2723
|
Tuesday, November 26, 2024, 14:52 |
Aaron Tam | South Hot-Cell | Standard Operation | TM3 | UCx#47 | UC#47 LP-SIS w/ gas Install | November 26, 2024 - Aaron Tam
Handover from TPO and inspection
Completed
Some |
6x |
|
2724
|
Thursday, November 28, 2024, 16:13 |
Aaron Tam | South Hot-Cell | Standard Operation | | TiC#9 Parasitics | TiC#9 Parasitics Leak Check and removal from hotcell | November 27th, 2024 - Aaron Tam with
Farran & David
Parasitic Assembly Leak Check (Aaron, |
|
|
2726
|
Tuesday, December 03, 2024, 10:51 |
Adam Newsome | South Hot-Cell | Standard Operation | TM2 | | TM2 move - ITE to SHC | TM2 was moved from ITE to SHC with Ta#68
target. During the move, a railing was lightly
bumped by the corner of the module - no obvious |
|
|
2727
|
Tuesday, December 03, 2024, 12:28 |
Adam Newsome | South Hot-Cell | Standard Operation | TM2 | | TM3 move - TCS to ITE | TM3 was moved with UCx#47 from TCS to ITE.
The move was smooth. |
|
|
2728
|
Tuesday, December 03, 2024, 15:53 |
Aaron Tam | South Hot-Cell | Standard Operation | TM2 | Ta#68 | Ta#68 Removal | Note: Ta#68 had a difficult
install. See E-log ID# 2698 for more info
First look: |
22x |
|
2731
|
Wednesday, December 04, 2024, 10:40 |
Adam Newsome | South Hot-Cell | Standard Operation | TM2 | | TM2 move - SHC to silo | TM2 was remotely moved from the South Hot
Cell to SW Silo. Reading at SHC = 89.8 mSv/h.
The move was smooth. |
|
|
2732
|
Wednesday, December 04, 2024, 14:30 |
Aaron Tam | South Hot-Cell | Standard Operation | | Ta#68 | Ta#68 PIE | Abstract:
This target has seen some irregular
beam patterns |
32x |
|
2733
|
Thursday, December 05, 2024, 11:43 |
Aaron Tam | South Hot-Cell | Standard Operation | | Ta#68 | Pail loading - Ta#68 & Others into Pail#300 | December 5, 2024 - Aaron Tam w/ help from
Chad, Peter and Adam at the Crane
Hot Cell Prep: |
|
|
2743
|
Wednesday, January 08, 2025, 07:37 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UCx#46 | UCx#46 removal | UCx#46 removed from TM4 and placed into
a pail back-filled with argon. Nothing visually
unusual; no issues. |
|
|
2748
|
Tuesday, January 14, 2025, 10:00 |
David Wang | South Hot-Cell | Standard Operation | TM3 | UCx#47 | after operation electrical check, Tm3 UCx 47 | TM3 UCx#47 after operation electrical check
is done at SHC. The result is normal. See
attachment. |
|
|
1857
|
Friday, January 11, 2019, 13:59 |
Isaac Earle | Safe Module Parking | Development | | | SMP motor selection decision | SMP drivetrain design work is currently
underway. Alejandro has selected a
suitable 1200:1 reducer which will give a |
|
|
1865
|
Monday, February 11, 2019, 10:26 |
Isaac Earle | Safe Module Parking | Development | | | SMP shield box and vacuum vessel moved to Target Hall | On February 8th the SMP shield
box (IRH1675) and the vacuum vessel (IRH1806)
were both raised from a horizontal to vertical |
6x |
|
1873
|
Thursday, February 21, 2019, 15:10 |
Isaac Earle | Safe Module Parking | Development | | | Seismic requirements for SMP | Dragan Mitrovic, TRIUMF structural engineer,
was consulted earlier this week regarding
seismic requirements for the SMP assembly. |
|
|
1903
|
Monday, April 01, 2019, 14:56 |
Isaac Earle | Safe Module Parking | Development | | | SMP shield box and vacuum vessel installed in final location | Last week drilling of the additional
required holes in the SMP shield box was
completed in the Target Hall. This |
|
|
1904
|
Thursday, April 04, 2019, 14:49 |
Isaac Earle | Safe Module Parking | Development | | | SMP vacuum vessel support roller friction check | With the SMP vacuum vessel now installed
inside the shield box, a test was performed
to measure the torque required to rotate |
|
|
1921
|
Wednesday, May 15, 2019, 16:06 |
Isaac Earle | Safe Module Parking | Development | | | SMP module support flange installed and leak checked | The SMP module support flange sub-assembly
(IRH1755) was installed today according to
drawing IRH1683. Dow Corning 111 sealing |
|
|
1925
|
Friday, May 17, 2019, 16:46 |
Adam Newsome | Safe Module Parking | Development | | | SMP Controls Installation Update |
The following controls-related |
|
|
1944
|
Thursday, June 20, 2019, 15:09 |
Isaac Earle | Safe Module Parking | Development | | | SMP motor wiring inspected by electrician | The AC wiring for the SMP motor was inspected
by Randy Boehm (TRIUMF electrician) as recommended
by Franco Mammarella (TRIUMF electrical engineer). |
|
|
1946
|
Thursday, July 04, 2019, 08:57 |
Isaac Earle | Safe Module Parking | Development | | | SMP vacuum system installed | July 3:
- Assembled exhaust line flexible
hose and fittings as per ISK0529 Rev D then |
|
|
1955
|
Friday, July 26, 2019, 15:43 |
Isaac Earle | Safe Module Parking | Development | | | SMP vacuum control system completed | The SMP vacuum control system has
been wired and setup to be controlled from
EPICS. Backing valve control (SMP:BV1) |
|