1250
|
Thursday, June 02, 2016, 18:04 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | 5K mega test on TM3 |
David Wang wrote: |
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment.
|
See attachment for sparking signs of the water lines mentioned above (Coil and Ground Electrode lines) in TM3 Source Tray. |
1251
|
Friday, June 03, 2016, 11:35 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module moved | TM#3 has been moved back to the north east silo. |
1252
|
Friday, June 03, 2016, 16:04 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | 5K mega test on TM3 |
Aurelia Laxdal wrote: |
David Wang wrote: |
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment.
|
See attachment for sparking signs of the water lines mentioned above (Coil and Ground Electrode lines) in TM3 Source Tray.
|
PLEASE NOTE: the resistance values for A and B on David's attachment are not correct since these measurements were done after Chad removed the target and the heat-shield bracket was moved, so consequently the water lines were not at their nominal locations. Once they were back in plac,e David took another measurement and the resistance values for A and B showed also 3,000 MOhm (as it was for most of the lines). The only lines that still showed a low resistance were the Coil lines. |
1284
|
Wednesday, July 13, 2016, 08:47 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module moved | TM#3 has been moved from the north east silo to the conditioning station. |
1287
|
Monday, July 18, 2016, 13:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module moved | TM#3 is now in the south hot cell. |
1288
|
Monday, July 18, 2016, 14:14 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 leak checked at TCS | Last Friday July-15, TM3 was leak checked at TCS. All air to vacuum seals on service cap are good. Helium pressure test on TM3 water lines(except GE, HS, and Window) were done. Leak detector has no response at 0.0xE-9 atm.cc/sec. They are leak free. |
1289
|
Tuesday, July 19, 2016, 14:35 |
Aurelia Laxdal | Conditioning Station | Repair | TM3 | | TM3 leak checked at TCS |
David Wang wrote: |
Last Friday July-15, TM3 was leak checked at TCS. All air to vacuum seals on service cap are good. Helium pressure test on TM3 water lines(except GE, HS, and Window) were done. Leak detector has no response at 0.0xE-9 atm.cc/sec. They are leak free.
|
Friday July 15: did HV tests (with no target installed and with the anode wire removed ). <br>
TM3 went up to 22.5kV. At this voltage it started sparking. The EL was kept at 1/2 with respect to the HV BIAS. <br>
Also HV tests were done while the EL was kept at zero V. In this case, the EL voltage was once in a while spiking up (up to 4kV). <br>
During sparking we saw responses in the vacuum. Checked the Service Cap (with the HV Cover) in the Target Hall: we couldn't hear/see sparks there. <br>
The HV was turned off in the same day, after 5:30pm. |
1290
|
Friday, July 22, 2016, 10:57 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 has been moved and connected at TCS | I started vacuum system.
I started TCS water system. The chiller does not work properly still. But, It will not affect the TM3 HV conditioning. HV cover is installed on TM3 in TH. The module is ready for HV conditioning. |
1291
|
Monday, July 25, 2016, 08:15 |
Anders Mjos | Conditioning Station | Repair | TM3 | | HV Test | Monday, July 25, 2016, 08:14: Enabled staging for chiller
Monday, July 25, 2016, 08:33: Disabled staging. Fault 2. Staging does not work at this point.
Monday, July 25, 2016, 08:34: Running CP1 manually to cool down water.
Monday, July 25, 2016, 09:15: Bias current limiting at 150 V. Investigating short.
Monday, July 25, 2016, 09:51: EE cable was shorting the BIAS on the TCS side.
Monday, July 25, 2016, 09:57: BIAS/ / EL at 20 / 10 kV
Monday, July 25, 2016, 10:08: Sparking at 24 kV. Lowered to 22 kV
Monday, July 25, 2016, 10:44: BIAS at 25 kV
Monday, July 25, 2016, 11:00: Sparking at 25.5 kV. Lowered to 25 kV
Monday, July 25, 2016, 12:03: 25.5 kV. No sparking for 10 min. Lower to 20 kV for lunch break.
Monday, July 25, 2016, 12:51: 26 kV
Monday, July 25, 2016, 13:00: Sparking at 27.3 kV. Lowered to 27 kV. EL at 14 kV
Monday, July 25, 2016, 13:04: More sparking. Lowered to 25 kV
Monday, July 25, 2016, 13:39: 25 kV
Monday, July 25, 2016, 14:21: A spark tripped the PS on water resistivity
Monday, July 25, 2016, 14:31: 25 kV
Monday, July 25, 2016, 15:34: ~20 sparks for the last 60 min
Monday, July 25, 2016, 16:28: ~10 sparks for the last 60 min. BIAS an EL off
Monday, July 25, 2016, 16:36: Stopped water cooling system.
Tuesday, July 26, 2016, 08:20: Started water cooling system.
Tuesday, July 26, 2016, 08:24: Ran CP1 manually for 3 min. Enabled staging.
