  1267   Tuesday, June 21, 2016, 13:47 Travis Cave/ Dan McDonaldSpent Target VaultRepair  Spent Target Vault Door

The spent target vault door does not open or close. The emergency door closing did have to be used to close the door as it was locked in an open position, the door stopped just off the open override limit. The door was closed and the spent target that was being assayed was placed into the mini storage. The problem with the door appears to be related to the motor itself, as all the controls to the motor appear to be in working order. Also it was noticed on the emergency door closing winch the wire rope has a kink in it from sitting in open position for so long this can cause the wire rope to jump from the pulleys.

 

6/27/2016  Dan McDonald. Replacement motor was ordered from Beaver Industries Friday the 24th received this morning the 27th. Once received Travis wired the motor to its proper operating orientation. Once the motor was wired  it was  set it up and plugged it in to test rotation and control function, at this point we disconnected the motor and re installed it to the gear box. Ran three open close sequences to ensure all was well. In the case of the emergency cable system a plan is being developed to correct the cable slack and kinking problem. We went ahead and ordered a spare  vault motor which is located in the RH Machine Shop 

  1269   Tuesday, June 28, 2016, 14:42 Travis CaveSpent Target VaultStandard Operation ManySpent target assay.

The spent target assay were finally started or re-started today. Four targets were done today.

June 29 2016 another four targets were done today.

June 30 2016 all targets have assayed and measured. see the attached PDFs for the results.

  1270   Thursday, June 30, 2016, 13:33 Dan McDonaldSpent Target VaultMaintenance  F308's

The five spent target F308  flasks where gone through in accordance with Nordion guidelines, the sixth spare is remains in the Hot Cell area. All flasks where in reasonable shape with two needing weld repairs on the pallets. I replaced all the 3/4" pallet to flask fasteners with new Grade 8 bolts nut and washer combo. Flasks have been moved into the Hot Cell area awaiting movement into the Target Hall.

  1280   Monday, July 11, 2016, 10:59 Travis CaveSpent Target VaultStandard Operation Ta#48Spent Target move

The spent Ta#48 was moved from the south hot cell to the spent target vault. I was placed in pail 139 and is in spot 6C in the vault. It was 201mSv/hr when measured at the hot cell. See the attached PDF for the latest results.

  1305   Thursday, August 04, 2016, 08:56 Travis CaveSpent Target VaultStandard Operation UC#16Spent Target move

The spent UC #16 have been moved from the south hot cell to the storage vault see attached PDF for details.

  1340   Thursday, August 25, 2016, 14:25 Travis CaveSpent Target VaultStandard Operation SiC#33Spent Target move

SiC#33 was placed into pail #141 which in turn was placed into slot 2B of the vault. I was 295mS/hr upon removal from the south hot cell.

  1362   Monday, September 26, 2016, 13:59 Travis CaveSpent Target VaultStandard Operation UC#17Spent Target move

The spent UC#17 has been moved from the south hot cell to the spent target vault. See the attached pdf for details.

  1373   Thursday, October 20, 2016, 10:45 Travis CaveSpent Target VaultStandard Operation Ta#49Spent Target move

Ta#49 has been removed from the south hot cell and placed in the storage vault. It is in pail 146 and in spot 6A.

  1392   Monday, November 07, 2016, 10:35 Travis CaveSpent Target VaultStandard Operation SiC#34Spent Target move

Spent SiC#34 was moved on the 3rd of November and  placed in the spent target vault. See attached pdf for details.

  1407   Friday, November 25, 2016, 09:04 Travis CaveSpent Target VaultStandard Operation SiC#35Spent Target move

On November 24th 2016 the spent SiC#35 was moved from the south hot cell to the spent target vault. see attached pdf for details.

  1452   Thursday, March 16, 2017, 10:32 David WangSpent Target VaultRepairTM4 TM4 and its silo rust photos

I watched rust on TM4 and its silo. Most of rust are on est side of module and silo. See attachments

  1454   Tuesday, March 21, 2017, 10:05 Travis CaveSpent Target VaultStandard Operation  Spent target assay.

All target in the ISAC spent target vault have been either assayed or had their fields measured or both.

  1461   Friday, March 24, 2017, 11:12 Keith C NgSpent Target VaultStandard Operation  2A window transfer

Transfered the 2A window from the ISAC Storage Vault to the Cyclotron Vault Tunnel Storage area. RPG storage form attached.

  1462   Friday, March 24, 2017, 11:19 Keith C NgSpent Target VaultStandard Operation 2A3 windowWindow now in vault

Travis Cave wrote:

The 2A3 window now has a lid, and lift yolk on it and it has been installed in the spent target vault in spot 2A. The lid is a normal unmodified and has no sealant on it.

The pail containing window was transferred from the Storage Vault to the Cyclotron Vault Tunnel Storage 2017 Mar 24. It was placed in a brick bunker along the north wall and marked with item #1434. RPG storage form is attached.

Highest field measured at 0.5 m was 3000 uSv/h with an estimate of 4000 uSv/h on contact with the pail. Pail exterior was not contaminated. See attached storage form for details.

 

  1463   Friday, March 24, 2017, 13:21 Travis CaveSpent Target VaultStandard Operation 2A window2A window has been removed from the vault.

2A window has been removed from the vault and moved over the cyclotron vault tunnels.  Attached is the updated storage vault list.

  1465   Monday, March 27, 2017, 12:55 David WangSpent Target VaultRepair  S/W silo rust clean up

Rust on S/W silo and cover plate stored at silo area are cleaned up.

  1519   Tuesday, May 02, 2017, 13:49 Travis CaveSpent Target VaultStandard Operation  Spent Targets moved

Five spent targets have been moved from the target storage vault to the mini vault in preparation for Thursdays loading of the F-308s. See attached for the list of targets in the mini vault, and the new status of the storage vault.

  1528   Monday, May 08, 2017, 14:46 Travis CaveSpent Target VaultMaintenance  Mini Vault Door

 Mini Vault Door as some difficulty over coming a small hump on its track. To open the door one needs to give the door  a slight tug while it is opening to over come this hump.

  1542   Thursday, May 18, 2017, 10:41 Travis CaveSpent Target VaultStandard Operation UC#19Spent Target move

The spent UC#19 target has been moved from the south hot cell into the spent target storage. It was placed in pail #145 and put in tray one spot C. See attached PDF for all vault details.

  1556   Monday, June 12, 2017, 13:51 Travis CaveSpent Target VaultStandard Operation  Spent Target move

The spent Ta#51 target has been moved from the south hot cell to the spent target vault. It was placed in pail#149 and put in spot 8B of the vault.