758
|
Wednesday, October 08, 2014, 09:39 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 has been moved from the North West
Silo to the conditioning station. |
|
759
|
Friday, October 10, 2014, 10:47 |
David Wang | Conditioning Station | Development | TM3 | | TM3 has been connected in CS | TM3 has been connected in CS. All water
supplies are bypassed theTM3 on the top of
the service cap. TM3 TP2 was difficult to |
|
764
|
Tuesday, October 14, 2014, 17:19 |
Anders Mjos | Conditioning Station | Standard Operation | TM3 | No target | High Voltage Conditioning | Wednesday, October 14, 2014
The BIAS voltage was brought
up between 1:30pm and 5pm. Sparks tripped |
|
768
|
Monday, October 20, 2014, 08:59 |
David Wang | Conditioning Station | Development | TM3 | | Started TCS water system. | I started TCS water system this morning
to check if the chillers work properly. |
|
769
|
Monday, October 20, 2014, 09:13 |
David Wang | Conditioning Station | Development | TM3 | | TM3 TP2 failed | TM3 TP2 stopped working this morning at
4:00 AM. I tried to start it but failed.
On normal start mode , It could not pass |
|
773
|
Wednesday, October 22, 2014, 09:41 |
David Wang | Conditioning Station | Development | TM3 | | TM3 has been disconnected at CS. | TM3 has been disconnected at CS. It is
vented and ready to move. |
|
784
|
Thursday, November 06, 2014, 13:43 |
David Wang | Conditioning Station | Development | TM3 | | CS vacuum system has been connected to TM3. | CS vacuum system has been connected
to TM3 for control system test(Dave.Morris). |
|
788
|
Monday, November 17, 2014, 11:38 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target has been moved from
the conditioning station to the north west
silo. |
|
1087
|
Wednesday, September 30, 2015, 08:50 |
Travis Cave | South Hot-Cell | Maintenance | TM3 | no target | Module moved | TM#3 is in the south hot cell it was moved
from the north west silo. |
|
1088
|
Wednesday, September 30, 2015, 11:14 |
Travis Cave | South Hot-Cell | Repair | TM3 | no target | Electrical Check | TM#3 electrical check at the south hot
cell, no target, all value are done at 1000Volts.
See the attached PDF for the results. |
|
1095
|
Tuesday, October 06, 2015, 21:12 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | TM3 service cap inspection in target hall | David Wang and I did the service cap inspection
in target hall: see WP I2015-10-06-10.<br>
Signs of sparking were seen underneath |
|
1096
|
Thursday, October 08, 2015, 14:08 |
David Wang | South Hot-Cell | Standard Operation | TM3 | Dummy target febiad. | TM3 has been moved from SHC to NW silo | Bill and I moved TM3 from SHC to NW silo
with a dummy febiad target installed on it.
The move is smooth. |
|
1116
|
Thursday, November 05, 2015, 09:57 |
Travis Cave | Conditioning Station | Maintenance | TM3 | no target | Module moved | TM#3 has been moved from the north west
silo to the conditioning station. |
|
1117
|
Friday, November 06, 2015, 14:36 |
Anders Mjos | Conditioning Station | Development | TM3 | FEBIAD test target | Testing TM3 | Friday, November 06, 2015, 14:35: Roughing
Turbos was started around 4pm. Later
it was found that the manual valve for the |
|
1118
|
Friday, November 06, 2015, 14:44 |
Anders Mjos | Conditioning Station | Repair | TM3 | | O-rings replaced on service cap | O-rings were replaced on the service cap
by Anders, Maico, Aurelia and Keith under
work permit I2015-11-05-5 |
|
1119
|
Monday, November 09, 2015, 16:47 |
Anders Mjos | Conditioning Station | Maintenance | TM3 | FEBIAD Test Target | Leak check of Service Cap | Service cap leak checked this afternoon.
Found multiple leaks of 10E-8 to 10E-7 range.
Connected to the backing line with IG1 at |
|
1120
|
Tuesday, November 10, 2015, 10:23 |
Anders Mjos | Conditioning Station | Maintenance | TM3 | | Air to vacuum leak on service cap | Conducted a more thorough leak check this
morning with Edi. He found a leak on the
base of the blue F/T insulator for |
|
1121
|
Tuesday, November 10, 2015, 16:53 |
Anders Mjos | Conditioning Station | Development | TM3 | FEBIAD test target | Testing TM3 | Tuesday, November 10, 2015, 16:53: Roughing
Tuesday, November 10, 2015, 18:24:
TP1S started |
|
1122
|
Thursday, November 12, 2015, 10:18 |
Anders Mjos | Conditioning Station | Maintenance | TM3 | | Air to vacuum leak on service cap |
|
|
1123
|
Thursday, November 12, 2015, 13:25 |
Anders Mjos | Conditioning Station | Standard Operation | TM3 | FEBIAD Test Target | Electrical check and leak check | Target to Anode and target to Common showed
~ 500 kOhm values. No leaks above 3E-9 atm-cc/s
seen. See attached. |
|