Tuesday, July 26, 2016, 08:31: BIAS / EL at 25 / 0 kV
Tuesday, July 26, 2016, 08:39: EL float to 300 V. Set to 500 V
Tuesday, July 26, 2016, 08:45: BIAS to 25.5 kV
Tuesday, July 26, 2016, 09:07: 26 kV
Tuesday, July 26, 2016, 09:12: Lost contact with EPICS. Scheduled maintenance
Tuesday, July 26, 2016, 10:26: 6 sparks for the last 60 min
Tuesday, July 26, 2016, 10:33: BIAS to 27 kV
Tuesday, July 26, 2016, 10:43: Sparking at 27.8 kV. Lowered to 23 kV
Tuesday, July 26, 2016, 10:51: BIAS back at 27 kV. A spark tripped the BIAS on water resistivity
Tuesday, July 26, 2016, 11:08: BIAS at 27 kV
Tuesday, July 26, 2016, 11:22: BIAS at 28 kV
Tuesday, July 26, 2016, 11:42: BIAS at 27 kV after trip due to water resistivity (spark)
Tuesday, July 26, 2016, 12:00: BIAS / EL off for lunch break
Tuesday, July 26, 2016, 14:10: EL to 10 kV
Tuesday, July 26, 2016, 14:14: El to 20 kV
Tuesday, July 26, 2016, 14:20: EL to 25 kV
Tuesday, July 26, 2016, 14:27: First spark at 27.6 kV
Tuesday, July 26, 2016, 14:29: EL to 28 kV (BIAS at 0 kV)
Tuesday, July 26, 2016, 14:43: RGA on
Tuesday, July 26, 2016, 14:49: No sparking for 20 min
Tuesday, July 26, 2016, 16:02: No sparks for 90 min.
Tuesday, July 26, 2016, 16:06: PS and water off.
Wednesday, July 27, 2016, 09:14: BIAS at 24 kV
Wednesday, July 27, 2016, 09:19: Lowered to 20 kV due to sparking
Wednesday, July 27, 2016, 09:28: BIAS at 22 kV
Wednesday, July 27, 2016, 15:30: BIAS and water off
Thursday, July 28, 2016, 08:43: RGA off |
1293
|
Thursday, July 28, 2016, 11:27 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module moved | TM#3 with no target has been moved from the conditioning station to the NE silo. |
1312
|
Wednesday, August 10, 2016, 09:44 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module moved | TM#3 has been moved from the north east silo to the conditioning station. |
1316
|
Thursday, August 11, 2016, 10:37 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 service tray cover plate ITA2108 has been removed. | Requested by Aurelia, and approved by Friedhelm, TM3 service tray cover plate ITA2108 has been remove out of the module. The plated is checked for active and contamination after removal. Then,It is double bagged, sealed , tagged, and placed downstairs in TH between south wall and green block . The ram contact reading on the plate is about 10 usv/hr. We will do anther TM3 HV test at TCS without this cover plate. |
1318
|
Friday, August 12, 2016, 10:59 |
Anders Mjos | Conditioning Station | Development | TM3 | | HV Test with Service Chase Panel removed | Water cooling is performed manually with CP1. RGA is ON since yesterday. EE is not connected and in conditioning mode.
Friday, August 12, 2016, 10:43: BIAS at 10 kV, EL at 0.5 kV. IG1 at 1.8E-6 T
Friday, August 12, 2016, 11:04: BIAS at 20 kV
Friday, August 12, 2016, 11:10: Sparking at 21 kV
Friday, August 12, 2016, 11:29: BIAS at 22 kV. Many small sparks/current excursions.
Friday, August 12, 2016, 11:32 : BIAS at 23 kV
Friday, August 12, 2016, 11:37: BIAS at 24 kV
Friday, August 12, 2016, 11:43: BIAS at 25 kV. Heavy sparking. Lowered to 24 kV to reduce spark rate.
Friday, August 12, 2016, 11:52: Increased sparking rate. Lowered to 23 kV.
Friday, August 12, 2016, 12:05: Lowered to 20 kV
Friday, August 12, 2016, 12:21: Back to 23 kV
Friday, August 12, 2016, 12:28: Heavy sparking between 23 and 24 kV. Lowered to 22 kV
Friday, August 12, 2016, 12:29: More sparking. Lowered to 21 kV.
Friday, August 12, 2016, 13:02: Increased back up to ~25 kV while Aurelia was listening for sparks in the Target Hall.
