14, 2016, 10:54 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)

Update TH schedule 130 according to mini-shut down change.See attachment 1,2,3,4

Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.pdf
Target_Hall_shedule_130_Apr_to_Sep.pdf
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.mpp
Attachment 3: Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
Target_Hall_shedule_130_Apr_to_Sep_2016.pdf Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
Attachment 4: Target_Hall_shedule_129_Sep_to_Dec.xlsx
  1327   Tuesday, August 23, 2016, 10:39 Travis CaveSouth Hot-CellStandard OperationTM2SiC#33module moved

TM#3 with SiC#33 has been moved from the west station to the south hot cell.

  1328   Tuesday, August 23, 2016, 13:31 chad fisherSouth Hot-CellStandard OperationTM2SiC#33SiC#33 Removed

SiC#33 has been removed from TM2.

  1329   Wednesday, August 24, 2016, 09:17 chad fisherSouth Hot-CellStandard OperationTM2 Ta#49

Ta#49 has been installed on TM2 and tested. All high current fasteners torqued to 130 in lbs.

  1331   Wednesday, August 24, 2016, 10:41 David WangITWStandard OperationTM2 TM2 was disconnected in ITW yesterday.

TM2 was disconnected in ITW yesterday and moved to SHC.

  1332   Wednesday, August 24, 2016, 10:44 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.

Chad and I leak checked Tm2 Hs line with new target installed. Base LR 0.0Xe-9 atm.cc/sec.   No leak has been found. This line will be helium pressured at TCS later.

  1333   Wednesday, August 24, 2016, 10:45 David WangConditioning StationStandard OperationTM2 TM2 vacuum system has been connected at TCS

Start of roughing now.

  1334   Wednesday, August 24, 2016, 11:06 Travis CaveSouth Hot-CellStandard OperationTM2Ta#49module moved and electrical check

TM#2 with Ta#49 has had its electrical check and was moved to the conditioning station. see the attached pdf for the electrical check details.

The electrical check has been edited to reflect that well the original has been just not the PDF.

Attachment 1: TM2_elechk_SiC34_SHC.PDF
TM2_elechk_SiC34_SHC.PDF
  1336   Wednesday, August 24, 2016, 14:42 Anders MjosConditioning StationStandard OperationTM2Ta#49Conditioning

Wednesday, August 24, 2016, 14:42: RGA on

Wednesday, August 24, 2016, 20:27: IG2 and IG1S on. Checked on water system.


Conditioning by ISAC operations. Water flow tripped power supplies after a few hours of conditioning at 580 / 230 A and 30 kV. See operations e-log for details.

Attachment 1: TCS-2016-08-24_Ta#49.rga
Attachment 2: Ta#49.docx
  1337   Thursday, August 25, 2016, 08:36 David WangConditioning StationStandard OperationTM2 Helium pressure test on TM2 HS water lline

I did a helium pressure test on TM2 HS water line at TCS. Leak detector base leak rate only could get to 1.8x e-8 atm.cc/sec at this moment. Applied 5 minutes 70psi helium on it. No leak has been found at this level. I connected water to this circuit after the test for weekend TM2 conditioning at TCS.

I will do another helium pressure test after the conditioning. The LD base leak rate should be 0.0Xe-9 atm.cc/sec at that time.

2016-08-29: LD Base leak rate 0.0xe-9atm.cc/sec.TM2 HS line helium pressure check again after conditioning. 70psi helium 5minutes. no response on LD. HS line is perfectly sealed.