ID Date Author Categorydown Type Module Target/Number Subject
  1709   Thursday, May 03, 2018, 13:26 Anders MjosSouth Hot-CellRepairTM4 EZL short troubleshooting

Yesterday Aaron, Isaac and Anders inspected the EZL connection from the service chase to the optics tray using the goose neck camera in SHC. No issues or shorts could be identified. Containment box was not removed.

Today David and Anders opened up two panels on the service cap and inspected the EZL connection. No issues or shorts could be identified. Photos available on DocuShare.

Next step will likely be to remove the containment box and inspect the optics tray.

  1711   Friday, May 04, 2018, 15:46 Anders MjosSouth Hot-CellRepairTM4 EZL short troubleshooting

Anders Mjos wrote:

Yesterday Aaron, Isaac and Anders inspected the EZL connection from the service chase to the optics tray using the goose neck camera in SHC. No issues or shorts could be identified. Containment box was not removed.

Today David and Anders opened up two panels on the service cap and inspected the EZL connection. No issues or shorts could be identified. Photos available on DocuShare.

Next step will likely be to remove the containment box and inspect the optics tray.

The containment box was removed yesterday. One of the main insulators on the source tray had cracked at the rear close to the bolt to the source tray mounting plate (see photos using link above)

Troubleshooting continued this morning with disconnection of the optics tray from the module. The banana plug copper tube connection was removed form the optics tray side. With the connection removed, the measurement showed open line on top of the module indicating that the problem is on the optics tray

  1719   Wednesday, May 23, 2018, 09:48 Travis CaveSouth Hot-CellStandard OperationTM4no targetModule move

 TM#4 with no target and no containment box has been moved from the conditioning station to the south hot cell.

  1720   Wednesday, May 23, 2018, 10:40 chad fisherSouth Hot-CellRepairTM4 Optics Tray Removal

The optics tray has been removed from TM4.

 

 

Attachment 1: 20180523_103405.jpg
20180523_103405.jpg
Attachment 2: 20180523_103435.jpg
20180523_103435.jpg
Attachment 3: 20180523_103440.jpg
20180523_103440.jpg
  1722   Thursday, May 24, 2018, 14:04 Travis CaveSouth Hot-CellStandard OperationTM4no targetModules moved

 TM#4 has been moved from the south hot cell to the east target station, and TM#2 has been moved from the south silo to the south hot cell.

  1724   Friday, May 25, 2018, 11:41 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move

TM#2 has been moved from the south hot cell to the conditioning station.

  1728   Thursday, May 31, 2018, 14:22 chad fisherSouth Hot-CellRepairTM4 Loop and beam shield

Tray with loop and beam shield has been inserted into the hot cell to be installed on TM4 .

  1729   Monday, June 04, 2018, 13:27 chad fisherSouth Hot-CellRepairTM4 Window Loop and Shield

The tray with window waterline loop and EF Shield has been installed into TM4.

Attachment 1: jhgf.jpg
jhgf.jpg
  1730   Thursday, June 07, 2018, 11:33 Travis CaveSouth Hot-CellStandard OperationTM4UC#22Electrical Check

 The results of TM#4 with UC#22 electrical check. See attached PDF.

Attachment 1: TM4_UC22_Electrical_Check_South_Hot_Cell.pdf
TM4_UC22_Electrical_Check_South_Hot_Cell.pdf
  1733   Friday, June 08, 2018, 11:36 chad fisherSouth Hot-CellRepairTM2 TM2 Source Tray Removal Progress

The containment box has been removed from TM2, the Enzel lens and steerers disconnected and optics tray removal has commenced.

Attachment 1: TM2_06082018.jpg
TM2_06082018.jpg
  1734   Friday, June 08, 2018, 14:24 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move

 TM#2 has been moved from the conditioning station to the south hot cell.

  1735   Monday, June 11, 2018, 11:30 chad fisherSouth Hot-CellRepairTM2 TM2 containment box on

Tm2 containment box has been re-installed onto TM2.

  1736   Tuesday, June 12, 2018, 11:26 chad fisherSouth Hot-CellRepairTM2 TM4 Optics Tray

I have "slung" the TM4 optics tray in preparation for its removal.

Attachment 1: fh.jpg
fh.jpg
  1739   Friday, June 22, 2018, 13:59 chad fisherSouth Hot-CellRepair  Soth Hot Cell Fields

Field measurements have been taken to determine the level before entry for repair of manipulators.

Field on contact at manipulator is 560 uSv/h, and at approximately 1/2 meter at table surface 920 uSv\h.

  1740   Monday, June 25, 2018, 11:31 chad fisherSouth Hot-CellStandard Operation  Fields at Al cover

The shield door has been opened and fields measured at 77 uSv/h on contact at the AL. panel.

  1742   Tuesday, June 26, 2018, 08:56 chad fisherSouth Hot-CellStandard Operation  South Hot Cell Fields

hot items have been moved and shielded as much as possible. Field at left manipulator has been reduced from 560 uSv/h to 85 uSv/h.

  1743   Wednesday, June 27, 2018, 14:56 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move

 TM2 has been moved from the silo to the south hot cell.

  1744   Friday, June 29, 2018, 10:12 chad fisherSouth Hot-CellMaintenance  Manipulator Tong Cable Replacement

Tuesday, June 26 the broken tong cable was replaced on the west manipulator in the south hot cell. Wednesday the tong cable was preemptively replaced on the east manipulator of the south hot cell.

  1745   Friday, June 29, 2018, 10:15 chad fisherSouth Hot-CellStandard OperationTM2 TM2 work and target install

On Thursday, June 29th the containment box of TM2 was removed and the optics tray re-installed and reconnected. The box was then re-installed.

Friday the window waterlines were leak checked, Nb target installed (with new fasteners, high current torqued to 130 in*lbs) target leak and electrical checked and containment box cover installed with new fasteners.

  1746   Friday, June 29, 2018, 10:27 chad fisherSouth Hot-CellMaintenance  South Hot Cell Filter Change

At the end of manipulator repair Thursday the ventilation pre-filter in the hot cell was changed. Old filter remains in the hot cell until such time as it can be removed.