Friday, August 12, 2016, 13:03: EL to 10 kV
Friday, August 12, 2016, 13:06: BIAS / EL to 23 / 12.5 kV
Friday, August 12, 2016, 13:34: Repeated sparking at 24.5 kV. Ramping down
Friday, August 12, 2016, 15:33: Stopped water package. RGA off |
1322
|
Tuesday, August 16, 2016, 12:35 |
David Wang | Conditioning Station | Repair | TM3 | | CS vacuum pumps have been stopped | The TCS is venting now. The TM3 blue insulator replacement job will be started soon. |
1325
|
Thursday, August 18, 2016, 14:19 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module moved | TM#3 is now back in the the north east silo. |
1346
|
Wednesday, September 07, 2016, 11:44 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module moved | TM#3 has been moved from the NE Silo to the conditioning station. |
1347
|
Thursday, September 08, 2016, 16:28 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 blue insulators have been replaced. | All TM3 blue insulators except Gas,EL, and 60 KV common on top of the module have been replaced with new designed insulators. The new blue insulator for gas line need to be modified to fit for the bent on the gas line. EL, and 60KV common blue insulators were replaced during last time TM3 refurbishment so they are relative new, and not replaced this time. All seals related to the blue insulators are changed to new seals. The o- r-ing surfaces for o-ring 221 inside the new insulators are rougher than old parts. The module top need to be leak checked. |
1348
|
Thursday, September 08, 2016, 16:30 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 vacuum system have been connected at TCS. | start of roughing now.
start of TCS and TM3 turbo-pumps. Everything is good so far. |
1349
|
Monday, September 12, 2016, 09:25 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 leak checked at TCS | After blue insulators replacement, TM3 service cap are leak checked. LD base leak rate 0.0xe-9 atm.cc/sec. I sprayed lots helium on all blue insulator seals. No leak has been found. Double checked them again, and got same result. All other seals on top of TM3 also have been checked. They are leak free. OVEN, TUBE, MSP, COIL, and EE water lines are pressurized with 70 psi helium for 3minutes each. They are good also. |
1350
|
Tuesday, September 13, 2016, 13:52 |
Anders Mjos | Conditioning Station | Standard Operation | TM3 | | HV Test with new insulators on Service Cap (vacuum to air) | Tuesday, September 12, 2016, 10:00: RGA on
Tuesday, September 13, 2016, 13:52: Source on
Tuesday, September 13, 2016, 13:55: BIAS / EL at 10 / 5 kV
Tuesday, September 13, 2016, 13:59: BIAS / EL at 18 / 9 kV
Tuesday, September 13, 2016, 14:06: BIAS / EL at 20 / 10 kV. Minor sparking
Tuesday, September 13, 2016, 14:25: Sparking at about 1 spark/min for the last 10 min
Tuesday, September 13, 2016, 15:38: ~10 sparks for the last 60 min.
Tuesday, September 13, 2016, 15:41: BIAS / EL 22 / 11 kV
Tuesday, September 13, 2016, 15:57: Heavy sparking at 24 kV. Lowered to 21 kV. EL at 12.5 kV
Tuesday, September 13, 2016, 16:00: BIAS / EL at 22 / 12.5 kV
Tuesday, September 13, 2016, 16:05: Trip on resistivity caused by spark
Tuesday, September 13, 2016, 16:07: BIAS / EL at 10 / 5 kV
Tuesday, September 13, 2016, 16:14: BIAS / EL at 20 / 10 kV
Tuesday, September 13, 2016, 16:25: BIAS / EL at 22 / 11 kV
Tuesday, September 13, 2016, 17:00: Sparking at about 1 spark/min for the last 30 min
Tuesday, September 13, 2016, 17:02: Source off.
Wednesday, September 14, 2016, 08:22: BIAS / EL at 20 / 10 kV
Wednesday, September 14, 2016, 08:33: BIAS / EL at 22 / 11 kV
Wednesday, September 14, 2016, 08:35: Trip on resistivity caused by spark
Wednesday, September 14, 2016, 08:38: BIAS / EL at 20 / 10 kV
Wednesday, September 14, 2016, 08:41: BIAS / EL at 21.5 / 11 kV
Wednesday, September 14, 2016, 08:45: BIAS / EL at 22 / 11 kV
Wednesday, September 14, 2016, 09:06: Sparking at about 1 spark/min for the last 20 min
Wednesday, September 14, 2016, 10:17: Sparking rate somewhat reduced. BIAS / EL at 23 / 11 kV
Wednesday, September 14, 2016, 10:23: BIAS / EL at 24 / 12 kV
Wednesday, September 14, 2016, 10:31: BIAS / EL at 25 / 12 kV.
Wednesday, September 14, 2016, 10:32: Trip on resistivity caused by spark
Wednesday, September 14, 2016, 10:36: BIAS / EL at 20 / 10 kV
Wednesday, September 14, 2016, 10:40: BIAS / EL at 23 / 12 kV
Wednesday, September 14, 2016, 10:51: BIAS / EL at 24 / 12 kV
Wednesday, September 14, 2016, 10:57: BIAS / EL at 25 / 12 kV
Wednesday, September 14, 2016, 11:01: Heavy sparking at 25 kV (>15 /min). Trip on resistivity caused by spark
Wednesday, September 14, 2016, 11:10: RGA off. |
|